NJDOT contract 24466 bid tabulation

Route I-80 MTN Bridge Painting Contract 2024-1. Let by New Jersey DOT on December 18, 2025, Bergen, Morris, H4. 2 bids received; low bid $8,474,592 by M. Painting Company, Inc..

Owner
New Jersey DOT
Letting
18 DEC 2025
Pay items
71
Data through
16 APR 2026

Bidders

RankBidderTotal bidAgainst the low bid
1M. Painting Company, Inc.$8,474,592Low
2Allied Painting, Inc.$13,832,665+63%
NJDOT contract 24466: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. M. Painting Company, Inc.2. Allied Painting, Inc.
0001Performance bond and payment bond (151006M)DOL50,000$1.00$1.00
0002Trainees (153011M)HR750$10.00$1.00
0003Mobilization (154003P)LS1$20,000$675,000
0004Testing, IF and where directed (MMG086M)DOL10,000$1.00$1.00
0005Breakaway barricade (159003M)U104$10.00$75.00
0006Drum (159006M)U300$5.00$24.00
0007Traffic cone (159009M)U3,000$1.00$8.00
0008Construction signs (159012M)SF1,000$1.00$10.00
0009Arrow board, 4' X 8' (159027M)U8$1,000.00$2,300.00
0010Portable variable message sign W/remote communication (159029M)U8$1,000.00$10,000
0011Traffic control truck with mounted crash cushion (159108M)U8$1,000.00$12,000
0012Floodlights for nighttime operation (MMB085M)U10$500.00$6,500.00
0013Clearing site (201003P)LS1$10,000$10,000
0014Pollution liability insurance (152015P)DOL40,000$1.00$1.00
0015Chain-link fence, aluminum- coated steel, 6' high (605009P)LF500$40.00$60.00
0016Field office type E set UP (155015M)U1$30,000$20,000
0017Field office type E maintenance (155033M)MO15$4,000.00$4,200.00
0018Lubricate bearing (506013P)U483$30.00$100.00
0019Substructure concrete repair (555003M)SF4,240$30.00$350.00
0020Epoxy waterproofing (504036P)SY2,778$25.00$60.00
0021Vertical concrete sealant (MMG154M)SY6,937$39.00$55.00
0022Containment system , 1413-161 (MMG082M)LS1$12,764$70,000
0023SSPC, blast/prime , 1413-161 (MMG083M)LS1$319,107$300,000
0024SSPC, stripe/intermediate , 1413-161 (MMG084M)LS1$191,464$160,000
0025SSPC, finish , 1413-161 (MMG085M)LS1$102,114$75,000
0026Final cleanup , 1413-161 (161003P)LS1$12,764$5,000.00
0027Containment system , 1414-160 (MMG082M)LS1$12,764$70,000
0028SSPC, blast/prime , 1414-160 (MMG083M)LS1$319,107$405,000
0029SSPC, stripe/intermediate , 1414-160 (MMG084M)LS1$191,464$195,000
0030SSPC, finish , 1414-160 (MMG085M)LS1$102,114$95,000
0031Final cleanup , 1414-160 (161003P)LS1$12,764$5,000.00
0032Containment system , 1414-164 (MMG082M)LS1$23,101$165,000
0033SSPC, blast/prime 1414-164 (MMG083M)LS1$577,518$860,000
0034SSPC, stripe/intermediate , 1414-164 (MMG084M)LS1$346,511$310,000
0035SSPC, finish , 1414-164 (MMG085M)LS1$196,356$150,000
0036Final cleanup , 1414-164 (161003P)LS1$11,550$5,000.00
0037Containment system , 1414-166 (MMG082M)LS1$17,416$165,000
0038SSPC, blast/prime , 1414-166 (MMG083M)LS1$435,392$860,000
0039SSPC, stripe/intermediate , 1414-166 (MMG084M)LS1$261,235$310,000
0040SSPC, finish , 1414-166 (MMG085M)LS1$139,325$150,000
0041Final cleanup , 1414-166 (161003P)LS1$17,416$5,000.00
0042Containment system , 1414-175 (MMG082M)LS1$25,685$170,000
0043SSPC, blast/prime , 1414-175 (MMG083M)LS1$642,121$910,000
0044SSPC, stripe/intermediate , 1414-175 (MMG084M)LS1$385,272$485,000
0045SSPC, finish , 1414-175 (MMG085M)LS1$218,321$245,000
0046Final cleanup , 1414-175 (161003P)LS1$12,842$5,000.00
0047Containment system , 1414-176 (MMG082M)LS1$13,798$95,000
0048SSPC, blast/prime , 1414-176 (MMG083M)LS1$344,948$500,000
0049SSPC, stripe/intermediate , 1414-176 (MMG084M)LS1$206,969$230,000
0050SSPC, finish , 1414-176 (MMG085M)LS1$113,833$135,000
0051Final cleanup , 1414-176 (161003P)LS1$10,348$5,000.00
0052Containment system , 1414-179 (MMG082M)LS1$10,180$90,000
0053SSPC, blast/prime , 1414-179 (MMG083M)LS1$254,504$355,000
0054SSPC, stripe/intermediate , 1414-179 (MMG084M)LS1$152,702$160,000
0055SSPC, finish , 1414-179 (MMG085M)LS1$81,441$97,000
0056Final cleanup , 1414-179 (161003P)LS1$10,180$5,000.00
0057Containment system , 1427-150 (MMG082M)LS1$11,214$70,000
0058SSPC, blast/prime , 1427-150 (MMG083M)LS1$280,345$425,000
0059SSPC, stripe/intermediate , 1427-150 (MMG084M)LS1$168,207$160,000
0060SSPC, finish , 1427-150 (MMG085M)LS1$89,710$80,000
0061Final cleanup , 1427-150 (161003P)LS1$11,214$5,000.00
0062Containment system , 0226-162 (MMG082M)LS1$13,798$65,000
0063SSPC, blast/prime , 0226-162 (MMG083M)LS1$334,948$660,000
0064SSPC, stripe/intermediate , 0226-162 (MMG084M)LS1$206,969$195,000
0065SSPC, finish , 0226-162 (MMG085M)LS1$113,833$95,000
0066Final cleanup , 0226-162 (161003P)LS1$10,348$5,000.00
0067Containment system , 0226-165 (MMG082M)LS1$13,798$65,000
0068SSPC, blast/prime , 0226-165 (MMG083M)LS1$341,948$575,000
0069SSPC, stripe/intermediate , 0226-165 (MMG084M)LS1$204,969$198,000
0070SSPC, finish , 0226-165 (MMG085M)LS1$112,833$95,000
0071Final cleanup , 0226-165 (161003P)LS1$10,348$5,000.00
NJDOT contract 24466: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

Every contract let that day: NJDOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy