MoDOT contract 251017-A05 bid tabulation

JNWM0110 - ROUTES I-29, I-229, 36 - BUCHANNAN, ANDREW COUNTIES. Let by Missouri DOT on October 17, 2025, Buchanan, Northwest. 3 bids received; low bid $1,484,418 by Collins & Hermann, Inc..

Owner
Missouri DOT
Letting
17 OCT 2025
Pay items
17
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Collins & Hermann, Inc.$1,484,418Low
2Mar-Jim Contracting, LLC$1,701,322+15%
3CSD Environmental Services, Inc.$1,771,779+19%
MoDOT contract 251017-A05: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Collins & Hermann, Inc.2. Mar-Jim Contracting, LLC3. CSD Environmental Services, Inc.
0010Removal of improvements (2022010)LS1$133,795$236,000$374,821
0020Misc.removal of improvements: catwalk & lighting (2029903)LF1,615$104.48$38.00$36.76
0030Changeable message sign with communication interface, contractor furnished retained (6161099)EACH2$3,764.47$6,000.00$3,200.00
0040Misc.lump sum temporary traffic control (6169901)LS1$284,221$265,219$90,000
0050Misc.traffic control type 7 (6169901)LS1$12,921$30,000$79,800
0060Mobilization (6181000)LS1$77,283$96,064$112,684
0070Substructure repair (formed) (7040101)SF550$231.46$364.00$400.00
0080Structural steel posts (9031210)LB2,220$6.49$12.00$8.00
0090SH-flat sheet (9035004A)SF57$24.81$27.00$29.00
0100ST-structural (9035011A)SF15,401$30.40$40.00$46.63
0110SHF-flat sheet fluorescent (9035069A)SF84$34.37$27.00$36.00
0120STF-structural fluorescent (9035071A)SF364$30.42$45.25$39.00
0130Misc.grout pad removal (9039902)EACH49$3,096.14$2,500.00$975.00
0140Misc.replace connection bolt (9039902)EACH6$974.65$451.00$950.00
0150Misc.replace handhole cover (9039902)EACH1$807.47$300.00$350.00
0160Misc.sign truss repair (9039902)EACH2$5,670.68$1,610.00$5,500.00
0170Misc.tighten bolts or anchor rod nuts (9039902)EACH7$707.16$1,255.00$1,300.00
MoDOT contract 251017-A05: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of October 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy