Utility fixture, valve assembly, furnish and install, 8" unit price, Florida

Low bidders on FDOT contracts carried a median of $4,826.67 per EACH for item 1080-24108, utility fixture, valve assembly, furnish and install, 8", over the 24 months to 28 OCT 2026, across 10 low bids. Half of all 58 bids fell between $3,496.81 and $5,146.16.

Owner
Florida DOT
Item
1080-24108
Unit
EACH
Latest letting
30 SEP 2026
$4,826.67Low bidder's median, per EACH
$4,205.00Median of all bids, per EACH
10Contracts in the window

By year of letting

Utility fixture, valve assembly, furnish and install, 8", FDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20181212$1,800.0067$1,860.00
201955$1,848.5724$1,956.95
202077$2,188.4636$2,294.23
202155$2,600.0031$2,619.03
202255$3,395.6813$3,409.61
202344$3,794.9518$3,841.45
202466$4,575.0026$5,000.00
202544$4,563.5016$4,270.00
202655$4,670.0538$3,816.36
Utility fixture, valve assembly, furnish and install, 8", FDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Utility fixture, valve assembly, furnish and install, 8", FDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 53$3,350.0024$3,947.50
District 43$4,670.0516$3,962.50
Utility fixture, valve assembly, furnish and install, 8", FDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

Latest contracts with this item

Latest FDOT contracts carrying Utility fixture, valve assembly, furnish and install, 8"
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
30 SEP 2026T6398District 618$5,167.75$5,025.144OHLA USA INCFDOT
29 JUL 2026T5883District 51$3,350.00$3,215.009MASCI GENERAL CONTRACTORS, INCFDOT
20 MAY 2026T4666District 45$4,670.05$3,752.508OHLA USA INCFDOT
20 MAY 2026T5882District 56$5,100.00$4,054.0010MASCI GENERAL CONTRACTORS, INCFDOT
29 APR 2026T7562District 78$3,400.00$3,807.737WATSON CIVIL CONSTRUCTION, INC.FDOT
11 JUN 2025T5851District 51$3,300.00$5,153.215JR. DAVIS CONSTRUCTION CO., INC.FDOT
28 MAY 2025T4575District 48$4,983.29$4,255.004ROADWAY CONSTRUCTION, LLCFDOT
28 MAY 2025T7533District 714$6,000.00$6,000.003DB CIVIL CONSTRUCTION, LLCFDOT
26 MAR 2025T4699District 47$4,143.71$3,931.864TIMOTHY ROSE CONTRACTING, INC.FDOT
13 NOV 2024T3918District 32$6,000.00$5,868.054C.W. ROBERTS CONTRACTING, INC.FDOT
14 AUG 2024T1899District 12$4,150.00$3,699.444LANE CONSTRUCTION CORPORATION (THE)FDOT
12 JUN 2024T7532District 72$2,316.00$4,000.005ZEP CONSTRUCTION, INC.FDOT
22 MAY 2024T7530District 712$5,500.00$5,500.003DE MOYA HIGHWAY INFRASTRUCTURE LLCFDOT
24 APR 2024T7520District 71$5,000.00$5,500.004WATSON CIVIL CONSTRUCTION, INC.FDOT
31 JAN 2024T4621District 41$3,300.00$4,272.506GENERAL ASPHALT COMPANY, LLCFDOT
Latest FDOT contracts carrying Utility fixture, valve assembly, furnish and install, 8"

Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.

How these prices were read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy