Line, multi-component, broken, yellow, 4 in. unit price, Indiana

Low bidders on INDOT contracts carried a median of $0.86 per LFT for item 808-10036, line, multi-component, broken, yellow, 4 in., over the 24 months to 05 NOV 2026, across 14 low bids. Half of all 63 bids fell between $0.66 and $2.33.

Owner
Indiana DOT
Item
808-10036
Unit
LFT
Latest letting
07 OCT 2026
$0.86Low bidder's median, per LFT
$1.30Median of all bids, per LFT
14Contracts in the window

By year of letting

Line, multi-component, broken, yellow, 4 in., INDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20222323$1.0060$1.39
20231010$1.1233$1.50
202455$1.0017$1.00
202566$1.6022$1.94
202688$0.5941$0.68
Line, multi-component, broken, yellow, 4 in., INDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Line, multi-component, broken, yellow, 4 in., INDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Fort Wayne8$1.0535$1.50
LaPorte4$0.6818$0.68
Line, multi-component, broken, yellow, 4 in., INDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Line, multi-component, broken, yellow, 4 in., INDOT: low bidder's median by quantity band
Quantity (LFT)Low bidsLow-bid median
50 to 843$4.44
95 to 1984$1.21
215 to 2,0943$0.68
4,557 to 99,0904$0.39
Line, multi-component, broken, yellow, 4 in., INDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest INDOT contracts carrying Line, multi-component, broken, yellow, 4 in.
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
07 OCT 2026B-44532-AFort Wayne50$3.00$3.004MILESTONE CONTRACTORS LPINDOT
07 OCT 2026T-45532-AFort Wayne4,557$0.40$0.556CE HUGHES MILLING INCINDOT
02 SEP 2026B-44107-ALaPorte356$0.68$0.686ELLAS CONSTRUCTION COMPANY INCINDOT
02 SEP 2026B-44108-ALaPorte120$0.68$0.687ELLAS CONSTRUCTION COMPANY INCINDOT
11 FEB 2026T-45895-AFort Wayne6,026$0.38$0.483CE HUGHES MILLING INCINDOT
11 FEB 2026T-46041-ALaPorte39,598$0.35$0.483CE HUGHES MILLING INCINDOT
14 JAN 2026B-42792-AGreenfield142$1.37$1.307PONTEM CONTRACTORS INCINDOT
14 JAN 2026T-45900-AFort Wayne99,090$0.50$0.625GRIDLOCK TRAFFIC SYSTEMS INCINDOT
10 DEC 2025R-42000-AFort Wayne60$4.61$4.644HRP CONSTRUCTION INCINDOT
10 SEP 2025B-42838-AFort Wayne215$1.50$1.505MILESTONE CONTRACTORS LPINDOT
10 SEP 2025T-44858-ACrawfordsville198$1.05$2.803ROADSAFE TRAFFIC SYSTEMS INCINDOT
06 AUG 2025B-42843-AFort Wayne95$1.70$1.575DUNCAN ROBERTSON INCINDOT
07 MAY 2025R-43589-ALaPorte84$4.44$4.442MILESTONE CONTRACTORS LPINDOT
15 JAN 2025R-44290-AFort Wayne2,094$0.60$0.603E & B PAVING LLCINDOT
11 SEP 2024R-41955-AFort Wayne690$1.00$1.002E & B PAVING LLCINDOT
Latest INDOT contracts carrying Line, multi-component, broken, yellow, 4 in.

Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.

How these prices were read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way