INDOT contract B-45691-A bid tabulation
DEBRIS REMOVAL FROM CHANNEL. Let by Indiana DOT on April 9, 2025, Vigo, Crawfordsville. 2 bids received; low bid $759,805 by Yarberry Companies Inc.
- Owner
- Indiana DOT
- Letting
- 09 APR 2025
- Pay items
- 13
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Yarberry Companies Inc | $759,805 | Low |
| 2 | Collom Excavating LLC | $1,348,405 | +77% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Yarberry Companies Inc | 2. Collom Excavating LLC |
|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $10,000 | $50,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 |
| 0007 | Mobilization and demobilization (110-01001) | LS | 1 | $36,000 | $105,000 |
| 0008 | Debris, remove, structure no. 1 (201-90788) | LS | 1 | $70,000 | $338,000 |
| 0009 | Debris, remove, structure no. 2 (201-90788) | LS | 1 | $60,000 | $302,000 |
| 0010 | Excavation, waterway (203-51223) | CYS | 1,660 | $330.00 | $240.00 |
| 0011 | Construction sign, type C (801-03290) | EACH | 4 | $600.00 | $500.00 |
| 0012 | Construction sign, type D (801-03291) | EACH | 6 | $600.00 | $500.00 |
| 0013 | Maintaining traffic (801-06775) | LS | 1 | $30,000 | $150,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of April 9, 2025. Compiled by Mirage Metrics.