Transverse marking, multi-component, crosswalk line, white, 6 in. unit price, Indiana
Low bidders on INDOT contracts carried a median of $5.00 per LFT for item 808-10056, transverse marking, multi-component, crosswalk line, white, 6 in., over the 24 months to 05 NOV 2026, across 16 low bids. Half of all 63 bids fell between $4.75 and $6.00.
- Owner
- Indiana DOT
- Item
- 808-10056
- Unit
- LFT
- Latest letting
- 05 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 11 | 11 | $5.55 | 21 | $5.00 |
| 2023 | 9 | 9 | $5.00 | 20 | $5.00 |
| 2024 | 9 | 9 | $5.00 | 26 | $5.00 |
| 2025 | 8 | 8 | $5.61 | 24 | $5.91 |
| 2026 | 6 | 6 | $4.75 | 30 | $5.69 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Fort Wayne | 7 | $5.31 | 20 | $6.00 |
| LaPorte | 4 | $3.37 | 15 | $5.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LFT) | Low bids | Low-bid median |
|---|---|---|
| 54 to 246 | 4 | $5.96 |
| 367 to 434 | 4 | $5.50 |
| 481 to 862 | 4 | $5.00 |
| 1,077 to 2,852 | 4 | $2.99 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 05 NOV 2026 | R-44293-A | Seymour | 54 | $9.95 | $6.00 | 7 | RIVER TOWN CONSTRUCTION, LLC | INDOT |
| 07 OCT 2026 | R-44652-A | LaPorte | 2,852 | $0.60 | $0.60 | 2 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 08 APR 2026 | R-43094-A | Greenfield | 1,077 | $4.50 | $4.50 | 4 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 08 APR 2026 | T-43855-A | Fort Wayne | 862 | $2.50 | $4.25 | 4 | AMERICA'S PARKING REMARKING, LLC | INDOT |
| 11 MAR 2026 | R-44130-A | Greenfield | 367 | $5.00 | $5.00 | 11 | OLCO INC | INDOT |
| 14 JAN 2026 | R-43844-A | Fort Wayne | 371 | $7.00 | $7.00 | 2 | MILESTONE CONTRACTORS LP | INDOT |
| 10 SEP 2025 | R-43800-A | Fort Wayne | 689 | $6.00 | $6.00 | 2 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 06 AUG 2025 | R-43984-A | Vincennes | 434 | $6.00 | $6.00 | 3 | MILESTONE CONTRACTORS LP | INDOT |
| 09 JUL 2025 | R-43802-A | Fort Wayne | 1,126 | $5.31 | $5.31 | 3 | BROOKS CONSTRUCTION COMPANY INC | INDOT |
| 07 MAY 2025 | B-43636-A | LaPorte | 160 | $5.91 | $5.91 | 5 | SUPERIOR CONSTRUCTION CO INC | INDOT |
| 12 MAR 2025 | R-43174-A | LaPorte | 566 | $5.00 | $5.00 | 3 | MILESTONE CONTRACTORS LP | INDOT |
| 12 FEB 2025 | R-45431-A | Fort Wayne | 383 | $3.94 | $6.00 | 3 | PHEND & BROWN INC | INDOT |
| 15 JAN 2025 | R-42198-A | Vincennes | 1,589 | $1.48 | $1.48 | 3 | E & B PAVING LLC | INDOT |
| 15 JAN 2025 | R-45434-A | Fort Wayne | 77 | $6.00 | $6.00 | 2 | BROOKS CONSTRUCTION COMPANY INC | INDOT |
| 11 DEC 2024 | R-41395-A | Fort Wayne | 481 | $5.00 | $5.00 | 4 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.
How these prices were read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.