KYTC contract 25-2371 bid tabulation
PAVEMENT (WITH ALTERNATES) MANCHESTER - LONDON ROAD (KY 80). Let by Kentucky Transportation Cabinet on November 20, 2025. 2 bids received; low bid $957,527 by L-M Asphalt Partners LTD D/B/A Ats Construction, -13% against the engineer's estimate of $1,098,149.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 NOV 2025
- Pay items
- 26
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $957,527 | Low | -13% |
| 2 | Strawser Construction Inc | $1,112,954 | +16% | +1.0% |
Engineer's estimate: $1,098,149.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. L-M Asphalt Partners LTD D/B/A Ats Construction | 2. Strawser Construction Inc |
|---|---|---|---|---|---|
| 0010 | Pave striping-temp paint-4 in | LF A A | 181,000 | $0.18 | |
| 0020 | Microsurfacing-leveling course | SQYD A A | 157,500 | $2.36 | |
| 0030 | Microsurfacing-surface course - type D | SQYD A A | 125,618 | $3.30 | |
| 0040 | Leveling & wedging PG64-22 | TON A A | 1,315 | $105.00 | |
| 0050 | Asphalt material for tack | TON A A | 67 | $10.00 | |
| 0060 | Mobilization for mill & text | LS A A | 1 | $2,500.00 | |
| 0070 | Pave striping-temp paint-4 in | LF A A | 50,000 | $0.22 | |
| 0080 | CL3 asph surf no.4D PG64-22 | TON A A | 5,185 | $113.50 | |
| 0090 | Fine milling | SQYD A A | 5,000 | $2.50 | |
| 0100 | Temporary signs | SQFT A A | 96 | $0.01 | $27.00 |
| 0110 | Maintain & control traffic | LS A A | 1 | $28,387 | $64,722 |
| 0120 | Portable changeable message sign | EACH A A | 2 | $749.00 | $1,760.00 |
| 0130 | Edgeline rumble strips | LF A A | 53,130 | $0.23 | $0.26 |
| 0140 | Arrow panel | EACH A A | 2 | $374.50 | $1,160.00 |
| 0150 | Pave striping-perm paint-6 in | LF A A | 150,060 | $0.30 | $0.44 |
| 0155 | Pave striping removal-6 in | LF A A | 10,000 | $0.30 | $0.70 |
| 0160 | Pave striping-thermo-6 in W | LF A A | 9,625 | $1.25 | $1.44 |
| 0170 | Pave striping-thermo-6 in Y | LF A A | 6,400 | $1.25 | $1.44 |
| 0180 | Pave striping-dur TY 1-6 in W | LF A A | 700 | $9.00 | $10.35 |
| 0190 | Pave striping-dur TY 1-6 in Y | LF A A | 350 | $9.00 | $10.35 |
| 0200 | Pave marking-thermo stop bar-24IN | LF A A | 400 | $10.00 | $11.50 |
| 0210 | Pave marking-thermo cross-hatch | SQFT A A | 7,050 | $4.00 | $4.60 |
| 0220 | Pave marking-thermo curv arrow | EACH A A | 14 | $120.00 | $138.00 |
| 0230 | Pave marking-thermo merge arrow | EACH A A | 3 | $300.00 | $345.01 |
| 0240 | Overband crack sealing | LB A A | 20,000 | $1.75 | $2.01 |
| 0250 | Demobilization | LS A A | 1 | $14,151 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of November 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.