Iowa DOT contract 61-0924-030 bid tabulation
Reconstruction - Bridge Deck Replacement - IOWA 92 Middle River 2.0 mi W of Co Rd P53. Let by Iowa DOT on October 20, 2026, Madison. 7 bids received; low bid $930,065 by Louis-Company, LLC..
- Owner
- Iowa DOT
- Letting
- 20 OCT 2026
- Pay items
- 39
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Louis-Company, LLC. | $930,065 | Low |
| 2 | Peterson Contractors Inc. | $1,072,074 | +15% |
| 3 | Herberger Construction Co., Inc. | $1,134,945 | +22% |
| 4 | Cramer and Assoc., Inc. | $1,171,085 | +26% |
| 5 | Jorgensen Contracting Co. | $1,294,136 | +39% |
| 6 | Iowa Civil Contracting, Inc. | $1,487,673 | +60% |
| 7 | Jasper Construction Services, Inc. | $1,575,198 | +69% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Louis-Company, LLC. | 2. Peterson Contractors Inc. | 3. Herberger Construction Co., Inc. | 4. Cramer and Assoc., Inc. | 5. Jorgensen Contracting Co. | 6. Iowa Civil Contracting, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Removals, as per plan (2401-6750001) | LS | 1 | $80,000 | $98,000 | $120,000 | $174,000 | $146,000 | $209,608 |
| 0020 | Excavation, class 20 (2402-2720000) | CY | 28.20 | $32.56 | $255.00 | $160.00 | $140.00 | $260.00 | $197.41 |
| 0030 | Structural concrete (bridge) (2403-0100010) | CY | 237.10 | $997.99 | $1,205.00 | $1,361.00 | $1,400.00 | $1,850.00 | $1,540.04 |
| 0040 | Fiber reinforcement for structural concrete (2403-1000005) | CY | 233.70 | $30.00 | $28.00 | $26.00 | $25.00 | $30.00 | $43.09 |
| 0050 | Trial batch and test placement (fiber reinforced concrete) (2403-1000010) | LS | 1 | $3,429.51 | $10,600 | $5,000.00 | $1,200.00 | $8,800.00 | $8,846.32 |
| 0060 | Reinforcing steel, epoxy coated (2404-7775005) | LB | 88,068 | $1.59 | $1.27 | $1.95 | $1.30 | $1.41 | $2.35 |
| 0070 | Reinforcing steel, stainless steel (2404-7775009) | LB | 4,175 | $4.52 | $3.52 | $5.60 | $4.00 | $4.12 | $6.69 |
| 0080 | Structural steel (2408-7800000) | LB | 611 | $16.77 | $26.50 | $14.00 | $25.00 | $16.00 | $67.01 |
| 0090 | Concrete barrier railing (2414-6424110) | LF | 433 | $112.40 | $100.00 | $92.00 | $89.02 | $89.02 | $129.14 |
| 0100 | Deck drains (2499-2300001) | LS | 1 | $10,547 | $44,000 | $50,000 | $45,000 | $48,000 | $101,194 |
| 0110 | Subdrain, standard, perforated, 4 in., as per plan (2502-8212304) | LF | 69.50 | $18.76 | $44.00 | $120.00 | $80.00 | $87.00 | $48.32 |
| 0120 | Bank shaping (2507-6799000) | LS | 1 | $1,836.33 | $8,000.00 | $3,000.00 | $6,000.00 | $10,000 | $17,905 |
| 0130 | Construction survey, location survey (2526-8285040) | LS | 1 | $7,647.19 | $8,000.00 | $8,500.00 | $6,000.00 | $6,000.00 | $10,250 |
| 0140 | Mobilization (2533-4980005) | LS | 1 | $30,665 | $100,000 | $65,000 | $110,000 | $120,000 | $54,500 |
| 0150 | Special backfill (2102-0425070) | TON | 75.18 | $67.89 | $115.00 | $73.00 | $243.29 | $70.00 | $72.65 |
| 0160 | Embankment-in-place (2102-2625000) | CY | 51.10 | $30.38 | $53.00 | $39.00 | $60.17 | $38.00 | $91.23 |
| 0170 | Excavation, class 10, roadway and borrow (2102-2710070) | CY | 176.90 | $10.38 | $46.00 | $19.00 | $24.85 | $8.00 | $36.51 |
| 0180 | Excavation, class 13, waste (2102-2713090) | CY | 23.60 | $38.91 | $52.00 | $50.00 | $62.08 | $13.25 | $51.18 |
