Removing Guardrail unit price, Alabama

Low bidders on ALDOT contracts carried a median of $3.67 per LF for item 206D001, removing guardrail, over the 24 months to 28 AUG 2026, across 176 low bids. Half of all 482 bids fell between $3.15 and $6.00.

Owner
Alabama DOT
Item
206D001
Unit
LF
Latest letting
28 AUG 2026
$3.67Low bidder's median, per LF
$4.29Median of all bids, per LF
176Contracts in the window

By year of letting

Removing Guardrail, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20226666$5.37149$5.71
20237474$4.42181$4.50
20249797$3.53257$3.37
20258282$3.51223$4.37
20265252$3.46147$3.83
Removing Guardrail, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Removing Guardrail, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
030115$5.5553$5.88
050214$4.9943$4.73
01046$3.2324$3.20
01025$4.2520$4.23
07046$3.1018$4.25
01036$3.7618$3.50
05047$5.9317$5.93
06037$3.0316$3.12
07016$4.1216$5.03
03024$3.3316$3.37
09016$3.5015$3.68
01055$5.0014$5.63
Removing Guardrail, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Removing Guardrail, ALDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
13 to 22744$5.52
230 to 59644$5.31
596 to 1,75044$3.41
1,776 to 38,65044$3.00
Removing Guardrail, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Removing Guardrail
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 20262026082800405023,141$5.38$3.656IVS HYDRO, INC.ALDOT
28 AUG 2026202608280110402340$5.60$5.624VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
28 AUG 2026202608280211008100$11.86$11.863DUNN CONSTRUCTION COMPANY, INC.ALDOT
28 AUG 202620260828023060150$6.58$4.912APAC-ALABAMA, INC.ALDOT
31 JUL 2026202607310030202225$3.00$3.223ROGERS GROUP, INC.ALDOT
31 JUL 20262026073100505062,025$4.49$4.491S. T. BUNN CONSTRUCTION COMPANY, INC.ALDOT
31 JUL 202620260731008080265$1.78$2.034PL RUSSELL LLCALDOT
31 JUL 2026202607310210701, 0705196$5.05$5.053APAC-ALABAMA, INC.ALDOT
26 JUN 2026202606260050502238$2.31$2.842APAC-ALABAMA, INC.ALDOT
26 JUN 202620260626011010311,388$3.22$3.403WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
26 JUN 2026202606260160103900$2.13$2.714WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
26 JUN 20262026062602003021,150$3.26$3.284GRAYSON CARTER & SON CONTRACTING, INC.ALDOT
29 MAY 20262026052900106037,538$2.31$5.383APAC-ALABAMA, INC.ALDOT
29 MAY 2026202605290210204288$5.00$5.173ROGERS GROUP, INC.ALDOT
29 MAY 20262026052902303011,288$3.55$3.774WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
Latest ALDOT contracts carrying Removing Guardrail

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy