Edgedrain draincrete, unit price, Florida

Low bidders on FDOT contracts carried a median of $41.00 per LF for item 0446-1-1, edgedrain draincrete,, over the 24 months to 28 OCT 2026, across 13 low bids. Half of all 67 bids fell between $38.32 and $59.33.

Owner
Florida DOT
Item
0446-1-1
Unit
LF
Latest letting
28 OCT 2026
$41.00Low bidder's median, per LF
$46.40Median of all bids, per LF
13Contracts in the window

By year of letting

Edgedrain draincrete,, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201888$24.9934$27.35
201933$29.0015$29.00
202033$30.0021$29.00
202177$27.0337$27.06
202233$47.3011$30.69
202333$50.009$123.24
202488$57.0028$52.30
202522$39.7510$43.45
20261010$40.0055$50.00
Edgedrain draincrete,, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Edgedrain draincrete,, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 74$37.0023$39.00
District 53$32.0019$44.00
Edgedrain draincrete,, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Edgedrain draincrete,, FDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
68 to 2073$50.00
1,130 to 1,7833$42.99
3,073 to 3,2023$39.00
3,850 to 59,4414$36.82
Edgedrain draincrete,, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Edgedrain draincrete,
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T1947District 13,202$52.37$81.194AJAX PAVING INDUSTRIES OF FLORIDA LLCFDOT
28 OCT 2026T3A25District 359,441$38.64$51.003ANDERSON COLUMBIA CO., INC.FDOT
29 JUL 2026T5883District 51,783$42.99$44.009MASCI GENERAL CONTRACTORS, INCFDOT
15 JUN 2026T5885District 53,151$32.00$40.094C.W. ROBERTS CONTRACTING, INC.FDOT
10 JUN 2026T5884District 53,850$30.00$44.746C.W. ROBERTS CONTRACTING, INC.FDOT
25 MAR 2026T6589District 6142$195.00$127.806AUM CONSTRUCTION INC.FDOT
25 MAR 2026T7586District 71,741$27.00$31.006GOSALIA CONCRETE CONSTRUCTORS, INC.FDOT
25 FEB 2026T2A37District 268$41.00$50.005GOSALIA CONCRETE CONSTRUCTORS, INC.FDOT
28 JAN 2026T2A56District 2207$50.00$105.835DE MOYA CONTRACTING LLCFDOT
28 JAN 2026T7577District 73,073$39.00$55.727WATSON CIVIL CONSTRUCTION, INC.FDOT
11 JUN 2025T7563District 75,162$35.00$43.005WEBBER, LLCFDOT
29 JAN 2025T7558District 75,621$44.50$43.905GOSALIA CONCRETE CONSTRUCTORS, INC.FDOT
04 DEC 2024T3931District 31,130$54.00$58.672C.W. ROBERTS CONTRACTING, INC.FDOT
25 SEP 2024T1902District 11,226$60.00$165.503OHLA USA INCFDOT
28 AUG 2024T9040StateWide11,394$38.00$39.006WATSON CIVIL CONSTRUCTION, INC.FDOT
Latest FDOT contracts carrying Edgedrain draincrete,

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy