MoDOT contract 260515-G07 bid tabulation

JSR0132 - ROUTE 13 - STONE COUNTY. Let by Missouri DOT on May 15, 2026, Stone, Southwest. 2 bids received; low bid $1,148,771 by Gemstone, LLC dba Gemstone, LLC MO.

Owner
Missouri DOT
Letting
15 MAY 2026
Pay items
16
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Gemstone, LLC dba Gemstone, LLC MO$1,148,771Low
2Thomas Industrial Coatings, Inc.$5,203,000+353%
MoDOT contract 260515-G07: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Gemstone, LLC dba Gemstone, LLC MO2. Thomas Industrial Coatings, Inc.
0010Truck mounted attenuator (TMA) (6123001)LS1$13,780$17,200
0020Construction signs (6161005)SF346$7.74$6.50
0030Buoys (boats keep out) (6161012)EACH16$297.50$250.00
0040Buoys (no wake) (6161013)EACH38$297.50$250.00
0050Special sign assembly (boats keep out) (6161014)EACH4$595.00$500.00
0060Channelizer (trim-line) (6161025)EACH150$23.80$20.00
0070Changeable message sign with communication interface, contractor furnished retained (6161099)EACH2$1,487.50$1,250.00
0080Mobilization (6181000)LS1$178,100$305,851
0090Surface preparation for recoating structural steel (7125200)SF13,700$28.00$160.00
0100Field application of inorganic zinc primer (7125210)SF13,700$10.00$65.00
0110Finished field coat (system L) (7125397)SF13,700$10.00$50.00
0120Misc.guide pin replacement (7129902)EACH8$14,998$29,983
0130Misc.rehabilitate saddle bearing (7129902)EACH17$5,540.10$24,370
0140Misc.saddle bearing stiffener repair (7129902)EACH17$2,525.20$22,833
0150Misc.stopper plate (7129902)EACH1$6,478.20$18,708
0160Misc.wind transfer device repair (7129902)EACH2$4,026.16$14,095
MoDOT contract 260515-G07: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of May 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy