IDOT contract 68K22 bid tabulation
Section D4. Let by Illinois DOT on April 24, 2026, Woodford, District 04. 2 bids received; low bid $2,172,735 by Stark Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 65
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Excavating, Inc. | $2,172,735 | Low |
| 2 | Gensini Excavating, Inc. | $2,337,119 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Excavating, Inc. | 2. Gensini Excavating, Inc. |
|---|---|---|---|---|---|
| 1 | Surface filler SPL (X0326444) | GAL | 3 | $1,000.00 | $654.86 |
| 2 | Curb removal SPL (X4402400) | LF | 8 | $150.00 | $25.28 |
| 3 | Protective coat SPL (X5030550) | SY | 644 | $55.00 | $101.72 |
| 4 | Abandon & fill EX SS (X5509900) | LF | 234 | $37.00 | $32.98 |
| 5 | Fill inlets SPL (X6050310) | EACH | 6 | $263.00 | $2,206.77 |
| 6 | Conc curb SPL (X6060505) | LF | 42 | $237.00 | $124.78 |
| 7 | Linear delin panels 4 (X6350204) | EACH | 38 | $75.00 | $136.41 |
| 8 | GDRL agg eros cont (Z0001002) | TON | 627 | $100.00 | $79.28 |
| 9 | Construction layout (Z0013798) | LS | 1 | $23,675 | $12,004 |
| 10 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 |
| 11 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 |
| 12 | Exc & GR EX shoulder (20200600) | UNIT | 21 | $1,645.00 | $48.89 |
| 13 | Stone dump rip CL B3 (28100725) | SY | 54 | $80.00 | $69.91 |
| 14 | Agg subgrade impr 12 (30300112) | SY | 896 | $65.00 | $73.51 |
| 15 | Bit matls tack CT (40600290) | LB | 309 | $4.10 | $4.37 |
| 16 | P bit matls tack CT (40600295) | LB | 2,532 | $4.10 | $4.37 |
| 17 | HMA surf rem butt JT (40600982) | SY | 1,597 | $35.10 | $38.20 |
| 18 | Temporary ramp (40600990) | SY | 707 | $30.10 | $32.74 |
| 19 | P HMA BC IL-4.75 N50 (40603200) | TON | 83 | $501.00 | $545.65 |
| 20 | P HMA SC IL-9.5 D N50 (40604160) | TON | 161 | $501.00 | $545.65 |
| 21 | HMA surf rem 1/2 (44000151) | SY | 55 | $35.10 | $38.20 |
| 22 | HMA surf rem 1 (44000153) | SY | 423 | $35.10 | $38.20 |
| 23 | Paved SHLD removal (44004250) | SY | 409 | $77.00 | $60.02 |
| 24 | HMA shoulders 8 (48203029) | SY | 682 | $136.00 | $147.33 |
| 25 | Conc headwall removal (50104400) | EACH | 6 | $0.01 | $1,499.38 |
| 26 | BR deck grooving (50300260) | SY | 2,265 | $13.00 | $9.26 |
| 27 | Protective coat (50300300) | SY | 2,397 | $6.50 | $9.02 |
| 28 | Deck slab rep (FD-T2) (53016002) | SY | 60 | $1,700.00 | $1,646.96 |
| 29 | BR deck scar 3/4 (53101002) | SY | 2,397 | $85.00 | $44.96 |
| 30 | BR DK mic C ovl 2 1/4 (53101608) | SY | 2,397 | $172.00 | $216.28 |
| 31 | STR rep con DP = < 5 (53212754) | SF | 3 | $710.00 | $1,756.81 |
| 32 | SPBGR TY A 6FT posts (63000001) | LF | 1,775 | $34.60 | $43.65 |
| 33 | Traf bar term T6 (63100085) | EACH | 16 | $3,000.00 | $5,565.65 |
| 34 | TR bar TRM T1 SPL tan (63100167) | EACH | 15 | $3,860.00 | $4,910.86 |
| 35 | TR bar TRM T1 SPL FLR (63100169) | EACH | 1 | $3,220.00 | $4,910.86 |
| 36 | Guardrail remov (63200310) | LF | 3,275 | $5.60 | $4.37 |
| 37 | Engr field office A (67000400) | CAL MO | 9 | $1,400.00 | $3,492.17 |
| 38 | Mobilization (67100100) | LS | 1 | $131,000 | $169,574 |
| 39 | Traf cont-prot 701321 (70100405) | EACH | 4 | $19,100 | $15,824 |
| 40 | Traf cont-prot 701201 (70100450) | LS | 1 | $1,980.00 | $927.61 |
| 41 | Traf cont-prot 701306 (70100460) | LS | 1 | $0.01 | $927.61 |
| 42 | Traf cont-prot 701326 (70100500) | LS | 1 | $3,560.00 | $927.61 |
| 43 | TR cont surveillance (70103815) | CAL DAY | 60 | $0.01 | $0.01 |
| 44 | Temp BR traf signals (70106500) | EACH | 4 | $25,000 | $19,098 |
| 45 | Temp rumble strips (70106700) | EACH | 4 | $1,830.00 | $7,202.60 |
| 46 | Changeable message SN (70107025) | CAL DAY | 70 | $151.00 | $60.02 |
| 47 | Short term pavt mking (70300100) | LF | 356 | $1.10 | $2.73 |
| 48 | SHRT TRM pavt MK rem (70300150) | SF | 120 | $2.10 | $4.37 |
| 49 | Temp PVT MK L4 T4 tape (70307120) | LF | 11,385 | $1.60 | $1.53 |
| 50 | Temp PVT MK L24 T4 tape (70307210) | LF | 155 | $9.60 | $10.91 |
| 51 | Temp conc barrier (70400100) | LF | 1,875 | $55.00 | $63.38 |
| 52 | Rel temp conc barrier (70400200) | LF | 1,850 | $15.00 | $27.83 |
| 53 | Imp attn temp NRN TL3 (70600251) | EACH | 8 | $6,002.00 | $4,910.86 |
| 54 | Imp attn rel NRN TL3 (70600352) | EACH | 8 | $1,130.00 | $1,364.13 |
| 55 | Terminal marker - DA (72501000) | EACH | 16 | $51.00 | $54.57 |
| 56 | Mod ureth PM LTR-sym (78009000) | SF | 32 | $4.60 | $8.73 |
| 57 | Mod ureth PM line 4 (78009004) | LF | 5,456 | $1.10 | $1.09 |
| 58 | Mod ureth PM line 6 (78009006) | LF | 6,470 | $1.85 | $1.64 |
| 59 | Mod ureth PM line 24 (78009024) | LF | 60 | $7.40 | $10.91 |
| 60 | GRV RCSD PM LTR & sym (78011000) | SF | 32 | $6.10 | $26.19 |
| 61 | GRV RCSD PVT MRKG 5 (78011025) | LF | 5,456 | $1.25 | $1.09 |
| 62 | GRV RCSD PVT MRKG 7 (78011035) | LF | 6,470 | $1.90 | $1.31 |
| 63 | Raised refl pavt MKR (78100100) | EACH | 10 | $500.00 | $927.61 |
| 64 | Raised ref PVT MK rem (78300200) | EACH | 10 | $20.50 | $21.83 |
| 65 | PVT MKG rem WTR blast (78300202) | SF | 9,066 | $0.98 | $1.64 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.