Sheet piling steel, f&i unit price, Florida

Low bidders on FDOT contracts carried a median of $74.41 per SF for item 0455-133-3, sheet piling steel, f&i, over the 24 months to 28 OCT 2026, across 19 low bids. Half of all 107 bids fell between $60.00 and $105.25.

Owner
Florida DOT
Item
0455-133-3
Unit
SF
Latest letting
28 OCT 2026
$74.41Low bidder's median, per SF
$76.00Median of all bids, per SF
19Contracts in the window

By year of letting

Sheet piling steel, f&i, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201866$37.0032$37.42
201988$37.0539$45.83
202066$38.2738$37.40
202166$50.5826$58.89
202245$75.0025$75.00
202377$86.2529$65.00
202456$75.3518$76.35
2025109$65.0055$78.00
2026910$85.0052$75.00
Sheet piling steel, f&i, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Sheet piling steel, f&i, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 46$61.7434$77.00
District 24$73.0019$80.75
District 33$90.0013$74.00
Sheet piling steel, f&i, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Sheet piling steel, f&i, FDOT: low bidder's median by quantity band
Quantity (SF)Low bidsLow-bid median
413 to 2,0704$171.85
3,126 to 7,1145$80.00
9,642 to 20,7835$68.00
29,060 to 120,6605$59.72
Sheet piling steel, f&i, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Sheet piling steel, f&i
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T3970District 39,642$99.85$75.005RBM CONTRACTING SERVICES, LLCFDOT
30 SEP 2026T6398District 630,800$106.50$98.374OHLA USA INCFDOT
20 MAY 2026T5882District 542,666$59.72$56.1510MASCI GENERAL CONTRACTORS, INCFDOT
29 APR 2026T2809District 23,126$80.00$80.003ANDERSON COLUMBIA CO., INC.FDOT
29 APR 2026T2809District 21,343$66.00$90.003ANDERSON COLUMBIA CO., INC.FDOT
29 APR 2026T3919District 36,102$90.00$78.504F & W CONSTRUCTION COMPANY, INC.FDOT
29 APR 2026T7562District 7413$217.00$175.007WATSON CIVIL CONSTRUCTION, INC.FDOT
31 MAR 2026T3845District 320,524$45.00$59.504PHOENIX CONSTRUCTION SERVICES, INC.FDOT
25 MAR 2026T1920District 120,783$68.00$64.006SEMA CONSTRUCTION, INC.FDOT
25 MAR 2026T6589District 61,320$215.00$162.006AUM CONSTRUCTION INC.FDOT
03 DEC 2025T4729District 414,100$45.00$64.478WEBBER, LLCFDOT
29 OCT 2025T1917District 12,912n/a$169.863OHLA USA INCFDOT
27 AUG 2025T4688District 4120,660$74.41$100.007CENTRAL CIVIL CONSTRUCTION CO.FDOT
11 JUN 2025T2A25District 27,114$86.50$95.005COXWELL, J.B. CONTRACTING, INC.FDOT
11 JUN 2025T5851District 54,009$65.00$64.905JR. DAVIS CONSTRUCTION CO., INC.FDOT
Latest FDOT contracts carrying Sheet piling steel, f&i

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy