KYTC contract 25-4710 bid tabulation
HIGH FRICTION SURFACE INTERSTATE 64/71 RAMPS 561, 532, AND 014. Let by Kentucky Transportation Cabinet on July 24, 2025. 3 bids received; low bid $359,359 by The Truesdell Corporation, +1.9% against the engineer's estimate of $352,545.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 JUL 2025
- Pay items
- 17
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | The Truesdell Corporation | $359,359 | Low | +2.0% |
| 2 | Ram Construction Services of Michigan Inc | $489,477 | +36% | +39% |
| 3 | A & A Safety Inc | $555,756 | +55% | +58% |
Engineer's estimate: $352,545.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. The Truesdell Corporation | 2. Ram Construction Services of Michigan Inc | 3. A & A Safety Inc |
|---|---|---|---|---|---|---|
| 0010 | Temporary signs | SQFT A A | 300 | $8.50 | $1.00 | $1.00 |
| 0020 | Maintain & control traffic | LS A A | 1 | $18,000 | $87,000 | $50,000 |
| 0030 | Truck mounted attenuator | EACH A A | 2 | $4,375.00 | $1,704.00 | $4,500.00 |
| 0040 | Portable changeable message sign | EACH A A | 2 | $635.00 | $360.00 | $650.00 |
| 0050 | Pave striping-temp paint-6 in | LF A A | 4,815 | $4.50 | $1.00 | $4.12 |
| 0060 | Pave striping-temp paint-12 in | LF A A | 2,181 | $4.75 | $2.00 | $4.43 |
| 0070 | Pavement marking removal | SQFT A A | 5,256 | $6.00 | $5.00 | $5.56 |
| 0080 | Law enforcement officer | HOUR A A | 100 | $100.00 | $150.00 | $125.00 |
| 0090 | High friction surface treatment | SQYD A A | 6,180 | $23.80 | $28.71 | $54.70 |
| 0100 | Pave mark thermo chevron | SQFT A A | 400 | $27.00 | $6.95 | $24.80 |
| 0110 | Pave striping-thermo-6 in W-wet reflect | LF A A | 2,408 | $3.60 | $15.00 | $3.39 |
| 0120 | Pave striping-thermo-6 in Y-wet reflect | LF A A | 2,408 | $3.60 | $15.00 | $3.39 |
| 0130 | Pave striping-thermo-12 in W-wet reflect | LF A A | 2,181 | $6.40 | $25.00 | $5.96 |
| 0140 | Pave stripe-wet ref cont tape-6 in W | LF A A | 302 | $23.75 | $25.00 | $22.22 |
| 0150 | Pave stripe-wet ref cont tape-6 in Y | LF A A | 533 | $23.75 | $25.00 | $22.22 |
| 0160 | Pave stripe-wet ref cont tape-12 in W | LF A A | 366 | $38.00 | $34.00 | $35.76 |
| 0170 | Demobilization | LS A A | 1 | $32,307 | $7,300.00 | $15,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of July 24, 2025. Compiled by Mirage Metrics.