Test piles-prestressed concrete,18" sq unit price, Florida
Low bidders on FDOT contracts carried a median of $248.00 per LF for item 0455-143-3, test piles-prestressed concrete,18" sq, over the 24 months to 28 OCT 2026, across 6 low bids. Half of all 30 bids fell between $297.13 and $622.56.
- Owner
- Florida DOT
- Item
- 0455-143-3
- Unit
- LF
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 10 | 10 | $239.25 | 54 | $260.00 |
| 2019 | 8 | 8 | $322.50 | 38 | $265.86 |
| 2020 | 3 | 3 | $205.00 | 14 | $300.90 |
| 2021 | 8 | 8 | $322.67 | 37 | $318.00 |
| 2022 | 2 | 2 | $292.50 | 5 | $365.00 |
| 2023 | 6 | 6 | $425.00 | 18 | $385.00 |
| 2024 | 6 | 6 | $370.41 | 26 | $400.00 |
| 2025 | 2 | 2 | $471.71 | 9 | $400.00 |
| 2026 | 4 | 4 | $179.20 | 21 | $335.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 3 | 15 | $230.00 | 54 | $280.00 |
| District 1 | 9 | $275.00 | 47 | $350.00 |
| District 4 | 8 | $335.17 | 43 | $300.00 |
| District 2 | 9 | $306.16 | 42 | $256.60 |
| District 7 | 4 | $345.30 | 17 | $318.00 |
| District 6 | 3 | $400.00 | 17 | $330.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 45 to 175 | 12 | $342.67 |
| 185 to 285 | 12 | $287.50 |
| 289 to 450 | 12 | $219.00 |
| 454 to 2,265 | 13 | $316.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T3970 | District 3 | 217 | $180.00 | $270.00 | 5 | RBM CONTRACTING SERVICES, LLC | FDOT |
| 30 SEP 2026 | T1944 | District 1 | 154 | $162.81 | $550.15 | 8 | ZEP CONSTRUCTION, INC. | FDOT |
| 30 SEP 2026 | T3908 | District 3 | 310 | $178.41 | $325.00 | 5 | RBM CONTRACTING SERVICES, LLC | FDOT |
| 28 JAN 2026 | T3954 | District 3 | 144 | $380.00 | $380.00 | 3 | MURPHREE BRIDGE CORPORATION | FDOT |
| 30 JUL 2025 | T4674 | District 4 | 170 | $627.42 | $1,648.50 | 4 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 29 JAN 2025 | T4705 | District 4 | 2,265 | $316.00 | $300.00 | 5 | GLF POSILLICO JV | FDOT |
| 28 AUG 2024 | T1874 | District 1 | 220 | $275.00 | $453.50 | 8 | THOMAS MARINE CONSTRUCTION, INC. | FDOT |
| 14 AUG 2024 | T1899 | District 1 | 290 | $642.00 | $351.26 | 4 | LANE CONSTRUCTION CORPORATION (THE) | FDOT |
| 12 JUN 2024 | T7532 | District 7 | 1,181 | $295.80 | $525.00 | 5 | ZEP CONSTRUCTION, INC. | FDOT |
| 22 MAY 2024 | T1865 | District 1 | 660 | $340.83 | $340.83 | 3 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 15 MAY 2024 | T6539 | District 6 | 204 | $575.60 | $575.60 | 3 | PRINCE CONTRACTING, LLC. | FDOT |
| 31 JAN 2024 | T3790 | District 3 | 669 | $400.00 | $400.00 | 3 | F & W CONSTRUCTION COMPANY, INC. | FDOT |
| 06 DEC 2023 | T2961 | District 2 | 310 | $450.00 | $345.00 | 2 | LEWARE CONSTRUCTION COMPANY OF FLORIDA, INC. | FDOT |
| 13 SEP 2023 | T6413 | District 6, Turnpike | 251 | $737.60 | $471.30 | 2 | GGI CONSTRUCTORS JV | FDOT |
| 14 JUN 2023 | T3791 | District 3 | 454 | $450.00 | $410.00 | 2 | MURPHREE BRIDGE CORPORATION | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.