IDOT contract 72348 bid tabulation
Section 1RS-5,. Let by Illinois DOT on April 24, 2026, Sangamon, District 06. 3 bids received; low bid $4,462,601 by P. H. Broughton & Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 64
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | P. H. Broughton & Sons, Inc. | $4,462,601 | Low |
| 2 | Truman L. Flatt & Sons Co., Inc. | $4,888,277 | +10% |
| 3 | Illinois Valley Paving, a div of UCM, Inc. | $5,436,434 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. P. H. Broughton & Sons, Inc. | 2. Truman L. Flatt & Sons Co., Inc. | 3. Illinois Valley Paving, a div of UCM, Inc. |
|---|---|---|---|---|---|---|
| 1 | Exc & GR EX SHLD SPL (X2020060) | UNIT | 255 | $588.98 | $624.91 | $560.55 |
| 2 | Remove exist riprap (X2810844) | SY | 6,441 | $8.70 | $9.19 | $9.19 |
| 3 | HMA surf rem var DP (X4401198) | SY | 590 | $7.98 | $15.36 | $20.82 |
| 4 | Aggregate SHLDS SPL (X4811900) | TON | 605 | $100.90 | $145.89 | $109.20 |
| 5 | Pipe culvert rem SPL (X5015225) | LF | 2 | $2,145.43 | $645.75 | $645.75 |
| 6 | SPBGR (short radius) (X6330725) | LF | 28 | $42.91 | $42.00 | $72.77 |
| 7 | Trainees (Z0076600) | HR | 3,500 | $0.80 | $0.80 | $0.80 |
| 8 | Trainees TPG (Z0076604) | HR | 3,500 | $15.00 | $15.00 | $15.00 |
| 9 | Furnished excavation (20400800) | CY | 240 | $66.85 | $81.90 | $81.90 |
| 10 | Seeding CL 2 (25000200) | ACRE | 0.20 | $20,382 | $19,950 | $19,950 |
| 11 | Nitrogen fert nutr (25000400) | LB | 17 | $10.73 | $10.50 | $10.50 |
| 12 | Phosphorus fert nutr (25000500) | LB | 17 | $10.73 | $10.50 | $10.50 |
| 13 | Potassium fert nutr (25000600) | LB | 17 | $10.73 | $10.50 | $10.50 |
| 14 | Agr ground limestone (25000700) | TON | 0.40 | $8.58 | $8.40 | $8.40 |
| 15 | Mulch method 2 (25100115) | ACRE | 0.20 | $20,382 | $19,950 | $19,950 |
| 16 | Temp eros contr seed (28000250) | LB | 19 | $26.82 | $26.25 | $26.25 |
| 17 | Temp ditch checks (28000305) | LF | 186 | $16.09 | $15.75 | $15.75 |
| 18 | Inlet & pipe protect (28000500) | EACH | 3 | $268.18 | $262.50 | $262.50 |
| 19 | Stone riprap CL A3 (28100205) | TON | 2,147 | $61.25 | $91.35 | $91.35 |
| 20 | Filter fabric (28200200) | SY | 6,441 | $4.66 | $1.05 | $1.05 |
| 21 | Agg base cse B (35101400) | TON | 38 | $41.66 | $69.29 | $193.43 |
| 22 | Preparation of base (35800100) | SY | 323 | $8.22 | $4.80 | $19.95 |
| 23 | Bit matls tack CT (40600290) | LB | 52,280 | $0.61 | $0.66 | $1.11 |
| 24 | Long joint sealant (40600370) | LF | 29,211 | $2.85 | $2.80 | $2.82 |
| 25 | Matl transfer device (40600405) | TON | 5,643 | $4.24 | $3.07 | $3.29 |
| 26 | HMA surf rem butt JT (40600982) | SY | 6,987 | $7.98 | $11.54 | $15.51 |
| 27 | Temporary ramp (40600990) | SY | 600 | $10.29 | $15.02 | $10.71 |
| 28 | HMA BC IL-19.0 N50 (40603080) | TON | 8,093 | $97.90 | $102.54 | $115.38 |
| 29 | P HMA SC IL-9.5 D N50 (40604160) | TON | 6,334 | $117.98 | $126.23 | $137.62 |
