Removing Curb unit price, Alabama

Low bidders on ALDOT contracts carried a median of $15.50 per LF for item 206D002, removing curb, over the 24 months to 28 AUG 2026, across 40 low bids. Half of all 148 bids fell between $14.10 and $27.01.

Owner
Alabama DOT
Item
206D002
Unit
LF
Latest letting
28 AUG 2026
$15.50Low bidder's median, per LF
$20.00Median of all bids, per LF
40Contracts in the window

By year of letting

Removing Curb, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20222424$13.9365$21.00
20232323$20.5071$25.00
20242121$14.0073$15.61
20251717$15.0765$20.00
20261010$15.5938$20.00
Removing Curb, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Removing Curb, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
03019$20.0037$20.00
05025$10.0024$18.15
09023$15.6113$19.41
Removing Curb, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Removing Curb, ALDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
6 to 13610$19.00
142 to 36610$15.29
444 to 82110$13.78
824 to 13,03310$13.36
Removing Curb, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Removing Curb
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 2026202608280300202188$15.70$19.008ROGERS GROUP, INC.ALDOT
26 JUN 2026202606260350902517$9.67$17.005WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 2026202605290230301821$20.43$28.044WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 2026202605290400704227$6.00$15.333APAC-ALABAMA, INC.ALDOT
24 APR 2026202604240190502581$10.00$11.802IKAROS, LLCALDOT
24 APR 2026202604240320301667$27.03$22.933APAC-ALABAMA, INC.ALDOT
27 FEB 202620260227001030145$18.00$29.755GILLESPIE CONSTRUCTION, LLCALDOT
27 FEB 202620260227038050413$81.78$81.783DUNN CONSTRUCTION COMPANY, INC.ALDOT
30 JAN 202620260130025010276$7.40$15.744ROGERS GROUP, INC.ALDOT
30 JAN 20262026013003104012,981$15.49$15.491GARY INGRAM GRADING & PAVING, INC.ALDOT
05 DEC 20252025120500202012,237$16.90$13.523MILLER & MILLER, INC.ALDOT
05 DEC 20252025120505903026$100.00$94.005BULLS CONSTRUCTION GROUP, LLCALDOT
05 DEC 2025202512050650502191$15.07$20.007GFC CONSTRUCTION, INC.ALDOT
07 NOV 2025202511070060301366$20.00$20.003BULLS CONSTRUCTION GROUP, LLCALDOT
26 SEP 2025202509260100301444$15.00$17.502SOUTH DADE AIR CONDITIONING & REFRIGERATION,ALDOT
Latest ALDOT contracts carrying Removing Curb

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy