KYTC contract 25-2043 bid tabulation
PAVEMENT (WITH ALTERNATES) KY 3005, US 62, KY 259, & KY 79 (VARIOUS COUNTIES). Let by Kentucky Transportation Cabinet on January 23, 2025, Breckinridge, Grayson, Hardin, District 4. 2 bids received; low bid $1,244,023 by Scotty'S Contracting & Stone LLC, -18% against the engineer's estimate of $1,515,014.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 JAN 2025
- Pay items
- 52
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $1,244,023 | Low | -18% |
| 2 | Strawser Construction Inc | $1,775,771 | +43% | +17% |
Engineer's estimate: $1,515,014.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Strawser Construction Inc |
|---|---|---|---|---|---|
| 0010 | Pave striping-temp paint-4 in | LF A | 70,187 | $0.36 | |
| 0020 | Microsurfacing-leveling course | SQYD A | 151,995 | $3.37 | |
| 0030 | Microsurfacing-surface course - type B | SQYD A | 135,088 | $3.64 | |
| 0040 | Microsurfacing-surface course - type D | SQYD A | 20,578 | $5.04 | |
| 0050 | Leveling & wedging PG64-22 | TON A | 714 | $89.95 | |
| 0060 | Asphalt material for tack | TON A | 73 | $0.01 | |
| 0070 | Mobilization for mill & text | LS A | 1 | $1,450.00 | |
| 0080 | Mobilization for mill & text | LS A | 1 | $1,450.00 | |
| 0090 | Mobilization for mill & text | LS A | 1 | $1,450.00 | |
| 0100 | Mobilization for mill & text | LS A | 1 | $1,450.00 | |
| 0110 | Asphalt pave milling & texturing | TON A | 60 | $67.75 | |
| 0120 | Pave striping-temp paint-4 in | LF A | 25,000 | $0.31 | |
| 0130 | CL2 asph surf no.4D PG64-22 | TON A | 715 | $101.40 | |
| 0140 | CL3 asph surf no.4B PG64-22 | TON A | 5,675 | $109.15 | |
| 0150 | Fine milling | SQYD A | 56,480 | $0.90 | |
| 0160 | Temporary signs | SQFT A | 1,140 | $5.50 | $16.48 |
| 0170 | Maintain & control traffic | LS A | 1 | $8,905.00 | $8,371.79 |
| 0180 | Maintain & control traffic | LS A | 1 | $14,765 | $24,574 |
| 0190 | Maintain & control traffic | LS A | 1 | $36,365 | $47,323 |
| 0200 | Maintain & control traffic | LS A | 1 | $16,000 | $24,574 |
| 0210 | Portable changeable message sign | EACH A | 8 | $390.00 | $1,648.08 |
| 0220 | Edgeline rumble strips | LF A | 6,470 | $0.95 | $1.00 |
| 0230 | Sidewalk-4 in concrete | SQYD A | 32 | $345.00 | $100.00 |
| 0240 | Arrow panel | EACH A | 6 | $270.00 | $1,200.00 |
| 0250 | Conduit-1 1/4 in | LF A | 10 | $5.20 | $57.91 |
| 0260 | Trenching and backfilling | LF A | 5 | $11.00 | $117.23 |
| 0270 | Piezoelectric sensor | EACH A | 4 | $3,156.25 | $4,300.00 |
| 0280 | Loop wire | LF A | 800 | $0.30 | $2.33 |
| 0290 | Loop saw slot and fill | LF A | 230 | $12.00 | $72.59 |
| 0300 | Pave striping-temp paint-4 in | LF A | 15,000 | $0.31 | $0.36 |
| 0310 | Pave striping-perm paint-6 in | LF A | 20,209 | $0.33 | $0.39 |
| 0320 | Pave striping removal-6 in | LF A | 78,478 | $0.70 | $0.88 |
| 0330 | Pave striping-thermo-6 in W | LF A | 27,162 | $1.35 | $1.59 |
| 0340 | Pave striping-thermo-6 in Y | LF A | 51,315 | $1.35 | $1.59 |
| 0350 | Pave striping-thermo-12 in W | LF A | 100 | $4.00 | $4.71 |
| 0360 | Pave marking-thermo R 6 FT | EACH A | 4 | $150.00 | $176.58 |
| 0370 | Pave marking-R/R xbucks 16 in | LF A | 80 | $11.00 | $12.95 |
| 0380 | Pave marking-thermo X-walk-6 in | LF A | 912 | $2.00 | $2.35 |
| 0390 | Pave marking-thermo stop bar-24IN | LF A | 626 | $15.00 | $17.66 |
| 0400 | Pave marking-thermo STR arrow | EACH A | 2 | $150.00 | $176.58 |
| 0410 | Pave marking-thermo curv arrow | EACH A | 76 | $150.00 | $176.58 |
| 0420 | Pave marking-thermo comb arrow | EACH A | 2 | $300.00 | $353.16 |
| 0430 | Pave marking-thermo merge arrow | EACH A | 2 | $400.00 | $470.88 |
| 0440 | Wood post | EACH A | 1 | $250.00 | $1,200.00 |
| 0450 | Electrical junction box-10 X 8 X 4 | EACH A | 1 | $1,000.00 | $1,400.00 |
| 0460 | Overband crack sealing | LB A | 11,000 | $1.75 | $2.06 |
| 0470 | Detectable warnings | SQFT A | 32 | $60.00 | $70.00 |
| 0480 | Polymer asphalt emulsion for scrub seal | TON A | 32 | $1,115.00 | $830.00 |
| 0490 | Asphalt emulsion for fog seal | TON A | 4 | $780.00 | $1,410.00 |
| 0500 | Remove pavement marker | EACH A | 886 | $1.00 | $74.87 |
| 0510 | Asphalt seal aggregate - type D | SQYD A | 20,578 | $1.00 | $2.13 |
| 0520 | Demobilization | LS A | 1 | $18,385 | $44,418 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 23, 2025. Compiled by Mirage Metrics.