Signal priority and preemption system, furnish and install, detector unit price, Florida

Low bidders on FDOT contracts carried a median of $8,548.00 per EACH for item 0663-1122, signal priority and preemption system, furnish and install, detector, over the 24 months to 28 OCT 2026, across 25 low bids. Half of all 108 bids fell between $7,956.47 and $10,310.

Owner
Florida DOT
Item
0663-1122
Unit
EACH
Latest letting
28 OCT 2026
$8,548.00Low bidder's median, per EACH
$8,987.00Median of all bids, per EACH
25Contracts in the window

By year of letting

Signal priority and preemption system, furnish and install, detector, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201833$3,883.0317$4,500.00
20191212$4,692.5049$4,949.63
202033$4,464.009$5,000.00
20211111$4,639.5355$5,000.00
20221313$6,122.1437$6,500.00
20231414$8,000.0038$9,030.00
20241010$7,971.1839$8,500.00
20251313$8,068.0051$8,800.00
20261010$8,801.2151$9,057.40
Signal priority and preemption system, furnish and install, detector, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Signal priority and preemption system, furnish and install, detector, FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 515$8,900.0070$9,022.20
District 43$4,280.0017$8,961.80
District 33$7,800.006$11,349
Signal priority and preemption system, furnish and install, detector, FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Signal priority and preemption system, furnish and install, detector, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 16$8,000.00
1 to 16$9,261.00
2 to 26$7,839.00
2 to 147$8,702.42
Signal priority and preemption system, furnish and install, detector, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Signal priority and preemption system, furnish and install, detector
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T4765District 41$4,280.00$5,640.006GENERAL ASPHALT COMPANY, LLCFDOT
30 SEP 2026T5893District 51$7,953.75$8,535.008MASCI GENERAL CONTRACTORS, INCFDOT
26 AUG 2026T5890District 51$10,400$10,3696WATSON CIVIL CONSTRUCTION, INC.FDOT
10 JUN 2026T5888District 53$8,900.00$9,093.508C.W. ROBERTS CONTRACTING, INC.FDOT
20 MAY 2026T5863District 51$12,442$8,518.826MASCI GENERAL CONTRACTORS, INCFDOT
29 APR 2026T5880District 52$8,552.00$9,627.003HALIFAX PAVING, INC.FDOT
29 APR 2026T5881District 510$9,854.31$10,4772MASCI GENERAL CONTRACTORS, INCFDOT
31 MAR 2026T3845District 31$10,798$11,9504PHOENIX CONSTRUCTION SERVICES, INC.FDOT
25 MAR 2026T5878District 51$8,122.00$8,918.663TRAFFIC CONTROL DEVICES, LLCFDOT
25 FEB 2026T1916District 114$8,702.42$8,702.425PREFERRED MATERIALS INC.FDOT
03 DEC 2025T2A48District 22$7,610.00$7,300.005COXWELL, J.B. CONTRACTING, INC.FDOT
27 AUG 2025T5872District 52$8,068.00$8,441.924BLACKTIP SERVICES INCORPORATEDFDOT
30 JUL 2025T4648District 42$4,200.00$8,961.805WEEKLEY ASPHALT PAVING, INC.FDOT
30 JUL 2025T5859District 51$9,500.00$9,500.005AMERICAN DESIGN ENGINEERING CONSTRUCTION INC.FDOT
30 JUL 2025T5871District 51$11,906$10,3202CARR CONSTRUCTION, LLCFDOT
Latest FDOT contracts carrying Signal priority and preemption system, furnish and install, detector

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy