Low bidders on INDOT contracts carried a median of $14.00 per LFT for item 808-10051, transverse marking, multi-component, stop line, white, 24 in., over the 24 months to 05 NOV 2026, across 63 low bids. Half of all 213 bids fell between $12.00 and $16.00.
- Owner
- Indiana DOT
- Item
- 808-10051
- Unit
- LFT
- Latest letting
- 05 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 21 | 21 | $14.00 | 48 | $13.25 |
| 2023 | 26 | 26 | $17.50 | 62 | $18.00 |
| 2024 | 34 | 34 | $13.57 | 105 | $14.49 |
| 2025 | 25 | 25 | $14.02 | 80 | $14.28 |
| 2026 | 35 | 35 | $12.62 | 121 | $14.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Fort Wayne | 23 | $14.34 | 74 | $14.64 |
| LaPorte | 17 | $13.61 | 48 | $13.80 |
| Greenfield | 7 | $12.00 | 37 | $19.95 |
| Seymour | 8 | $13.72 | 30 | $14.00 |
| Vincennes | 6 | $15.51 | 16 | $15.51 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LFT) | Low bids | Low-bid median |
|---|---|---|
| 16 to 38 | 15 | $14.00 |
| 43 to 132 | 16 | $14.11 |
| 135 to 302 | 16 | $13.53 |
| 310 to 1,642 | 16 | $11.63 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 05 NOV 2026 | R-43809-A | LaPorte | 25 | $11.02 | $11.02 | 3 | F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES LLC | INDOT |
| 07 OCT 2026 | R-44279-A | Seymour | 135 | $16.00 | $16.00 | 4 | MILESTONE CONTRACTORS LP | INDOT |
| 07 OCT 2026 | R-44652-A | LaPorte | 1,183 | $14.00 | $14.00 | 2 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 07 OCT 2026 | B-44576-A | Greenfield | 24 | $11.43 | $19.95 | 5 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 07 OCT 2026 | T-45532-A | Fort Wayne | 653 | $8.00 | $13.00 | 6 | CE HUGHES MILLING INC | INDOT |
| 02 SEP 2026 | B-44473-A | Seymour | 60 | $14.00 | $14.00 | 5 | FORCE CONSTRUCTION CO INC | INDOT |
| 02 SEP 2026 | T-44365-C | Vincennes | 699 | $11.27 | $40.00 | 3 | RAGLE, INC. | INDOT |
| 02 SEP 2026 | T-44477-A | Seymour | 35 | $6.95 | $12.97 | 4 | MIDWESTERN ELECTRIC, LLC | INDOT |
| 02 SEP 2026 | T-45968-A | Fort Wayne | 976 | $15.00 | $15.00 | 5 | MICHIANA CONTRACTING, INC. | INDOT |
| 02 SEP 2026 | T-45970-A | Fort Wayne | 195 | $12.04 | $12.04 | 1 | MICHIANA CONTRACTING, INC. | INDOT |
| 05 AUG 2026 | B-44407-A | Seymour | 144 | $13.45 | $12.50 | 4 | MILESTONE CONTRACTORS LP | INDOT |
| 05 AUG 2026 | B-44526-A | Fort Wayne | 67 | $12.11 | $12.11 | 2 | MILESTONE CONTRACTORS LP | INDOT |
| 08 JUL 2026 | R-43130-A | LaPorte | 130 | $12.62 | $12.62 | 2 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
| 08 JUL 2026 | R-43623-A | Fort Wayne | 24 | $23.00 | $20.00 | 5 | FLEMING EXCAVATING INC | INDOT |
| 08 JUL 2026 | R-45569-A | Fort Wayne | 182 | $15.00 | $17.50 | 2 | RIETH-RILEY CONSTRUCTION CO., INC. | INDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the INDOT explorer.
How these prices were read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are INDOT's own: this item is compared with INDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.