Multi-conductor cable, furnish & install unit price, Florida
Low bidders on FDOT contracts carried a median of $5.60 per LF for item 0633-8-1, multi-conductor cable, furnish & install, from 31 JAN 2018 to 19 JUN 2024, across 115 low bids. Half of all 502 bids fell between $4.47 and $6.60.
- Owner
- Florida DOT
- Item
- 0633-8-1
- Unit
- LF
- Latest letting
- 19 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 12 | 13 | $5.06 | 62 | $4.89 |
| 2019 | 9 | 9 | $5.25 | 51 | $5.00 |
| 2020 | 13 | 14 | $4.96 | 66 | $5.00 |
| 2021 | 28 | 29 | $5.00 | 149 | $5.15 |
| 2022 | 21 | 21 | $6.06 | 75 | $6.20 |
| 2023 | 22 | 23 | $6.29 | 76 | $6.38 |
| 2024 | 6 | 6 | $6.89 | 23 | $6.46 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 48 | $5.18 | 199 | $5.11 |
| District 4 | 24 | $5.91 | 136 | $5.79 |
| District 1 | 12 | $5.03 | 49 | $5.15 |
| District 2 | 14 | $6.03 | 46 | $5.72 |
| District 7 | 5 | $4.10 | 28 | $5.08 |
| District 6 | 6 | $6.54 | 26 | $6.59 |
| District 3 | 4 | $9.50 | 11 | $6.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 112 | 28 | $6.00 |
| 115 to 449 | 29 | $6.05 |
| 464 to 1,185 | 29 | $5.06 |
| 1,214 to 15,845 | 29 | $5.33 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 19 JUN 2024 | T7501 | District 7 | 464 | $40.00 | $8.77 | 4 | WEBBER, LLC | FDOT |
| 12 JUN 2024 | T4692 | District 4 | 1,766 | $6.28 | $6.28 | 3 | SICE INC | FDOT |
| 12 JUN 2024 | T5816 | District 5 | 11,983 | $4.89 | $5.42 | 4 | PREFERRED MATERIALS INC. | FDOT |
| 22 MAY 2024 | T5813 | District 5 | 100 | $4.50 | $4.92 | 4 | SOUTHLAND CONSTRUCTION, INC. | FDOT |
| 15 MAY 2024 | T6539 | District 6 | 1,586 | $7.75 | $7.75 | 3 | PRINCE CONTRACTING, LLC. | FDOT |
| 28 FEB 2024 | T7519 | District 7 | 502 | $7.50 | $7.50 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 25 OCT 2023 | T9030 | StateWide | 2,800 | $5.99 | $5.14 | 5 | CHINCHOR ELECTRIC INC. | FDOT |
| 27 SEP 2023 | T3854 | District 3 | 283 | $13.00 | $13.87 | 2 | WEBBER, LLC | FDOT |
| 27 SEP 2023 | T5801 | District 5 | 8,794 | $3.05 | $3.25 | 3 | HALIFAX PAVING, INC. | FDOT |
| 27 SEP 2023 | T5801 | District 5 | 172 | $3.05 | $3.10 | 3 | HALIFAX PAVING, INC. | FDOT |
| 27 SEP 2023 | T5806 | District 5 | 109 | $8.10 | $8.00 | 5 | SUPERIOR ASPHALT, INC. | FDOT |
| 13 SEP 2023 | T5803 | District 5 | 296 | $7.20 | $8.05 | 3 | HIGHWAY SAFETY DEVICES, INC. | FDOT |
| 13 SEP 2023 | T6413 | District 6, Turnpike | 7,027 | $13.80 | $12.40 | 2 | GGI CONSTRUCTORS JV | FDOT |
| 26 JUL 2023 | T2936 | District 2 | 250 | $9.00 | $25.93 | 2 | DUVAL ASPHALT PRODUCTS, INC. | FDOT |
| 24 MAY 2023 | T3849 | District 3 | 75 | $31.00 | $24.19 | 2 | PHOENIX CONSTRUCTION SERVICES, INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.