NJDOT contract 24468 bid tabulation

Route I-287 MTN Bridge Painting Contract 2024-3. Let by New Jersey DOT on December 23, 2025, Middlesex, Somerset, H4. 3 bids received; low bid $17,439,418 by M. Painting Company, Inc..

Owner
New Jersey DOT
Letting
23 DEC 2025
Pay items
89
Data through
16 APR 2026

Bidders

RankBidderTotal bidAgainst the low bid
1M. Painting Company, Inc.$17,439,418Low
2Allied Painting, Inc.$17,911,125+3.0%
3Ahern Painting Contractors, Inc.$24,618,610+41%
NJDOT contract 24468: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. M. Painting Company, Inc.2. Allied Painting, Inc.3. Ahern Painting Contractors, Inc.
0001Performance bond and payment bond (151006M)DOL50,000$1.00$1.00$1.00
0002Trainees (153011M)HR750$10.00$1.00$100.00
0003Mobilization (154003P)LS1$1,000.00$875,000$1,000,000
0004Testing, IF and where directed (MMG086M)DOL10,000$1.00$1.00$1.00
0005Breakaway barricade (159003M)U104$10.00$50.00$350.00
0006Drum (159006M)U400$5.00$20.00$120.00
0007Traffic cone (159009M)U3,000$1.00$3.00$50.00
0008Construction signs (159012M)SF1,000$3.00$10.00$12.50
0009Arrow board, 4' X 8' (159027M)U8$1,000.00$2,400.00$10,000
0010Portable variable message sign W/remote communication (159029M)U8$1,000.00$15,000$20,000
0011Traffic control truck with mounted crash cushion (159108M)U8$2,000.00$15,000$35,000
0012Traffic director, flagger (159141M)HR1,000$10.00$1.00$115.00
0013Floodlights for nighttime operation (MMB085M)U10$1,000.00$6,500.00$8,000.00
0014Clearing site (201003P)LS1$10,000$10,000$84,500
0015Railroad protective liability insurance (152012P)DOL50,000$1.00$1.00$1.00
0016Pollution liability insurance (152015P)DOL25,000$1.00$1.00$1.00
0017Railroad services (MMB188M)DOL250,000$1.00$1.00$1.00
0018Chain-link fence, aluminum- coated steel, 6' high (605009P)LF1,000$20.00$50.00$90.00
0019Field office type E set UP (155015M)U1$30,000$20,000$150,000
0020Field office type E maintenance (155033M)MO15$4,000.00$4,000.00$8,500.00
0021Lubricate bearing (506013P)U704$30.00$100.00$1,000.00
0022Substructure concrete repair (555003M)SF3,503$300.00$340.00$420.00
0023Epoxy waterproofing (504036P)SY3,516$40.00$55.00$150.00
0024Vertical concrete sealant (MMG154M)SY9,315$39.00$45.00$70.00
0025Containment system , 1230-151 (MMG082M)LS1$28,789$100,000$870,000
0026SSPC, blast/prime , 1230-151 (MMG083M)LS1$719,714$700,000$761,250
0027SSPC, stripe/intermediate , 1230-151 (MMG084M)LS1$431,828$460,000$217,500
0028SSPC, finish , 1230-151 (MMG085M)LS1$244,703$240,000$217,500
0029Final cleanup , 1230-151 (161003P)LS1$14,394$5,000.00$108,750
0030Containment system , 1230-152 (MMG082M)LS1$28,789$100,000$870,000
0031SSPC, blast/prime , 1230-152 (MMG083M)LS1$719,714$700,000$761,250
0032SSPC, stripe/intermediate , 1230-152 (MMG084M)LS1$431,828$460,000$217,500
0033SSPC, finish , 1230-152 (MMG085M)LS1$244,703$240,000$217,500
0034Final cleanup , 1230-152 (161003P)LS1$14,394$5,000.00$108,750
0035Containment system , 1230-154 (MMG082M)LS1$23,722$100,000$600,000
0036SSPC, blast/prime , 1230-154 (MMG083M)LS1$593,061$490,000$525,000
0037SSPC, stripe/intermediate , 1230-154 (MMG084M)LS1$355,837$304,000$150,000
0038SSPC, finish , 1230-154 (MMG085M)LS1$201,641$157,000$150,000
0039Final cleanup , 1230-154 (161003P)LS1$11,861$5,000.00$75,000
0040Containment system , 1230-164 (MMG082M)LS1$21,189$50,000$720,000
0041SSPC, blast/prime , 1230-164 (MMG083M)LS1$529,734$610,000$630,000
0042SSPC, stripe/intermediate , 1230-164 (MMG084M)LS1$317,841$350,000$180,000
