IDOT contract 76L46 bid tabulation
Section 133RS-7. Let by Illinois DOT on January 17, 2025, Madison, District 08. 2 bids received; low bid $619,161 by Charles E. Mahoney Co..
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 35
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Charles E. Mahoney Co. | $619,161 | Low |
| 2 | Christ Bros. Asphalt, Inc. | $639,451 | +3.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Charles E. Mahoney Co. | 2. Christ Bros. Asphalt, Inc. |
|---|---|---|---|---|---|
| 1 | Earth excavation (20200100) | CY | 15 | $72.00 | $92.00 |
| 2 | Trench backfill (20800150) | CY | 24 | $104.00 | $124.00 |
| 3 | Stone riprap CL B3 (28100225) | TON | 6 | $315.00 | $335.00 |
| 4 | Filter fabric (28200200) | SY | 17 | $20.00 | $20.00 |
| 5 | Agg base cse B 6 (35101800) | SY | 36 | $53.00 | $73.00 |
| 6 | Bit matls tack CT (40600290) | LB | 7,656 | $2.50 | $2.94 |
| 7 | Long joint sealant (40600370) | LF | 8,208 | $3.75 | $3.67 |
| 8 | Temporary ramp (40600990) | SY | 64 | $28.27 | $0.01 |
| 9 | HMA BC IL-19.0 N70 (40603085) | TON | 2 | $1,026.37 | $138.04 |
| 10 | HMA SC IL-9.5L C N30 (40604090) | TON | 300 | $127.90 | $138.04 |
| 11 | P HMA SC IL-9.5 D N70 (40604162) | TON | 1,432 | $169.54 | $138.04 |
| 12 | PC conc sidewalk 4 (42400100) | SF | 80 | $42.00 | $62.00 |
| 13 | HMA surf rem 1 1/2 (44000155) | SY | 20,576 | $4.44 | $3.82 |
| 14 | Drive pavement rem (44000200) | SY | 24 | $27.00 | $47.00 |
| 15 | CL B patch T2 12 (44200994) | SY | 37 | $394.00 | $394.00 |
| 16 | Dowel bars 1 1/2 (44201299) | EACH | 42 | $34.00 | $34.00 |
| 17 | CL D patch T1 12 (44201785) | SY | 5 | $1,102.20 | $492.00 |
| 18 | Saw cuts (44213200) | LF | 84 | $50.00 | $25.00 |
| 19 | Agg wedge SHLD type B (48102100) | TON | 30 | $236.14 | $98.33 |
| 20 | Pipe culvert remov (50105220) | LF | 76 | $41.00 | $61.00 |
| 21 | P cul CL D 1 18 (542D0223) | LF | 92 | $74.00 | $94.00 |
| 22 | Steel FL end sec 18" (54261718) | EACH | 4 | $2,300.00 | $3,300.00 |
| 23 | Mobilization (67100100) | LS | 1 | $54,333 | $59,844 |
| 24 | TR cont & prot 701502 (70102622) | LS | 1 | $21,914 | $58,950 |
| 25 | Changeable message SN (70107025) | CAL DAY | 56 | $89.00 | $99.00 |
| 26 | Short term pavt mking (70300100) | LF | 1,500 | $3.14 | $3.93 |
| 27 | SHRT TRM pavt MK rem (70300150) | SF | 251 | $11.15 | $0.01 |
| 28 | Temp PVT MK LTR & sym paint (70300211) | SF | 655 | $0.01 | $0.01 |
| 29 | Remov sign panel T1 (72400310) | SF | 3 | $30.00 | $30.00 |
| 30 | Reloc sign panel T1 (72400710) | SF | 3 | $30.00 | $30.00 |
| 31 | THPL PVT MK LTR & sym (78000100) | SF | 655.20 | $15.00 | $10.65 |
| 32 | THPL PVT MK line 6 (78000400) | LF | 18,496 | $0.79 | $2.85 |
| 33 | Raised refl pavt MKR (78100100) | EACH | 214 | $68.21 | $61.95 |
| 34 | Raised ref PVT MK rem (78300200) | EACH | 214 | $5.60 | $0.01 |
| 35 | PVT MKG rem WTR blast (78300202) | SF | 6,167 | $0.01 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.