MoDOT contract 250620-B02 bid tabulation

Rank vendor id vendor name total bid percent of low bid. Let by Missouri DOT on June 20, 2025, Adair, Northeast. 2 bids received; low bid $652,789 by W. L. Miller Company.

Owner
Missouri DOT
Letting
20 JUN 2025
Pay items
13
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1W. L. Miller Company$652,789Low
2BMC Enterprises, Inc. dba Missouri Petroleum Products Company$1,074,981+65%
MoDOT contract 250620-B02: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. W. L. Miller Company2. BMC Enterprises, Inc. dba Missouri Petroleum Products Company
0010Emulsified asphalt, seal coat (4091048)GAL35,360$3.10$2.80
0020Seal coat aggregate, grade B2 (4094012)SY126,270$1.27$2.00
0030Changeable message sign without communication interface, contractor furnished retained (6161098A)EACH2$1,500.00$3,000.00
0040Misc.lump sum temporary traffic control (6169901)LS1$11,026$81,500
0050Mobilization (6181000)LS1$22,800$81,500
0060Plural component liquid pavement marking, 6 in. white (6200008)LF40$20.00$150.00
00704 in. white standard waterborne pavement marking paint, type P beads (6206000C)LF69,231$0.15$0.11
00804 in. yellow standard waterborne pavement marking paint, type P beads (6206001C)LF109,244$0.14$0.10
0090Emulsified asphalt, seal coat (4091048)GAL35,870$3.10$2.80
0100Seal coat aggregate, grade B2 (4094012)SY128,102$1.25$2.00
0110Misc.lump sum temporary traffic control (6169901)LS1$11,026$81,500
0120Mobilization (6181000)LS1$22,800$81,500
01304 in. yellow standard waterborne pavement marking paint, type P beads (6206001C)LF102,535$0.14$0.10
MoDOT contract 250620-B02: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of June 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy