KYTC contract 25-1112 bid tabulation
ASPHALT SURFACE WITH GUARDRAIL US 150 (150). Let by Kentucky Transportation Cabinet on August 21, 2025. 1 bid received; low bid $893,898 by L-M Asphalt Partners LTD D/B/A Ats Construction, -4.0% against the engineer's estimate of $931,358.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 AUG 2025
- Pay items
- 77
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $893,898 | Low | -4.0% |
Engineer's estimate: $931,358.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. L-M Asphalt Partners LTD D/B/A Ats Construction |
|---|---|---|---|---|
| 0010 | Asphalt seal aggregate | TON A A | 53 | $230.00 |
| 0020 | Asphalt seal coat | TON A A | 6.40 | $1,100.00 |
| 0030 | CL3 asph base 1.00D PG64-22 | TON A A | 61 | $175.00 |
| 0040 | CL3 asph surf 0.38B PG64-22 | TON A A | 2,765 | $125.00 |
| 0050 | Mobilization for mill & text | LS A A | 1 | $3,500.00 |
| 0060 | Asphalt pave milling & texturing | TON A A | 2,826 | $25.00 |
| 0070 | Joint adhesive | LF A A | 12,006 | $0.01 |
| 0080 | Pave mount infrared temp equipment | SF A A | 301,617 | $0.01 |
| 0090 | Asphalt material for tack non-tracking | TON A A | 12 | $10.00 |
| 0100 | Geocomposite reinforcement for asphalt | SQYD A A | 247 | $25.00 |
| 0110 | Crushed aggregate size no 57 | TON A A | 57 | $60.00 |
| 0120 | Crushed aggregate size no 2 | TON A A | 113 | $60.00 |
| 0130 | Leveling & wedging PG64-22 | TON A A | 15 | $200.00 |
| 0140 | Perforated pipe-4 in | LF A A | 600 | $18.00 |
| 0150 | Delineator for guardrail BI directional white | EACH A A | 36 | $13.00 |
| 0160 | Temp ditch | LF A A | 4,707 | $0.01 |
| 0170 | Clean temp ditch | LF A A | 2,345 | $0.01 |
| 0180 | Ditching | LF A A | 150 | $60.00 |
| 0190 | Water | MGAL A A | 357 | $0.01 |
| 0200 | Guardrail terminal section no 1 | EACH A A | 2 | $85.00 |
| 0210 | Guardrail end treatment type 1 | EACH A A | 4 | $4,000.00 |
| 0220 | Remove guardrail | LF A A | 2,275 | $4.25 |
| 0230 | Remove guardrail end treatment | EACH A A | 4 | $500.00 |
| 0240 | Temporary signs | SQFT A A | 114 | $12.00 |
| 0250 | Fabric-geotextile class 2 | SQYD A A | 200 | $8.00 |
| 0260 | Maintain & control traffic | LS A A | 1 | $55,000 |
| 0270 | Portable changeable message sign | EACH A A | 2 | $1,134.20 |
| 0280 | Edgeline rumble strips | LF A A | 11,692 | $0.48 |
| 0290 | Temp silt fence | LF A A | 4,707 | $0.01 |
| 0300 | Silt trap type B | EACH A A | 2 | $525.00 |
| 0310 | Silt trap type C | EACH A A | 2 | $535.00 |
| 0320 | Clean silt trap type B | EACH A A | 2 | $0.01 |
| 0330 | Clean silt trap type C | EACH A A | 2 | $0.01 |
| 0340 | Staking | LS A A | 1 | $25,000 |
| 0350 | Erosion control blanket | SQYD A A | 40 | $15.00 |
| 0360 | Temp mulch | SQYD A A | 162 | $0.33 |
| 0370 | Temp seeding and protection | SQYD A A | 121 | $0.35 |
| 0380 | Initial fertilizer | TON A A | 0.10 | $1,800.00 |
| 0390 | Maintenance fertilizer | TON A A | 0.10 | $1,900.00 |
| 0400 | Seeding and protection | SQYD A A | 242 | $5.75 |
| 0410 | Agricultural limestone | TON A A | 0.20 | $85.00 |
| 0420 | Pave striping-temp paint-6 in | LF A A | 84,160 | $0.30 |
| 0430 | Pave striping-thermo-6 in W | LF A A | 19,464 | $1.25 |
| 0440 | Pave striping-thermo-6 in Y | LF A A | 22,616 | $1.25 |
| 0450 | Pave marking-thermo stop bar-24IN | LF A A | 85 | $12.00 |
| 0460 | Pave marking-thermo cross-hatch | SQFT A A | 6,451 | $5.00 |
| 0470 | Pave marking-thermo curv arrow | EACH A A | 19 | $120.00 |
| 0480 | Pave mark temp paint stop bar | LF A A | 44 | $6.00 |
| 0490 | Pave mark temp paint line arrow | EACH A A | 19 | $90.00 |
| 0500 | Object marker TY 3 | EACH A A | 4 | $450.00 |
| 0510 | Remove & relocate signs | EACH A A | 1 | $800.00 |
| 0520 | Centerline rumble strips | LF A A | 6,459 | $0.45 |
| 0530 | Relocate signal head | EACH A A | 1 | $250.00 |
| 0540 | G/R steel W beam-S face (7 FT post) | LF A A | 2,275 | $31.00 |
| 0550 | Clean | LF A A | 100 | $100.00 |
| 0560 | Barcode sign inventory | EACH A A | 11 | $65.00 |
| 0570 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 |
| 0580 | Storm sewer pipe-18 in | LF A A | 8 | $645.00 |
| 0590 | Remove pipe | LF A A | 4 | $400.00 |
| 0600 | Sloped box outlet type 1-18 in | EACH A A | 1 | $1,900.00 |
| 0610 | Curb box inlet type A mod | EACH A A | 1 | $10,750 |
| 0620 | Drop box inlet type 13G | EACH A A | 1 | $8,000.00 |
| 0630 | Cap drop box inlet | EACH A A | 1 | $4,000.00 |
| 0640 | Remove drop box inlet | EACH A A | 1 | $2,300.00 |
| 0650 | Junction box | EACH A A | 1 | $4,500.00 |
| 0660 | Remove headwall | EACH A A | 1 | $1,300.00 |
| 0670 | Conduit-1 in | LF A A | 10 | $4.79 |
| 0680 | Electrical junction box type B | EACH A A | 1 | $2,500.00 |
| 0690 | Trenching and backfilling | LF A A | 60 | $10.00 |
| 0700 | Loop wire | LF A A | 350 | $0.30 |
| 0710 | Cable-no. 14/1 pair | LF A A | 225 | $2.11 |
| 0720 | Loop saw slot and fill | LF A A | 150 | $24.40 |
| 0730 | SBM alum sheet signs .080 in | SQFT A A | 47.75 | $80.00 |
| 0740 | Steel post type 2 | LF A A | 133 | $68.00 |
| 0750 | PVC conduit-1 1/4 in-schedule 80 | LF A A | 50 | $1.40 |
| 0760 | Loop test | EACH A A | 1 | $2,500.00 |
| 0770 | Demobilization | LS A A | 1 | $13,211 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.