Removing Pipe unit price, Alabama

Low bidders on ALDOT contracts carried a median of $29.00 per LF for item 206D000, removing pipe, over the 24 months to 28 AUG 2026, across 81 low bids. Half of all 299 bids fell between $20.31 and $51.11.

Owner
Alabama DOT
Item
206D000
Unit
LF
Latest letting
28 AUG 2026
$29.00Low bidder's median, per LF
$34.46Median of all bids, per LF
81Contracts in the window

By year of letting

Removing Pipe, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20223838$29.62109$30.00
20234747$34.00137$38.23
20244040$26.26145$30.00
20254242$28.26151$36.82
20262222$30.6190$28.72
Removing Pipe, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Removing Pipe, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
030111$50.0045$50.00
09025$15.4626$20.62
06015$50.0019$45.81
09015$19.3317$24.61
02023$22.0017$38.00
02014$39.0916$42.30
05025$28.3515$35.43
07024$30.5015$24.35
01033$24.0010$28.55
04043$26.509$35.00
03053$50.719$50.71
Removing Pipe, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Removing Pipe, ALDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
1 to 5220$45.00
54 to 14720$37.91
149 to 39320$23.11
400 to 5,98921$26.46
Removing Pipe, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Removing Pipe
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 202620260828011040240$40.00$37.504VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
28 AUG 202620260828030020281$22.00$39.008ROGERS GROUP, INC.ALDOT
31 JUL 2026202607310010301936$20.00$30.636IKAROS, LLCALDOT
31 JUL 20262026073101704021,268$20.82$27.914ALABAMA GRADING & EXCAVATION, LLC.ALDOT
31 JUL 2026202607310250902147$9.00$16.876ARRINGTON CURB & EXCAVATION, INC.ALDOT
26 JUN 202620260626027060148$50.00$50.003ASPHALT CONTRACTORS, INC.ALDOT
26 JUN 202620260626029060119$35.00$35.005DUBOSE CONSTRUCTION COMPANY, LLCALDOT
26 JUN 2026202606260350902469$15.46$24.495WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 2026202605290010603344$34.72$32.353APAC-ALABAMA, INC.ALDOT
29 MAY 202620260529023030134$138.58$117.184WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 202620260529040070466$46.00$29.463APAC-ALABAMA, INC.ALDOT
24 APR 20262026042400706041,435$18.50$15.845S. A. GRAHAM COMPANY, INC.ALDOT
24 APR 202620260424044060428$15.82$18.003WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
27 MAR 2026202603270280404200$26.50$35.003APAC-ALABAMA, INC.ALDOT
27 MAR 2026202603270440606149$110.00$68.212EAST ALABAMA PAVING COMPANY, INC.ALDOT
Latest ALDOT contracts carrying Removing Pipe

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.