Removing Headwalls unit price, Alabama

Low bidders on ALDOT contracts carried a median of $545.29 per EACH for item 206E000, removing headwalls, over the 24 months to 28 AUG 2026, across 56 low bids. Half of all 222 bids fell between $401.70 and $997.92.

Owner
Alabama DOT
Item
206E000
Unit
EACH
Latest letting
28 AUG 2026
$545.29Low bidder's median, per EACH
$600.00Median of all bids, per EACH
56Contracts in the window

By year of letting

Removing Headwalls, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20222222$626.5260$750.00
20233333$712.7594$792.26
20243434$584.05128$633.59
20252929$560.71111$624.88
20261010$546.4546$568.87
Removing Headwalls, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Removing Headwalls, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
03016$829.4028$934.54
09025$311.7426$352.34
08043$250.0016$550.00
05024$1,097.8815$1,000.00
09014$369.8314$369.83
07023$477.6510$486.90
01033$275.0010$419.43
03053$810.179$564.16
Removing Headwalls, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Removing Headwalls, ALDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 214$775.00
2 to 314$390.00
4 to 1014$564.93
11 to 5414$460.00
Removing Headwalls, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Removing Headwalls
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 20262026082801104023$800.00$987.854VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
31 JUL 202620260731001030138$800.00$741.336IKAROS, LLCALDOT
31 JUL 202620260731017040211$642.90$668.754ALABAMA GRADING & EXCAVATION, LLC.ALDOT
31 JUL 20262026073102509022$450.00$389.846ARRINGTON CURB & EXCAVATION, INC.ALDOT
26 JUN 202620260626035090219$128.81$316.625WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 202620260529001060315$1,030.46$960.033APAC-ALABAMA, INC.ALDOT
24 APR 20262026042400706046$750.00$480.005S. A. GRAHAM COMPANY, INC.ALDOT
24 APR 20262026042404406047$316.30$356.003WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
30 JAN 202620260130001010518$230.00$659.026ROGERS GROUP, INC.ALDOT
30 JAN 202620260130025010231$290.00$267.854ROGERS GROUP, INC.ALDOT
05 DEC 20252025120500202012$845.07$589.953MILLER & MILLER, INC.ALDOT
05 DEC 20252025120500309012$214.77$449.884MCINNIS CONSTRUCTION, LLCALDOT
05 DEC 20252025120501507021$903.28$699.724WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
05 DEC 20252025120502101033$253.30$300.003WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
07 NOV 20252025110705708042$250.00$460.958PINE CITY CONTRACTING, LLCALDOT
Latest ALDOT contracts carrying Removing Headwalls

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy