Utility structure, below ground, adjust/modify unit price, Florida
Low bidders on FDOT contracts carried a median of $2,375.73 per EACH for item 1060-15, utility structure, below ground, adjust/modify, over the 24 months to 28 OCT 2026, across 11 low bids. Half of all 55 bids fell between $1,731.59 and $5,516.18.
- Owner
- Florida DOT
- Item
- 1060-15
- Unit
- EACH
- Latest letting
- 28 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 13 | 13 | $912.00 | 78 | $1,039.95 |
| 2019 | 6 | 6 | $775.00 | 18 | $890.00 |
| 2020 | 8 | 8 | $569.50 | 54 | $800.00 |
| 2021 | 7 | 8 | $907.00 | 75 | $660.00 |
| 2022 | 8 | 8 | $1,525.00 | 35 | $1,050.00 |
| 2023 | 6 | 6 | $3,330.00 | 28 | $3,950.09 |
| 2024 | 7 | 7 | $1,500.00 | 25 | $2,000.00 |
| 2025 | 3 | 3 | $2,065.00 | 10 | $3,376.64 |
| 2026 | 8 | 8 | $2,562.86 | 45 | $3,400.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| District 7 | 4 | $3,256.35 | 20 | $4,800.00 |
| District 6 | 3 | $1,619.00 | 12 | $1,624.50 |
Districts with at least three low bids, over the last 24 months.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 28 OCT 2026 | T7591 | District 7 | 4 | $2,375.73 | $2,546.33 | 5 | PREFERRED MATERIALS INC. | FDOT |
| 30 SEP 2026 | T6398 | District 6 | 44 | $1,619.00 | $2,601.30 | 4 | OHLA USA INC | FDOT |
| 10 JUN 2026 | T7534 | District 7 | 25 | $3,762.69 | $3,214.24 | 4 | PREFERRED MATERIALS INC. | FDOT |
| 20 MAY 2026 | T5882 | District 5 | 4 | $1,250.00 | $1,740.00 | 10 | MASCI GENERAL CONTRACTORS, INC | FDOT |
| 29 APR 2026 | T7562 | District 7 | 1 | $5,400.00 | $5,700.00 | 7 | WATSON CIVIL CONSTRUCTION, INC. | FDOT |
| 25 MAR 2026 | T1920 | District 1 | 2 | $12,100 | $12,402 | 6 | SEMA CONSTRUCTION, INC. | FDOT |
| 28 JAN 2026 | T6618 | District 6 | 10 | $1,250.00 | $1,100.00 | 5 | WEEKLEY ASPHALT PAVING, INC. | FDOT |
| 28 JAN 2026 | T7580 | District 7 | 2 | $2,750.00 | $10,500 | 4 | AJ GENERAL CONSTRUCTION SERVICES, INC. | FDOT |
| 26 FEB 2025 | T3853 | District 3 | 3 | $2,500.00 | $4,000.00 | 3 | COLLINS LAND SERVICES, LLC | FDOT |
| 26 FEB 2025 | T4697 | District 4 | 1 | $2,065.00 | $4,226.64 | 4 | OHLA USA INC | FDOT |
| 29 JAN 2025 | T6610 | District 6 | 21 | $1,813.18 | $1,813.18 | 3 | FLORIDA ENGINEERING & DEVELOPMENT CORP | FDOT |
| 25 SEP 2024 | T6598 | District 6 | 2 | $2,750.00 | $1,431.25 | 4 | BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A B | FDOT |
| 31 JUL 2024 | T6586 | District 6 | 2 | $1,265.00 | $1,442.05 | 2 | GENERAL ASPHALT COMPANY, LLC | FDOT |
| 12 JUN 2024 | T1875 | District 1 | 4 | $1,127.41 | $5,900.00 | 3 | HUBBARD CONSTRUCTION COMPANY | FDOT |
| 22 MAY 2024 | T6566 | District 6 | 16 | $2,400.00 | $1,750.00 | 6 | BACALLAO CONSTRUCTION & ENGINEERING DEVELOPMENT, LLC D/B/A B | FDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the FDOT explorer.
How these prices were read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are FDOT's own: this item is compared with FDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way