Wire fence type 2 unit price, Washington
Low bidders on WSDOT contracts carried a median of $8.00 per LF for wire fence type 2, from 19 DEC 2001 to 01 FEB 2023, across 54 low bids. Half of all 356 bids fell between $4.00 and $14.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Latest letting
- 01 FEB 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 1 | 1 | $11.50 | 11 | $11.00 |
| 2002 | 1 | 1 | $3.45 | 4 | $3.23 |
| 2004 | 3 | 3 | $7.25 | 14 | $7.00 |
| 2005 | 6 | 5 | $4.00 | 27 | $3.40 |
| 2006 | 2 | 2 | $9.50 | 9 | $11.00 |
| 2007 | 5 | 5 | $4.48 | 45 | $4.71 |
| 2008 | 4 | 4 | $3.45 | 25 | $3.50 |
| 2010 | 5 | 5 | $4.00 | 32 | $3.98 |
| 2011 | 2 | 2 | $6.62 | 17 | $4.15 |
| 2012 | 3 | 3 | $5.20 | 30 | $5.00 |
| 2013 | 3 | 3 | $15.00 | 19 | $12.50 |
| 2014 | 1 | 1 | $8.00 | 12 | $9.00 |
| 2015 | 1 | 1 | $8.00 | 6 | $7.00 |
| 2016 | 1 | 1 | $14.00 | 11 | $12.50 |
| 2017 | 3 | 3 | $16.50 | 22 | $20.00 |
| 2018 | 6 | 6 | $15.00 | 25 | $24.50 |
| 2019 | 2 | 2 | $14.25 | 11 | $12.63 |
| 2020 | 2 | 2 | $13.00 | 13 | $15.00 |
| 2021 | 1 | 1 | $7.25 | 8 | $7.95 |
| 2022 | 2 | 2 | $28.50 | 11 | $25.00 |
| 2023 | 1 | 1 | $21.00 | 4 | $20.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| SCR region | 17 | $5.00 | 137 | $5.00 |
| NWR region | 11 | $6.90 | 78 | $5.95 |
| ER region | 10 | $8.12 | 46 | $6.00 |
| OR region | 6 | $16.50 | 39 | $18.00 |
| NCR region | 6 | $6.75 | 29 | $6.00 |
| SWR region | 4 | $10.25 | 27 | $11.75 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 55 to 240 | 13 | $19.00 |
| 255 to 823 | 14 | $9.98 |
| 862 to 3,790 | 13 | $4.00 |
| 4,080 to 85,294 | 14 | $4.12 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 FEB 2023 | 009928 | OR region | 862 | $21.00 | $20.50 | $34.00 | 4 | TUCCI & SONS, INC. | WSDOT |
| 24 FEB 2022 | 009769 | NWR region | 109 | $38.00 | $39.00 | $20.00 | 4 | GRANITE CONSTRUCTION COMPANY | WSDOT |
| 09 FEB 2022 | 009763 | OR region | 140 | $19.00 | $20.00 | $25.00 | 7 | KRAEMER NORTH AMERICA, LLC. | WSDOT |
| 03 FEB 2021 | 009625 | SCR region | 6,032 | $7.25 | $7.95 | $9.00 | 8 | SCARSELLA BROS., INC. | WSDOT |
| 08 APR 2020 | 009535 | OR region | 372 | $14.00 | $14.00 | $10.00 | 5 | ROGNLIN'S, INC. | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 401 | $12.00 | $15.00 | $16.00 | 8 | INTERWEST CONSTRUCTION, INC. | WSDOT |
| 17 APR 2019 | 009418 | SCR region | 90 | $16.00 | $29.00 | $25.00 | 3 | ASCORP, INC. DBA DEBCO | WSDOT |
| 10 APR 2019 | 009419 | SWR region | 823 | $12.49 | $12.25 | $15.00 | 8 | FARLINE BRIDGE, INCORPORATED | WSDOT |
| 19 DEC 2018 | 009349 | ER region | 72 | $20.00 | $20.70 | $31.25 | 4 | CENTRAL WASHINGTON ASPHALT, IN | WSDOT |
| 25 APR 2018 | 009258 | ER region | 210 | $37.00 | $37.50 | $9.00 | 2 | CPM DEVELOPMENT CORPORATION | WSDOT |
| 07 MAR 2018 | 009214 | SCR region | 320 | $33.00 | $31.50 | $12.00 | 6 | GRAHAM CONTRACTING, LTD. | WSDOT |
| 22 FEB 2018 | 009211 | OR region | 1,080 | $10.00 | $10.00 | $5.73 | 6 | ROGNLIN'S, INC. | WSDOT |
| 22 FEB 2018 | 009210 | ER region | 100 | $10.00 | $25.00 | $40.00 | 3 | N.A. DEGERSTROM, INC. | WSDOT |
| 18 JAN 2018 | 009192 | NWR region | 255 | $10.00 | $15.00 | $20.00 | 4 | NORTHWEST CONSTRUCTION, INC. | WSDOT |
| 15 FEB 2017 | 009026 | SCR region | 634 | $9.00 | $9.00 | $10.00 | 3 | KIEWIT INFRASTRUCTURE WEST CO. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.