Low bidders on FDOT contracts carried a median of $9,728.00 per EACH for item 0663-1121, signal priority and preemption system, furnish and install, replace cabinet electronics, over the 24 months to 28 OCT 2026, across 2 low bids. Half of all 10 bids fell between $9,305.26 and $10,384.
- Owner
- Florida DOT
- Item
- 0663-1121
- Unit
- EACH
- Latest letting
- 25 MAR 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 4 | 4 | $6,487.16 | 25 | $9,500.00 |
| 2019 | 11 | 11 | $5,900.00 | 47 | $5,518.92 |
| 2020 | 3 | 3 | $6,000.00 | 10 | $6,320.50 |
| 2021 | 11 | 11 | $5,509.65 | 46 | $5,790.00 |
| 2022 | 11 | 11 | $7,887.08 | 27 | $7,788.63 |
| 2023 | 14 | 14 | $10,309 | 38 | $10,500 |
| 2024 | 2 | 2 | $8,350.00 | 9 | $9,980.00 |
| 2025 | 1 | 1 | $10,336 | 7 | $9,700.00 |
| 2026 | 1 | 1 | $9,120.00 | 3 | $9,120.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 5 | 25 | $6,053.40 | 85 | $6,082.00 |
| District 4 | 11 | $6,000.00 | 59 | $6,858.00 |
| District 1 | 6 | $8,202.50 | 29 | $8,150.00 |
| District 3 | 8 | $9,934.00 | 16 | $10,159 |
| District 2 | 6 | $5,704.82 | 16 | $5,821.89 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 14 | $5,704.82 |
| 1 to 1 | 15 | $8,550.00 |
| 1 to 2 | 14 | $8,202.50 |
| 2 to 20 | 15 | $5,802.72 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 25 MAR 2026 | T5878 | District 5 | 1 | $9,120.00 | $9,120.00 | 3 | TRAFFIC CONTROL DEVICES, LLC | FDOT |
| 30 APR 2025 | T5793 | District 5 | 3 | $10,336 | $9,700.00 | 7 | P & S PAVING, INC. | FDOT |
| 22 MAY 2024 | T4677 | District 4 | 1 | $7,800.00 | $9,690.00 | 4 | WEEKLEY ASPHALT PAVING, INC. | FDOT |
| 28 FEB 2024 | T7519 | District 7 | 2 | $8,900.00 | $9,980.00 | 5 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 06 DEC 2023 | T2951 | District 2 | 1 | $9,415.04 | $10,500 | 3 | PREFERRED MATERIALS INC. | FDOT |
| 15 NOV 2023 | T5798 | District 5 | 2 | $10,500 | $10,400 | 4 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 25 OCT 2023 | T3870 | District 3 | 1 | $19,000 | $25,000 | 3 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 26 JUL 2023 | T3855 | District 3 | 1 | $11,000 | $11,000 | 1 | INGRAM SIGNALIZATION, INC. | FDOT |
| 14 JUN 2023 | T5760 | District 5 | 5 | $11,330 | $11,615 | 2 | HUBBARD CONSTRUCTION COMPANY | FDOT |
| 14 JUN 2023 | T5795 | District 5 | 2 | $11,439 | $14,687 | 2 | HUBBARD CONSTRUCTION COMPANY | FDOT |
| 24 MAY 2023 | T1807 | District 1 | 1 | $11,500 | $11,500 | 2 | C.W. ROBERTS CONTRACTING, INC. | FDOT |
| 24 MAY 2023 | T3849 | District 3 | 1 | $10,118 | $9,405.18 | 2 | PHOENIX CONSTRUCTION SERVICES, INC. | FDOT |
| 26 APR 2023 | T5787 | District 5 | 1 | $7,424.00 | $10,025 | 4 | ATLANTIC CIVIL CONSTRUCTORS CORP | FDOT |
| 22 FEB 2023 | T5783 | District 5 | 1 | $7,900.00 | $8,560.00 | 2 | HIGHWAY SAFETY DEVICES, INC. | FDOT |
| 25 JAN 2023 | T4634 | District 4 | 1 | $9,500.00 | $9,750.00 | 4 | FLORIDA ENGINEERING & DEVELOPMENT CORP | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.