KYTC contract 25-1031 bid tabulation
UTILITY ADJUSTMENT I-24. Let by Kentucky Transportation Cabinet on October 23, 2025. 1 bid received; low bid $1,224,852 by Roe Enterprises Inc DBA Swartz Pipeline Contracting, -24% against the engineer's estimate of $1,609,918.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 OCT 2025
- Pay items
- 30
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Roe Enterprises Inc DBA Swartz Pipeline Contracting | $1,224,852 | Low | -24% |
Engineer's estimate: $1,609,918.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Roe Enterprises Inc DBA Swartz Pipeline Contracting |
|---|---|---|---|---|
| 0010 | Dga base | TON A A | 140 | $58.00 |
| 0020 | Fence-8 FT chain link | LF A A | 104 | $80.00 |
| 0030 | Double vehicular chain link gate | EACH A A | 1 | $2,500.00 |
| 0040 | Maintain & control traffic | LS A A | 1 | $5,000.00 |
| 0050 | Staking | LS A A | 1 | $2,000.00 |
| 0060 | W air release valve 3/4 inch | EACH A A | 6 | $850.00 |
| 0070 | W fire hydrant assembly | EACH A A | 2 | $12,500 |
| 0080 | W flush hydrant assembly | EACH A A | 1 | $4,500.00 |
| 0090 | W meter 1-1/2 inch | EACH A A | 1 | $8,400.00 |
| 0100 | W pipe PVC 06 inch | LF A A | 3,438 | $62.00 |
| 0110 | W service special | EACH A A | 1 | $2,800.00 |
| 0120 | W structure abandonment | EACH A A | 1 | $1,200.00 |
| 0130 | W structure removal | EACH A A | 8 | $1,500.00 |
| 0140 | W tapping sleeve and valve size 2 | EACH A A | 1 | $8,500.00 |
| 0150 | W valve 04 inch | EACH A A | 1 | $2,400.00 |
| 0160 | W valve 06 inch | EACH A A | 1 | $2,600.00 |
| 0170 | W line marker | EACH A A | 7 | $50.00 |
| 0180 | W meter vault size range 1 | EACH A A | 1 | $85,000 |
| 0190 | S force main air RLS/vac VLV 02 in | EACH A A | 8 | $15,000 |
| 0200 | S force main PVC 04 inch | LF A A | 5,057 | $58.00 |
| 0210 | S force main tie-in 04 inch | EACH A A | 1 | $2,500.00 |
| 0220 | S manhole | EACH A A | 1 | $9,800.00 |
| 0230 | S manhole casting standard | EACH A A | 1 | $850.00 |
| 0240 | S manhole tap existing | EACH A A | 1 | $500.00 |
| 0250 | S pipe PVC 08 inch | LF A A | 16 | $450.00 |
| 0260 | S pump station | EACH A A | 1 | $195,000 |
| 0270 | S special item | EACH A A | 2 | $80,000 |
| 0280 | S structure removal | EACH A A | 10 | $2,000.00 |
| 0290 | S line marker | EACH A A | 10 | $50.00 |
| 0300 | Demobilization | LS A A | 1 | $18,250 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.