Caltrans letting results, April 26, 2023
5 contracts let by Caltrans on April 26, 2023, $10,894,832 in low bids, a median of 4 bidders per contract. On the 5 with an engineer's estimate, the low bid came in under it 2 times; median low bid +4.0% against the estimate.
- Owner
- Caltrans
- Contracts
- 5
- Low bids, total
- $10,894,832
- Data through
- 09 MAY 2023
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 11-2N1664 | Cold plane, RHMA overlay, pavement marking, & rumble strip | District 11 | 4 | Martin Marietta San Diego Aggregates | $2,886,641 | $3,163,598 | +10% | -6.0% | Caltrans |
| 08-1M4904 | Polyester concrete overlay and bridge deck treatment | District 08 | 4 | Velarde Concrete Construction | $2,826,987 | $3,483,413 | +23% | +4.0% | Caltrans |
| 07-0W4004 | Concrete pavement slabs replacement & slurry shoulder | District 07 | 4 | Re Chaffee Construction Inc | $2,705,704 | $2,981,210 | +10% | +27% | Caltrans |
| 03-2G8804 | Modify changeable message sign systems | District 03 | 2 | Studebaker Electric, Inc. | $1,531,050 | $1,796,000 | +17% | +8.0% | Caltrans |
| 02-2J4904 | Modify signal and lighting systems, replace AC surfacing, & striping | District 02 | 4 | Robert J. Frank Construction, Inc. | $944,450 | $968,000 | +2.0% | -2.0% | Caltrans |
Gap is the second bid over the low bid. Where a contract shows fewer bids than Caltrans received, the others did not match their published totals and are left out.