NJDOT contract 25120 bid tabulation
Rt. 46, Fairfield Ave to Rifle Camp Rd (CR633). Let by New Jersey DOT on September 18, 2025, Essex, Passaic, N1. 6 bids received; low bid $4,580,898 by Schifano Construction Corp..
- Owner
- New Jersey DOT
- Letting
- 18 SEP 2025
- Pay items
- 53
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Schifano Construction Corp. | $4,580,898 | Low |
| 2 | Smith-Sondy Asphalt Construction Co., Inc | $5,665,633 | +24% |
| 3 | D'Annunzio & Sons, Inc. | $5,747,000 | +25% |
| 4 | Della Pello Paving, Inc. | $5,785,834 | +26% |
| 5 | Crisdel Group, Inc. | $5,976,603 | +30% |
| 6 | Tilcon New York, Inc. | $6,395,000 | +40% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Schifano Construction Corp. | 2. Smith-Sondy Asphalt Construction Co., Inc | 3. D'Annunzio & Sons, Inc. | 4. Della Pello Paving, Inc. | 5. Crisdel Group, Inc. | 6. Tilcon New York, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $21,704 | $34,965 | $31,500 | $27,020 | $23,915 | $12,448 |
| 0002 | Pollution liability insurance (152015P) | DOL | 1 | $7,552.50 | $15,200 | $12,500 | $10,500 | $1.00 | $1,000.00 |
| 0003 | Progress schedule (153003P) | LS | 1 | $5,500.00 | $5,000.00 | $10,000 | $12,040 | $3,400.00 | $11,000 |
| 0004 | Progress schedule update (153005M) | U | 5 | $600.00 | $1,000.00 | $800.00 | $885.00 | $840.00 | $750.00 |
| 0005 | No item (original item: 153011M trainees qty 1800) (999999P) | U | 1 | $0.00 | $0.01 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0006 | Mobilization (154003P) | LS | 1 | $331,216 | $273,980 | $574,000 | $1,011,060 | $947,779 | $707,000 |
| 0007 | Field office type F set UP (155018M) | U | 1 | $22,500 | $25,000 | $50,000 | $32,100 | $22,350 | $84,200 |
| 0008 | Field office type F maintenance (155036M) | MO | 11 | $4,500.00 | $5,000.00 | $4,700.00 | $6,050.00 | $4,500.00 | $16,000 |
| 0009 | Inlet filter type 2, 2' X 4' (158030M) | U | 250 | $1.00 | $36.80 | $100.00 | $20.00 | $110.00 | $200.00 |
| 0010 | Inlet filter type 2, 4' X 4' (158033M) | U | 30 | $1.00 | $73.60 | $200.00 | $25.00 | $202.00 | $200.00 |
| 0011 | Concrete washout system (158063P) | LS | 1 | $500.00 | $5,000.00 | $1,500.00 | $500.00 | $1,442.00 | $3,500.00 |
| 0012 | Oil only emergency spill kit, type 1 (158072M) | U | 2 | $500.00 | $1,000.00 | $1,100.00 | $170.00 | $515.00 | $3,500.00 |
| 0013 | Breakaway barricade (159003M) | U | 100 | $1.00 | $0.01 | $1.00 | $50.00 | $0.01 | $10.00 |
| 0014 | Drum (159006M) | U | 250 | $1.00 | $0.01 | $1.00 | $1.00 | $0.01 | $30.00 |
| 0015 | Traffic cone (159009M) | U | 250 | $20.00 | $0.01 | $30.00 | $30.00 | $15.45 | $20.00 |
| 0016 | Construction signs (159012M) | SF | 1,130 | $15.25 | $19.00 | $15.00 | $23.00 | $22.40 | $30.00 |
| 0017 | Construction identification sign, 4' X 8' (159015M) | U | 2 | $1,500.00 | $2,000.00 | $1,000.00 | $2,120.00 | $2,070.00 | $1,000.00 |
| 0018 | Arrow board, 4' X 8' (159027M) | U | 4 | $100.00 | $0.01 | $1,700.00 | $100.00 | $1.00 | $7,500.00 |
| 0019 | Portable variable message sign (159030M) | U | 6 | $1.00 | $0.01 | $2,700.00 | $10.00 | $5,800.00 | $7,500.00 |
| 0020 | Traffic control truck with mounted crash cushion (159108M) | U | 4 | $7,500.00 | $0.01 | $6,000.00 | $100.00 | $1.00 | $5,500.00 |
| 0021 | HMA patch (159138M) | T | 67 | $125.00 | $0.01 | $90.00 | $90.00 | $448.00 | $500.00 |
| 0022 | Construction identification sign, iija 8' X 5' (159262M) | U | 2 | $1,600.00 | $2,000.00 | $1,100.00 | $2,120.00 | $2,430.00 | $2,000.00 |
| 0023 | Traffic stripes, latex, 4" (159300M) | LF | 715,256 | $0.01 | $0.28 | $0.20 | $0.01 | $0.10 | $0.01 |
| 0024 | Traffic markings lines, latex, 8" (159312M) | LF | 52,454 | $0.01 | $0.01 | $0.01 | $0.01 | $0.67 | $0.01 |
| 0025 | Traffic markings lines, latex, 24" (159314M) | LF | 18,018 | $0.01 | $0.01 | $0.01 | $0.01 | $1.05 | $0.01 |
| 0026 | Traffic markings symbols, latex (159320M) | SF | 7,920 | $0.01 | $0.01 | $0.01 | $0.01 | $1.30 | $0.01 |
| 0027 | Fuel price adjustment (160004M) | DOL | 1 | $14,500 | $14,500 | $14,500 | $14,500 | $14,500 | $14,500 |
| 0028 | Asphalt price adjustment (160007M) | DOL | 1 | $22,400 | $22,400 | $22,400 | $22,400 | $22,400 | $22,400 |
| 0029 | Final cleanup (161003P) | LS | 1 | $5,000.00 | $1,000.00 | $12,000 | $3,000.00 | $9,220.00 | $5,000.00 |
| 0030 | Clearing site (201003P) | LS | 1 | $5,000.00 | $198,150 | $58,767 | $3,000.00 | $16,780 | $60,000 |
| 0031 | HMA milling, 3" or less (401009P) | SY | 1,578 | $15.00 | $30.11 | $25.00 | $16.40 | $36.10 | $20.00 |
| 0032 | Micro-milling (401017P) | SY | 289,395 | $2.71 | $3.73 | $3.85 | $3.10 | $3.75 | $3.50 |
| 0033 | Hot mix asphalt pavement repair (401021M) | SY | 100 | $75.00 | $0.01 | $150.00 | $90.00 | $282.30 | $400.00 |
| 0034 | Polymerized joint adhesive (401027M) | LF | 200,280 | $0.34 | $0.01 | $0.35 | $0.62 | $0.44 | $0.35 |
| 0035 | Tack coat (401030M) | GAL | 44,738 | $0.01 | $0.01 | $3.00 | $0.01 | $0.01 | $0.01 |
| 0036 | Hot mix asphalt 12.5 M E surface course (401061M) | T | 273 | $179.50 | $318.00 | $260.00 | $206.10 | $290.25 | $300.00 |
| 0037 | Core samples, hot mix asphalt (401108M) | U | 85 | $95.00 | $0.01 | $170.00 | $135.00 | $192.15 | $200.00 |
| 0038 | High performance thin overlay (406005M) | T | 16,680 | $152.65 | $180.26 | $156.00 | $160.60 | $152.00 | $168.00 |
| 0039 | Full depth concrete pavement repair, HMA (453006M) | SY | 50 | $100.00 | $300.00 | $500.00 | $330.00 | $453.00 | $350.00 |
| 0040 | Curb piece (602213M) | U | 12 | $475.00 | $220.00 | $1,100.00 | $425.00 | $885.00 | $900.00 |
| 0041 | Cleaning drainage structure (602216M) | U | 262 | $1.00 | $440.00 | $425.00 | $555.00 | $551.00 | $1,100.00 |
| 0042 | Concrete sidewalk, 4" thick (606012P) | SY | 16 | $346.50 | $363.00 | $500.00 | $400.00 | $585.00 | $700.00 |
| 0043 | Detectable warning surface (606084P) | SY | 2 | $630.00 | $660.00 | $520.00 | $730.00 | $412.00 | $1,000.00 |
| 0044 | 9" X 16" concrete vertical curb (607018P) | LF | 25 | $250.00 | $253.00 | $120.00 | $280.00 | $224.00 | $300.00 |
| 0045 | Traffic stripes, 4" (610003M) | LF | 238,419 | $0.74 | $0.43 | $0.50 | $0.50 | $0.64 | $0.50 |
| 0046 | RPM, mono-directional, white lens (610012M) | U | 3,110 | $37.80 | $39.60 | $36.00 | $44.00 | $33.00 | $40.00 |
| 0047 | Traffic marking lines, 8" (610014M) | LF | 17,485 | $1.78 | $1.87 | $1.75 | $2.10 | $1.80 | $2.00 |
| 0048 | Traffic marking lines, 24" (610017M) | LF | 5,990 | $6.30 | $6.60 | $6.50 | $7.30 | $4.35 | $7.00 |
| 0049 | RPM, mono-directional, amber lens (610018M) | U | 799 | $37.80 | $39.60 | $36.00 | $44.00 | $33.00 | $40.00 |
| 0050 | Removal of RPM (610024M) | U | 3,909 | $2.00 | $0.01 | $1.00 | $5.00 | $13.00 | $2.00 |
| 0051 | Rumble strip (610033M) | LF | 9,675 | $1.40 | $2.44 | $1.85 | $1.65 | $1.85 | $2.00 |
| 0052 | Traffic markings symbols (610060M) | SF | 2,640 | $8.66 | $9.08 | $9.00 | $10.00 | $7.20 | $10.00 |
| 0053 | TVS roadway loops __ lanes 1 lane (704203M) | U | 8 | $8,400.00 | $2,500.00 | $6,000.00 | $11,500 | $9,682.00 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of September 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.