ARDOT contract 061888 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT A SIDEWALK AT THE INTERSECTION OF HIGHWAY 10 AND CEDAR HILL ROAD IN PULASKI COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, MAINTENANCE OF TRAFFIC, EROSION CONTROL, CONCRETE WALKS, WHEELCHAIR RAMPS, TRAFFIC SIGNAL ITEMS, PAVEMENT MARKINGS, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Pulaski. 1 bid received; low bid $93,156 by L.E.G. Enterprises, Inc..

Owner
Arkansas DOT
Letting
15 JAN 2025
Pay items
21
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1L.E.G. Enterprises, Inc.$93,156Low
ARDOT contract 061888: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. L.E.G. Enterprises, Inc.
0001Removal and disposal of curb (202001)LF25$50.00
0002Removal and disposal of planters (202198)EACH1$3,600.00
0003Maintenance of traffic (603010)LS1$5,500.00
0004Signs (604003)SF144$25.00
0005Vertical panels (604083)EACH25$45.00
0006Solid sodding (624001)SY41$75.00
0007Concrete walks (633011)SY24$225.00
0008Wheelchair ramps (type 3) (641020)SY28$900.00
0009Traffic signal controller (modification) (701401)EACH1$3,800.00
0010Central control unit (707006)EACH1$6,068.03
0011Pole mounted assembly (707007)EACH2$1,728.00
0012Countdown pedestrian signal head, LED (707015)EACH2$1,426.00
0013Traffic signal cable (5C/12 A.W.G.) (708007)LF185$4.65
0014Traffic signal cable (5C/14 A.W.G.) (708008)LF171$5.25
0015Electrical conductors-in-conduit (1C/8 A.W.G., E.G.C.) (708207)LF358$2.70
0016Non-metallic conduit (2") (710004)LF40$40.00
0017Concrete pull box (type 2 HD) (711105)EACH1$2,175.30
0018Traffic signal pedestal pole with foundation (715011)EACH1$5,400.00
0019Removal of traffic signal equipment (715704)LS1$1,500.00
0020Thermoplastic pavement marking white (12") (719005)LF281$38.50
0021Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$4,011.50
ARDOT contract 061888: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy