IDOT contract 72741 bid tabulation

Section 16S(PP,DR). Let by Illinois DOT on April 24, 2026, Sangamon, District 06. 2 bids received; low bid $313,859 by P. H. Broughton & Sons, Inc..

Owner
Illinois DOT
Letting
24 APR 2026
Pay items
32
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1P. H. Broughton & Sons, Inc.$313,859Low
2Phoenix Corporation of the Quad Cities$335,344+7.0%
IDOT contract 72741: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. P. H. Broughton & Sons, Inc.2. Phoenix Corporation of the Quad Cities
1Traf cont-prot BLR 21 (X7011800)LS1$2,500.00$3,248.00
2Detour signing (X7200203)LS1$15,677$3,920.00
3Construction layout (Z0013798)LS1$17,419$10,000
4RR prot liability ins (Z0048665)LS1$7,257.94$5,000.00
5Earth excavation (20200100)CY150$67.61$54.00
6Trench backfill (20800150)CY50$92.10$103.00
7Bit matls tack CT (40600290)LB1,267$2.00$3.08
8Long joint sealant (40600370)LF1,056$14.81$12.75
9Temporary ramp (40600990)SY36$14.00$25.00
10HMA SC IL-9.5 C N50 (40604050)TON315$161.98$223.19
11HMA surf rem 2 (44000157)SY2,816$5.75$7.50
12Comb curb gutter rem (44000500)LF477$11.59$33.00
13Pavt patch T2 17 (44200202)SY9$605.26$525.00
14Storm sew CL A 1 15 (550A0070)LF167$157.08$107.00
15Storm sew CL A 1 18 (550A0090)LF42$169.31$121.00
16Storm sewer rem 12 (55100500)LF119$12.65$28.50
17Storm sewer rem 15 (55100700)LF50$13.30$30.00
18Storm sewer rem 18 (55100900)LF42$14.05$35.00
19Man TA 5 dia T3F&G (60221200)EACH1$7,500.00$6,400.00
20Inlets TB T3F&G (60240220)EACH5$2,500.00$4,000.00
21Remov inlets (60500060)EACH6$150.00$525.00
22Comb CC&G TB9.24 aep (60607500)LF477$119.62$130.00
23Mobilization (67100100)LS1$18,376$26,225
24Traf cont-prot 701201 (70100450)LS1$116.12$750.00
25Traf cont-prot 701306 (70100460)LS1$929.02$750.00
26Traf cont-prot 701326 (70100500)LS1$1,393.52$750.00
27Changeable message SN (70107025)CAL DAY40$100.00$75.00
28Short term pavt mking (70300100)LF212$8.04$3.00
29SHRT TRM pavt MK rem (70300150)SF71$7.07$6.75
30Mod ureth PM line 5 (78009005)LF4,224$3.21$2.76
31Raised refl pavt MKR (78100100)EACH14$327.48$282.00
32Raised ref PVT MK rem (78300200)EACH14$11.61$50.00
IDOT contract 72741: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy