Vehicle detection system- relocate above ground equipment unit price, Florida

Low bidders on FDOT contracts carried a median of $1,381.70 per EACH for item 0660-4-42, vehicle detection system- relocate above ground equipment, over the 24 months to 28 OCT 2026, across 7 low bids. Half of all 38 bids fell between $1,070.00 and $2,644.75.

Owner
Florida DOT
Item
0660-4-42
Unit
EACH
Latest letting
28 OCT 2026
$1,381.70Low bidder's median, per EACH
$1,652.00Median of all bids, per EACH
7Contracts in the window

By year of letting

Vehicle detection system- relocate above ground equipment, FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201855$1,848.0420$1,287.53
201944$1,105.5517$1,511.10
202066$1,130.6049$1,500.00
202155$1,357.6932$733.59
202266$1,435.0022$1,400.00
202366$1,597.0032$1,685.42
202455$2,156.2516$2,459.50
202544$1,552.0016$1,775.00
202633$1,070.0022$1,260.85
Vehicle detection system- relocate above ground equipment, FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Vehicle detection system- relocate above ground equipment, FDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 68$1,021.5063$1,500.00
District 515$1,594.0061$1,661.10
District 410$1,480.8559$1,491.00
District 24$1,985.0018$1,656.00
District 13$1,848.0414$1,464.42
Vehicle detection system- relocate above ground equipment, FDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Vehicle detection system- relocate above ground equipment, FDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 111$1,500.00
1 to 211$1,564.00
2 to 411$2,050.00
4 to 2411$1,050.00
Vehicle detection system- relocate above ground equipment, FDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest FDOT contracts carrying Vehicle detection system- relocate above ground equipment
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 OCT 2026T4765District 416$1,070.00$1,710.006GENERAL ASPHALT COMPANY, LLCFDOT
20 MAY 2026T5882District 52$1,381.70$1,061.9010MASCI GENERAL CONTRACTORS, INCFDOT
25 MAR 2026T4735District 49$717.47$2,288.006SICE INCFDOT
30 APR 2025T3963District 31$1,500.00$2,757.032INGRAM SIGNALIZATION, INC.FDOT
30 APR 2025T4711District 42$2,479.00$2,992.254GLF CONSTRUCTION CORPORATIONFDOT
29 JAN 2025T4705District 41$1,604.00$1,750.005GLF POSILLICO JVFDOT
29 JAN 2025T5843District 54$1,208.46$2,200.005HUBBARD CONSTRUCTION COMPANYFDOT
22 MAY 2024T2979District 22$2,600.00$2,811.085WATSON CIVIL CONSTRUCTION, INC.FDOT
22 MAY 2024T4655District 41$15,000$8,409.504OHLA USA INCFDOT
22 MAY 2024T5804District 52$2,156.25$2,753.122CHINCHOR ELECTRIC INC.FDOT
22 MAY 2024T5825District 52$2,050.00$2,050.003HALIFAX PAVING, INC.FDOT
31 JAN 2024T3892-R0District 324$806.45$903.232ANDERSON COLUMBIA CO., INC.FDOT
15 NOV 2023T5798District 52$1,600.00$1,640.004WATSON CIVIL CONSTRUCTION, INC.FDOT
27 SEP 2023T5801District 51$1,564.00$1,600.003HALIFAX PAVING, INC.FDOT
26 JUL 2023T5797District 56$1,594.00$1,675.004MASCI GENERAL CONTRACTORS, INCFDOT
Latest FDOT contracts carrying Vehicle detection system- relocate above ground equipment

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way