IDOT contract 72316 bid tabulation
Section (2CS,22X)RS-2;(28CS)RS-3. Let by Illinois DOT on June 13, 2025, Logan, District 06. 3 bids received; low bid $1,188,874 by Truman L. Flatt & Sons Co., Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 54
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Truman L. Flatt & Sons Co., Inc. | $1,188,874 | Low |
| 2 | P. H. Broughton & Sons, Inc. | $1,243,895 | +5.0% |
| 3 | Illinois Valley Paving, a div of UCM, Inc. | $1,250,403 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Truman L. Flatt & Sons Co., Inc. | 2. P. H. Broughton & Sons, Inc. | 3. Illinois Valley Paving, a div of UCM, Inc. |
|---|---|---|---|---|---|---|
| 1 | PC conc sidewalk 4 SP (X4240420) | SF | 3,113 | $25.46 | $26.03 | $31.18 |
| 2 | HMA surf rem var DP (X4401198) | SY | 4,532 | $5.35 | $3.61 | $4.03 |
| 3 | Construction layout (Z0013798) | LS | 1 | $15,750 | $26,835 | $9,132.55 |
| 4 | RR prot liability ins (Z0048665) | LS | 1 | $10,088 | $5,089.91 | $6,861.10 |
| 5 | Trainees TPG (Z0076604) | HR | 1,500 | $15.00 | $15.00 | $15.00 |
| 6 | Tree remov over 15 (20100210) | UNIT | 42 | $150.00 | $375.69 | $367.50 |
| 7 | Agg surf course TY B (40200800) | TON | 20 | $71.84 | $70.29 | $141.55 |
| 8 | Bit matls tack CT (40600290) | LB | 12,698 | $0.68 | $0.64 | $1.30 |
| 9 | Long joint sealant (40600370) | LF | 8,661 | $4.12 | $4.59 | $3.98 |
| 10 | Matl transfer device (40600405) | TON | 2,653 | $3.88 | $7.66 | $4.61 |
| 11 | HMA surf rem butt JT (40600982) | SY | 942 | $17.73 | $11.30 | $15.40 |
| 12 | Temporary ramp (40600990) | SY | 446 | $15.03 | $9.78 | $12.64 |
| 13 | HMA SC IL-9.5 C N50 (40604050) | TON | 508 | $136.37 | $136.24 | $139.45 |
| 14 | P HMA SC IL-9.5 C N50 (40604150) | TON | 2,653 | $130.80 | $136.24 | $140.08 |
| 15 | Bit matls tack CT (40800029) | LB | 424 | $0.68 | $2.10 | $4.06 |
| 16 | Incidental HMA surf (40800050) | TON | 92 | $350.22 | $220.83 | $277.75 |
| 17 | Detectable warnings (42400800) | SF | 241 | $55.65 | $56.89 | $42.41 |
| 18 | HMA surf rem 1 1/2 (44000155) | SY | 20,152 | $2.75 | $3.61 | $2.83 |
| 19 | HMA surf rem 2 (44000157) | SY | 3,531 | $3.54 | $4.07 | $2.83 |
| 20 | Comb curb gutter rem (44000500) | LF | 852 | $40.95 | $41.86 | $20.19 |
| 21 | Sidewalk rem (44000600) | SF | 2,459 | $8.14 | $8.32 | $7.14 |
| 22 | Agg wedge SHLD type B (48102100) | TON | 158 | $79.14 | $70.29 | $85.85 |
| 23 | Man adjust (60255500) | EACH | 13 | $1,131.00 | $2,093.15 | $2,415.35 |
| 24 | Inlets adj new T3F&G (60260500) | EACH | 8 | $2,520.00 | $2,576.18 | $1,985.41 |
| 25 | Inlets adj new T15F&L (60261500) | EACH | 17 | $2,336.25 | $2,388.33 | $1,855.71 |
| 26 | VV adjust (60265700) | EACH | 11 | $834.76 | $912.40 | $1,034.82 |
| 27 | Conc curb TB (60600605) | LF | 123 | $110.25 | $112.71 | $197.13 |
| 28 | Comb CC&G TB6.18 (60604400) | LF | 852 | $68.78 | $70.31 | $123.73 |
| 29 | Non SPL waste disposl (66900200) | CY | 54 | $186.53 | $190.69 | $324.56 |
| 30 | Soil disposal analy (66900530) | EACH | 3 | $1,365.00 | $1,395.43 | $1,365.00 |
| 31 | Reg sub P-const plan (66901001) | LS | 1 | $2,310.00 | $2,361.50 | $2,310.00 |
| 32 | Reg sub F con report (66901003) | LS | 1 | $2,310.00 | $2,361.50 | $2,310.00 |
| 33 | Reg sub mon (66901006) | CAL DAY | 17 | $1,060.50 | $1,084.14 | $1,060.50 |
| 34 | Engr field office A (67000400) | CAL MO | 6 | $2,658.48 | $3,344.80 | $3,675.59 |
| 35 | Mobilization (67100100) | LS | 1 | $45,885 | $64,459 | $29,057 |
| 36 | TR cont & prot 701501 (70102620) | LS | 1 | $12,327 | $5,152.36 | $28,523 |
| 37 | TR cont & prot 701701 (70102635) | LS | 1 | $21,016 | $3,091.42 | $2,049.07 |
| 38 | TR cont & prot 701801 (70102640) | LS | 1 | $2,894.71 | $3,606.65 | $2,442.82 |
| 39 | Changeable message SN (70107025) | CAL DAY | 180 | $107.97 | $69.77 | $66.94 |
| 40 | Short term pavt mking (70300100) | LF | 4,516 | $0.44 | $2.09 | $0.01 |
| 41 | SHRT TRM pavt MK rem (70300150) | SF | 1,506 | $3.04 | $1.92 | $0.01 |
| 42 | Remov sin pan assy TA (72400100) | EACH | 5 | $155.78 | $107.34 | $136.62 |
| 43 | Remov sign panel T1 (72400310) | SF | 13 | $17.58 | $42.94 | $52.55 |
| 44 | Reloc sin pan assy TA (72400500) | EACH | 5 | $152.41 | $402.53 | $189.00 |
| 45 | Reloc sign panel T1 (72400710) | SF | 13 | $17.58 | $48.30 | $17.85 |
| 46 | Teles STL sin support (72800100) | LF | 98 | $21.18 | $32.20 | $33.08 |
| 47 | THPL PVT MK LTR & sym (78000100) | SF | 140 | $4.46 | $4.56 | $4.46 |
| 48 | THPL PVT MK line 5 (78000300) | LF | 14,962 | $0.90 | $0.92 | $0.90 |
| 49 | THPL PVT MK line 6 (78000400) | LF | 6,530 | $1.08 | $1.11 | $1.08 |
| 50 | THPL PVT MK line 8 (78000500) | LF | 812 | $1.44 | $1.47 | $1.44 |
| 51 | THPL PVT MK line 12 (78000600) | LF | 120 | $2.16 | $2.21 | $2.16 |
| 52 | THPL PVT MK line 24 (78000650) | LF | 173 | $4.73 | $4.83 | $4.73 |
| 53 | Raised refl pavt MKR (78100100) | EACH | 160 | $42.99 | $43.95 | $42.99 |
| 54 | Raised ref PVT MK rem (78300200) | EACH | 160 | $16.19 | $17.28 | $20.08 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.