Vehicle detection system- avi, bluetooth, furnish & install, above ground equipment unit price, Florida
Low bidders on FDOT contracts carried a median of $9,692.51 per EACH for item 0660-6122, vehicle detection system- avi, bluetooth, furnish & install, above ground equipment, over the 24 months to 28 OCT 2026, across 15 low bids. Half of all 71 bids fell between $9,510.00 and $12,056.
- Owner
- Florida DOT
- Item
- 0660-6122
- Unit
- EACH
- Latest letting
- 29 JUL 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 6 | 8 | $7,097.00 | 44 | $7,254.50 |
| 2019 | 7 | 7 | $7,969.91 | 34 | $6,904.00 |
| 2020 | 4 | 4 | $9,021.51 | 14 | $8,862.03 |
| 2021 | 10 | 10 | $8,607.08 | 36 | $8,550.00 |
| 2022 | 11 | 11 | $9,100.00 | 37 | $9,152.00 |
| 2023 | 14 | 14 | $11,009 | 43 | $11,430 |
| 2024 | 6 | 6 | $11,798 | 20 | $10,925 |
| 2025 | 7 | 7 | $9,530.00 | 35 | $10,962 |
| 2026 | 7 | 7 | $9,692.51 | 33 | $10,700 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 1 | 6 | $10,096 | 28 | $11,528 |
| District 5 | 3 | $9,335.00 | 11 | $9,335.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $9,400.00 |
| 1 to 3 | 4 | $10,015 |
| 3 to 3 | 4 | $10,357 |
| 3 to 9 | 4 | $9,318.77 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 29 JUL 2026 | T7599 | District 7 | 3 | $15,250 | $13,596 | 4 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 20 MAY 2026 | T5863 | District 5 | 1 | $9,335.00 | $9,432.50 | 6 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 1 | $12,700 | $13,350 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 25 MAR 2026 | T1934 | District 1 | 1 | $16,860 | $17,165 | 4 | AJAX PAVING INDUSTRIES OF FLORIDA LLC | FDOT |
| 25 FEB 2026 | T1813 | District 1 | 1 | $9,400.00 | $9,302.64 | 4 | SUPERIOR ASPHALT, INC. | FDOT |
| 25 FEB 2026 | T1916 | District 1 | 3 | $9,692.51 | $9,692.51 | 5 | PREFERRED MATERIALS INC. | FDOT |
| 28 JAN 2026 | T1922 | District 1 | 3 | $8,815.00 | $11,815 | 4 | SUPERIOR ASPHALT, INC. | FDOT |
| 03 DEC 2025 | T4717 | District 4 | 3 | $9,530.00 | $11,598 | 8 | RTECH ENGINEERING, LLC | FDOT |
| 24 SEP 2025 | T2A24 | District 2 | 3 | $12,200 | $10,537 | 8 | MASTEC CIVIL LLC | FDOT |
| 24 SEP 2025 | T5867 | District 5 | 3 | $7,508.77 | $8,026.89 | 2 | CHINCHOR ELECTRIC INC. | FDOT |
| 28 MAY 2025 | T1926 | District 1 | 2 | $10,500 | $11,389 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 26 FEB 2025 | T7565 | District 7 | 3 | $11,021 | $11,058 | 4 | HUBBARD CONSTRUCTION COMPANY | FDOT |
| 29 JAN 2025 | T2993 | District 2 | 6 | $7,815.00 | $9,454.50 | 3 | TRAFFIC CONTROL DEVICES, LLC | FDOT |
| 29 JAN 2025 | T4705 | District 4 | 1 | $9,227.00 | $10,200 | 5 | GLF POSILLICO JV | FDOT |
| 30 OCT 2024 | T5832 | District 5 | 9 | $9,822.54 | $9,822.54 | 3 | CHINCHOR ELECTRIC INC. | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.