IDOT contract 70C33 bid tabulation
Section (104,121)DR. Let by Illinois DOT on September 19, 2025, Mclean, District 05. 3 bids received; low bid $1,043,581 by Phoenix Corporation of the Quad Cities.
- Owner
- Illinois DOT
- Letting
- 19 SEP 2025
- Pay items
- 51
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Phoenix Corporation of the Quad Cities | $1,043,581 | Low |
| 2 | Stark Excavating, Inc. | $1,134,377 | +9.0% |
| 3 | CSD Environmental Services, Inc. | $2,007,359 | +92% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Phoenix Corporation of the Quad Cities | 2. Stark Excavating, Inc. | 3. CSD Environmental Services, Inc. |
|---|---|---|---|---|---|---|
| 1 | Construction layout (Z0013798) | LS | 1 | $10,500 | $11,500 | $12,792 |
| 2 | RR prot liability ins (Z0048665) | LS | 1 | $10,000 | $5,500.00 | $35,000 |
| 3 | Earth excavation (20200100) | CY | 10,770 | $34.50 | $40.50 | $81.12 |
| 4 | Porous gran backfill (20900110) | CY | 236 | $162.00 | $115.00 | $94.04 |
| 5 | Explor trench 60 (21301060) | LF | 1,000 | $20.00 | $6.00 | $33.91 |
| 6 | Seeding CL 2 (25000200) | ACRE | 4 | $1,320.00 | $1,350.00 | $1,608.10 |
| 7 | Seeding CL 4 (25000310) | ACRE | 4 | $1,320.00 | $1,350.00 | $1,608.10 |
| 8 | Seeding CL 5A (25000322) | ACRE | 4 | $1,100.00 | $1,110.00 | $1,340.09 |
| 9 | Nitrogen fert nutr (25000400) | LB | 720 | $1.00 | $1.00 | $1.22 |
| 10 | Phosphorus fert nutr (25000500) | LB | 720 | $1.00 | $1.00 | $1.22 |
| 11 | Potassium fert nutr (25000600) | LB | 720 | $1.00 | $1.00 | $1.22 |
| 12 | Mulch method 2 (25100115) | ACRE | 8 | $1,325.00 | $1,335.00 | $1,614.19 |
| 13 | Temp eros contr seed (28000250) | LB | 800 | $7.00 | $5.50 | $2.44 |
| 14 | Temp ditch checks (28000305) | LF | 490 | $61.00 | $25.00 | $18.27 |
| 15 | Perimeter eros bar (28000400) | LF | 200 | $10.00 | $14.50 | $7.52 |
| 16 | Inlet & pipe protect (28000500) | EACH | 8 | $375.00 | $225.00 | $179.81 |
| 17 | Stone riprap CL A4 (28100107) | SY | 181 | $130.00 | $151.00 | $105.00 |
| 18 | Filter fabric (28200200) | SY | 181 | $4.00 | $3.50 | $7.19 |
| 19 | Agg base cse B (35101400) | TON | 24 | $144.00 | $190.00 | $41.56 |
| 20 | Agg surf course TY B (40200800) | TON | 123 | $114.00 | $112.00 | $70.68 |
| 21 | Bit matls PR CT (40800025) | LB | 177 | $5.00 | $9.00 | $30.46 |
| 22 | Incidental HMA surf (40800050) | TON | 12 | $580.00 | $700.00 | $548.22 |
| 23 | Drive pavement rem (44000200) | SY | 30 | $60.00 | $66.00 | $115.26 |
| 24 | CL D patch T2 9 (44201753) | SY | 60 | $525.00 | $580.00 | $158.37 |
| 25 | CL D patch T3 9 (44201757) | SY | 42 | $415.00 | $505.00 | $303.35 |
| 26 | CL D patch T4 9 (44201759) | SY | 113 | $408.00 | $380.00 | $352.08 |
| 27 | Aggregate SHLDS B (48101200) | TON | 18 | $186.00 | $180.00 | $143.57 |
| 28 | Rem exist struct (50100100) | EACH | 9 | $3,000.00 | $4,600.00 | $21,825 |
| 29 | P cul CL A 1 eqrs 24 (542A5479) | LF | 39 | $206.00 | $335.00 | $656.75 |
| 30 | P cul CL A 1 eqrs 30 (542A5485) | LF | 147 | $250.00 | $278.00 | $427.35 |
| 31 | P cul CL A 1 eqrs 36 (542A5491) | LF | 186 | $295.00 | $331.00 | $484.03 |
| 32 | P cul CL D 1 eqrs 18 (542D5473) | LF | 125 | $95.00 | $91.00 | $161.00 |
| 33 | P cul CL D 1 eqrs 36 (542D5491) | LF | 180 | $136.00 | $140.00 | $242.77 |
| 34 | PRCF end S EL eqrs 24 (54214719) | EACH | 2 | $2,900.00 | $2,850.00 | $2,816.11 |
| 35 | PRCF end S EL eqrs 30 (54214725) | EACH | 6 | $3,400.00 | $3,350.00 | $2,964.09 |
| 36 | PRCF end S EL eqrs 36 (54214731) | EACH | 8 | $4,250.00 | $4,675.00 | $3,007.62 |
| 37 | Metal FL ES EQ RS 18" (54262818) | EACH | 6 | $500.00 | $750.00 | $728.59 |
| 38 | Metal FL ES EQ RS 36" (54262836) | EACH | 8 | $1,500.00 | $1,950.00 | $1,235.57 |
| 39 | Inlets TA T8G (60236200) | EACH | 1 | $1,975.00 | $2,650.00 | $3,647.66 |
| 40 | Remov catch bas (60500050) | EACH | 1 | $300.00 | $400.00 | $1,728.91 |
| 41 | Non SPL waste disposl (66900200) | CY | 95 | $95.00 | $140.00 | $105.00 |
| 42 | Soil disposal analy (66900530) | EACH | 1 | $1,200.00 | $1,250.00 | $2,680.17 |
| 43 | Reg sub P-const plan (66901001) | LS | 1 | $3,000.00 | $3,200.00 | $2,801.99 |
| 44 | Reg sub F con report (66901003) | LS | 1 | $1,000.00 | $1,050.00 | $2,558.34 |
| 45 | Reg sub mon (66901006) | CAL DAY | 5 | $1,000.00 | $1,100.00 | $1,705.00 |
| 46 | Engr field office A (67000400) | CAL MO | 6 | $4,100.00 | $2,000.00 | $3,654.77 |
| 47 | Mobilization (67100100) | LS | 1 | $80,800 | $62,000 | $32,893 |
| 48 | Traf cont-prot 701201 (70100450) | LS | 1 | $100.00 | $50,000 | $129,531 |
| 49 | Traf cont-prot 701206 (70100455) | LS | 1 | $3,100.00 | $2,050.62 | $129,531 |
| 50 | Changeable message SN (70107025) | CAL DAY | 28 | $125.00 | $160.00 | $152.28 |
| 51 | Paint PVT MK line 4 (78001110) | LF | 4,613 | $0.76 | $0.76 | $4.69 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.