NJDOT contract 25702 bid tabulation
Maintenance Dredging and Channel Imp Waretown. Let by New Jersey DOT on July 31, 2025, Ocean, C4. 1 bid received; low bid $6,227,255 by J.F. Brennan Co., Inc..
- Owner
- New Jersey DOT
- Letting
- 31 JUL 2025
- Pay items
- 14
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | J.F. Brennan Co., Inc. | $6,227,255 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. J.F. Brennan Co., Inc. |
|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $20,000 |
| 0002 | Pollution liability insurance (152015P) | DOL | 1 | $5,000.00 |
| 0003 | Bar chart progress schedule and updates (153009P) | LS | 1 | $10,000 |
| 0004 | Mobilization (154003P) | LS | 1 | $3,065,000 |
| 0005 | Field office type A set UP (155003M) | U | 1 | $10,000 |
| 0006 | Field office type A maintenance (155021M) | MO | 9 | $2,500.00 |
| 0007 | Heavy duty silt fence, orange (158009M) | LF | 500 | $20.00 |
| 0008 | Construction driveway (158060M) | T | 50 | $120.00 |
| 0009 | Oil only emergency spill kit, type 1 (158072M) | U | 2 | $2,700.00 |
| 0010 | Construction identification sign, 6' X 12' (159018M) | U | 1 | $1,500.00 |
| 0011 | Final cleanup (161003P) | LS | 1 | $30,000 |
| 0012 | Clearing site (201003P) | LS | 1 | $25,000 |
| 0013 | Dredging, transport and placement to CDF (202041M) | CY | 89,130 | $33.50 |
| 0014 | Confined disposal facility construction (berm) (MMG124M) | CY | 1,000 | $31.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of July 31, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.