| 30 | Bit matls tack CT (40800029) | LB | 2,577 | $0.61 | $3.30 | $0.83 |
| 31 | Incidental HMA surf (40800050) | TON | 791 | $153.29 | $217.00 | $215.19 |
| 32 | HMA surf rem 1 1/2 (44000155) | SY | 69,971 | $1.30 | $1.91 | $2.80 |
| 33 | CL C patch T2 14 (44201403) | SY | 14 | $697.26 | $577.50 | $577.50 |
| 34 | CL C patch T4 14 (44201409) | SY | 67 | $697.26 | $572.25 | $572.25 |
| 35 | Agg wedge SHLD type B (48102100) | TON | 1,669 | $27.38 | $28.88 | $22.07 |
| 36 | HMA shoulders 6 1/2 (48203023) | SY | 16,669 | $35.91 | $40.50 | $45.76 |
| 37 | HMA shoulders (48203100) | TON | 1,693 | $122.67 | $115.06 | $116.05 |
| 38 | Pipe culvert remov (50105220) | LF | 50 | $42.91 | $30.45 | $30.45 |
| 39 | P cul CL D 2 12 (542D1057) | LF | 60 | $85.82 | $45.68 | $45.68 |
| 40 | Cip RC end sec 48 (54215448) | EACH | 2 | $11,263 | $12,075 | $12,075 |
| 41 | Insert cul lin 36 (54390230) | LF | 240 | $252.09 | $294.00 | $294.00 |
| 42 | Flap gate 36 (60801036) | EACH | 1 | $9,868.96 | $18,375 | $18,375 |
| 43 | Conc thrust blocks (61000050) | EACH | 2 | $1,930.89 | $1,102.50 | $1,102.50 |
| 44 | SPBGR TY A 9FT posts (63000003) | LF | 13,543 | $40.76 | $39.90 | $44.38 |
| 45 | LSG OV cul 12'6" span (63000350) | LF | 100 | $49.34 | $48.30 | $46.10 |
| 46 | Traf bar term T2 (63100045) | EACH | 1 | $1,716.34 | $1,680.00 | $2,588.25 |
| 47 | Traf bar term T6 (63100085) | EACH | 4 | $4,827.21 | $4,725.00 | $6,594.00 |
| 48 | TR bar TRM T1 SPL tan (63100167) | EACH | 29 | $3,861.77 | $3,780.00 | $4,079.25 |
| 49 | Guardrail remov (63200310) | LF | 14,943 | $6.44 | $6.30 | $9.19 |
| 50 | Shoulder rum strip 8 (64200108) | LF | 15,212 | $0.56 | $0.36 | $0.61 |
| 51 | Engr field office A (67000400) | CAL MO | 12 | $3,450.00 | $3,009.26 | $3,453.71 |
| 52 | Mobilization (67100100) | LS | 1 | $30,183 | $74,655 | $139,879 |
| 53 | Traf cont-prot 701201 (70100450) | LS | 1 | $107.27 | $18,900 | $34,650 |
| 54 | Traf cont-prot 701306 (70100460) | LS | 1 | $10,137 | $21,842 | $29,230 |
| 55 | Traf cont-prot 701326 (70100500) | LS | 1 | $10,379 | $13,162 | $5,441.96 |
| 56 | Changeable message SN (70107025) | CAL DAY | 14 | $123.36 | $132.37 | $589.65 |
| 57 | Short term pavt mking (70300100) | LF | 8,345 | $1.33 | $1.78 | $2.31 |
| 58 | SHRT TRM pavt MK rem (70300150) | SF | 2,781 | $1.98 | $2.73 | $0.79 |
| 59 | Terminal marker - DA (72501000) | EACH | 29 | $53.64 | $52.50 | $52.50 |
| 60 | Mod ureth PM line 5 (78009005) | LF | 58,028 | $0.53 | $0.51 | $0.51 |
| 61 | Mod ureth PM line 24 (78009024) | LF | 234 | $17.16 | $16.80 | $16.80 |
| 62 | Raised refl pavt MKR (78100100) | EACH | 348 | $56.08 | $54.89 | $54.89 |
| 63 | Grdrail ref type A (78200005) | EACH | 206 | $10.73 | $10.50 | $10.50 |
| 64 | Raised ref PVT MK rem (78300200) | EACH | 348 | $13.92 | $12.51 | $7.15 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.