MoDOT contract 250221-D05 bid tabulation
JCD0091 - ROUTE I-70, I-44 - VARIOUS COUNTIES. Let by Missouri DOT on February 21, 2025, Cooper, Central. 5 bids received; low bid $633,975 by Advanced Highway Sign and Supply, LLC.
- Owner
- Missouri DOT
- Letting
- 21 FEB 2025
- Pay items
- 14
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Advanced Highway Sign and Supply, LLC | $633,975 | Low |
| 2 | J M Scheidle, LLC | $674,162 | +6.0% |
| 3 | James H. Drew Corporation | $794,590 | +25% |
| 4 | Collins & Hermann, Inc. | $980,000 | +55% |
| 5 | CSD Environmental Services, Inc. | $1,286,790 | +103% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advanced Highway Sign and Supply, LLC | 2. J M Scheidle, LLC | 3. James H. Drew Corporation | 4. Collins & Hermann, Inc. | 5. CSD Environmental Services, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $17,500 | $25,000 | $51,270 | $220,886 | $127,000 |
| 0020 | Construction signs (6161005) | SF | 683 | $9.35 | $7.00 | $30.00 | $9.00 | $10.00 |
| 0030 | Channelizer (trim line) (6161025) | EACH | 138 | $24.20 | $22.00 | $112.00 | $36.00 | $25.00 |
| 0040 | Directional indicator barricade (6161033) | EACH | 28 | $132.00 | $45.00 | $142.00 | $118.00 | $150.00 |
| 0050 | Flashing arrow panel (6161040) | EACH | 2 | $2,200.00 | $1,500.00 | $2,365.00 | $2,600.00 | $1,250.00 |
| 0060 | Sequential flashing warning light (6161055) | EACH | 28 | $93.50 | $35.00 | $100.00 | $118.00 | $115.00 |
| 0070 | Mobilization (6181000) | LS | 1 | $40,000 | $80,000 | $20,510 | $119,000 | $44,910 |
| 0080 | Contractor furnished surveying and staking (6274000) | LS | 1 | $10,000 | $5,000.00 | $11,960 | $15,000 | $5,500.00 |
| 0090 | Square steel sign post (4IN.) base (9031005) | EACH | 23 | $1,365.00 | $800.00 | $1,385.00 | $1,250.00 | $900.00 |
| 0100 | Concrete footings, embedded (9031010) | CY | 53.50 | $1,955.00 | $1,200.00 | $3,560.00 | $1,600.00 | $7,733.21 |
| 0110 | Structural steel posts (9031210) | LB | 41,570 | $4.65 | $5.30 | $4.70 | $4.55 | $3.52 |
| 0120 | 4 in. square steel post (9031230) | LF | 419 | $39.00 | $60.00 | $50.00 | $71.00 | $25.00 |
| 0130 | ST-structural (9035011A) | SF | 9,181 | $21.60 | $24.00 | $24.00 | $29.00 | $53.60 |
| 0140 | STF-structural fluorescent (9035071A) | SF | 90 | $23.30 | $30.00 | $49.00 | $30.00 | $65.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of February 21, 2025. Compiled by Mirage Metrics.