| 0190 | Granular shoulders, type B (2121-7425020) | TON | 1.96 | $690.20 | $700.00 | $400.00 | $407.43 | $200.00 | $63.93 |
| 0200 | Paved shoulder, hot mix asphalt mixture, 9 in. (2122-5500090) | SY | 192.30 | $221.57 | $166.00 | $180.00 | $165.00 | $173.00 | $141.15 |
| 0210 | Shoulder construction, earth (2123-7450000) | STA | 5.91 | $621.43 | $915.00 | $350.00 | $850.00 | $325.00 | $700.74 |
| 0220 | Bridge approach, BR-203 (2301-0690203) | SY | 548.20 | $287.65 | $278.00 | $255.00 | $260.00 | $315.00 | $334.91 |
| 0230 | Longitudinal grooving in concrete, bridge deck and/or approaches (2412-0000100) | SY | 686.30 | $12.75 | $5.55 | $11.00 | $6.00 | $6.00 | $17.21 |
| 0240 | Bridge end drain, DR-402 (2503-0500402) | EACH | 4 | $4,493.73 | $6,600.00 | $4,800.00 | $3,800.00 | $2,800.00 | $8,510.43 |
| 0250 | Removal of steel beam guardrail (2505-4008120) | LF | 454.40 | $19.12 | $11.25 | $14.00 | $12.90 | $17.00 | $10.00 |
| 0260 | Steel beam guardrail (2505-4008300) | LF | 150 | $38.24 | $23.00 | $23.00 | $23.00 | $30.00 | $25.30 |
| 0270 | Steel beam guardrail barrier transition section, BA-201 (2505-4008410) | EACH | 4 | $4,460.87 | $3,000.00 | $3,000.00 | $3,000.00 | $2,900.00 | $3,300.00 |
| 0280 | Steel beam guardrail end anchor, bolted (2505-4021010) | EACH | 4 | $446.09 | $300.00 | $300.00 | $300.00 | $290.00 | $330.00 |
| 0290 | Steel beam guardrail tangent end terminal, BA-205 (2505-4021720) | EACH | 4 | $4,557.73 | $3,300.00 | $3,300.00 | $3,300.00 | $3,750.00 | $3,630.00 |
| 0300 | Removal of pavement (2510-6745850) | SY | 615.50 | $11.00 | $24.25 | $39.00 | $25.00 | $21.00 | $39.43 |
| 0310 | Remove and reinstall sign as per plan (2524-6765010) | EACH | 2 | $318.64 | $250.00 | $320.00 | $300.00 | $300.00 | $275.00 |
| 0320 | Perforated square steel tube posts (2524-9276010) | LF | 26 | $38.24 | $30.00 | $12.80 | $12.00 | $12.00 | $33.00 |
| 0330 | Perforated square steel tube post anchor, break-away soil installation (2524-9276021) | EACH | 2 | $254.91 | $200.00 | $160.00 | $150.00 | $150.00 | $220.00 |
| 0340 | Painted pavement markings, waterborne or solvent-based (2527-9263209) | STA | 11.51 | $350.50 | $275.00 | $260.00 | $250.00 | $250.00 | $302.50 |
| 0350 | Safety closure (2528-2518000) | EACH | 2 | $127.46 | $100.00 | $100.00 | $100.00 | $100.00 | $107.50 |
| 0360 | Traffic control (2528-8445110) | LS | 1 | $14,530 | $13,600 | $10,500 | $9,965.00 | $9,965.00 | $12,540 |
| 0370 | Longitudinal grooving in concrete, pavement (2557-0000100) | SY | 497.40 | $13.51 | $5.55 | $11.00 | $6.00 | $6.00 | $18.72 |
| 0380 | Perimeter and slope sediment control device, 12 in. dia. (2602-0000312) | LF | 790 | $4.78 | $1.75 | $1.75 | $1.75 | $4.00 | $1.93 |
| 0390 | Removal of perimeter and slope or ditch check sediment control device (2602-0000351) | LF | 790 | $0.38 | $0.30 | $0.30 | $0.30 | $1.00 | $0.33 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from Iowa DOT's tabulation for this contract. Iowa DOT bid tabulation PDFs: the letting of 19 January 2022 (read from the Internet Archive's copy of Iowa DOT's file) and lettings of August to October 2026. On A+B contracts the item total is kept and the time part dropped. Bids that did not match their published total are left out.
Every contract let that day: Iowa DOT letting of October 20, 2026. Compiled by Mirage Metrics.