0043SSPC, finish , 1230-164 (MMG085M)LS1$180,110$150,000$180,000
0044Final cleanup , 1230-164 (161003P)LS1$10,595$5,000.00$90,000
0045Containment system , 1230-165 (MMG082M)LS1$21,189$50,000$720,000
0046SSPC, blast/prime , 1230-165 (MMG083M)LS1$529,734$610,000$630,000
0047SSPC, stripe/intermediate , 1230-165 (MMG084M)LS1$317,841$350,000$180,000
0048SSPC, finish , 1230-165 (MMG085M)LS1$180,110$150,000$180,000
0049Final cleanup , 1230-165 (161003P)LS1$10,595$5,000.00$90,000
0050Containment system , 1231-154 (MMG082M)LS1$27,944$100,000$600,000
0051SSPC, blast/prime , 1231-154 (MMG083M)LS1$698,605$600,000$525,000
0052SSPC, stripe/intermediate , 1231-154 (MMG084M)LS1$419,163$379,000$150,000
0053SSPC, finish , 1231-154 (MMG085M)LS1$237,526$196,000$150,000
0054Final cleanup , 1231-154 (161003P)LS1$13,972$5,000.00$75,000
0055Containment system , 1231-157 (MMG082M)LS1$20,345$100,000$308,000
0056SSPC, blast/prime , 1231-157 (MMG083M)LS1$508,626$309,000$269,500
0057SSPC, stripe/intermediate , 1231-157 (MMG084M)LS1$305,175$190,000$77,000
0058SSPC, finish , 1231-157 (MMG085M)LS1$172,933$98,000$77,000
0059Final cleanup , 1231-157 (161003P)LS1$10,173$5,000.00$38,500
0060Containment system , 1231-160 (MMG082M)LS1$27,944$100,000$680,000
0061SSPC, blast/prime , 1231-160 (MMG083M)LS1$698,605$683,000$595,000
0062SSPC, stripe/intermediate , 1231-160 (MMG084M)LS1$419,163$455,000$170,000
0063SSPC, finish , 1231-160 (MMG085M)LS1$237,526$235,000$170,000
0064Final cleanup , 1231-160 (161003P)LS1$13,972$5,000.00$85,000
0065Containment system , 1231-161 (MMG082M)LS1$27,944$100,000$620,000
0066SSPC, blast/prime , 1231-161 (MMG083M)LS1$698,605$670,000$542,500
0067SSPC, stripe/intermediate , 1231-161 (MMG084M)LS1$419,163$380,000$155,000
0068SSPC, finish , 1231-161 (MMG085M)LS1$237,526$195,000$155,000
0069Final cleanup , 1231-161 (161003P)LS1$13,972$5,000.00$77,500
0070Containment system , 1231-164 (MMG082M)LS1$22,034$100,000$540,000
0071SSPC, blast/prime , 1231-164 (MMG083M)LS1$550,843$600,000$472,500
0072SSPC, stripe/intermediate , 1231-164 (MMG084M)LS1$330,506$379,000$135,000
0073SSPC, finish , 1231-164 (MMG085M)LS1$187,287$195,000$135,000
0074Final cleanup , 1231-164 (161003P)LS1$11,017$5,000.00$67,500
0075Containment system , 1815-171 (MMG082M)LS1$18,656$100,000$204,000
0076SSPC, blast/prime , 1815-171 (MMG083M)LS1$462,408$204,000$178,500
0077SSPC, stripe/intermediate , 1815-171 (MMG084M)LS1$279,845$112,000$51,000
0078SSPC, finish , 1815-171 (MMG085M)LS1$153,915$57,000$51,000
0079Final cleanup , 1815-171 (161003P)LS1$13,992$5,000.00$25,500
0080Containment system , 1815-172 (MMG082M)LS1$18,656$100,000$204,000
0081SSPC, blast/prime , 1815-172 (MMG083M)LS1$466,408$204,000$178,500
0082SSPC, stripe/intermediate , 1815-172 (MMG084M)LS1$279,845$112,000$51,000
0083SSPC, finish , 1815-172 (MMG085M)LS1$153,915$57,000$51,000
0084Final cleanup , 1815-172 (161003P)LS1$13,992$5,000.00$25,500
0085Containment system , 1815-174 (MMG082M)LS1$18,656$100,000$420,000
0086SSPC, blast/prime , 1815-174 (MMG083M)LS1$466,408$395,000$367,500
0087SSPC, stripe/intermediate , 1815-174 (MMG084M)LS1$279,845$223,000$105,000
0088SSPC, finish , 1815-174 (MMG085M)LS1$153,915$115,000$105,000
0089Final cleanup , 1815-174 (161003P)LS1$13,992$5,000.00$52,500
NJDOT contract 24468: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

Every contract let that day: NJDOT letting of December 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy