NYSDOT contract D265473 bid tabulation
BRIDGE PAINITING - Various Locations. Let by New York State DOT on March 20, 2025, Chenango, Delaware, Otsego, Region 09. 3 bids received; low bid $1,061,470 by Rover Contracting Inc.
- Owner
- New York State DOT
- Letting
- 20 MAR 2025
- Pay items
- 31
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rover Contracting Inc | $1,061,470 | Low |
| 2 | Amstar of Western New York Inc | $1,383,000 | +30% |
| 3 | Erie Painting & Maintenance Inc | $1,461,881 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rover Contracting Inc | 2. Amstar of Western New York Inc | 3. Erie Painting & Maintenance Inc |
|---|---|---|---|---|---|---|
| 1 | (210.481201) | SF | 40 | $50.00 | $1.00 | $250.00 |
| 2 | (210.481202) | SF | 30 | $50.00 | $1.00 | $250.00 |
| 3 | Lead-Exposure Control Plan (570.01) | LS | 1 | $5,000.00 | $3,100.00 | $5,000.00 |
| 4 | Medical Testing (570.02) | DOL | 3,000 | $1.00 | $1.00 | $1.00 |
| 5 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 4,000 | $1.00 | $1.00 | $1.00 |
| 6 | Decontamination Facilities (570.04) | CALENDAR WEEK | 25 | $50.00 | $25.00 | $100.00 |
| 7 | (570.150001) | LS | 1 | $40,000 | $38,700 | $5,000.00 |
| 8 | (570.150002) | LS | 1 | $40,000 | $15,000 | $5,000.00 |
| 9 | (570.150003) | LS | 1 | $30,000 | $18,900 | $5,000.00 |
| 10 | (570.150004) | LS | 1 | $50,000 | $27,000 | $10,000 |
| 11 | (570.150005) | LS | 1 | $80,000 | $180,300 | $10,000 |
| 12 | (570.150006) | LS | 1 | $50,000 | $54,000 | $10,000 |
| 13 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 12,472 | $0.25 | $0.40 | $1.00 |
| 14 | Disposal of Non-Hazardous Industrial Solid Paint Removal Waste (571.04) | LB | 4,809 | $0.25 | $1.00 | $1.00 |
| 15 | (573.010001) | LS | 1 | $50,000 | $105,715 | $220,000 |
| 16 | (573.010002) | LS | 1 | $50,000 | $60,415 | $90,000 |
| 17 | (573.010003) | LS | 1 | $50,000 | $69,415 | $90,000 |
| 18 | (573.010004) | LS | 1 | $120,000 | $78,415 | $140,000 |
| 19 | (573.010005) | LS | 1 | $270,000 | $436,115 | $230,000 |
| 20 | (573.010006) | LS | 1 | $120,000 | $141,415 | $430,000 |
| 21 | (619.01000109) | LS | 1 | $2,000.00 | $8,000.00 | $7,500.00 |
| 22 | (619.01000209) | LS | 1 | $2,000.00 | $8,000.00 | $7,500.00 |
| 23 | (619.01000309) | LS | 1 | $2,000.00 | $8,000.00 | $7,500.00 |
| 24 | (619.01000409) | LS | 1 | $2,000.00 | $8,000.00 | $10,000 |
| 25 | (619.01000509) | LS | 1 | $20,000 | $8,000.00 | $10,000 |
| 26 | (619.01000609) | LS | 1 | $2,000.00 | $8,000.00 | $10,000 |
| 27 | (619.111111) | EACH | 6 | $500.00 | $2,500.00 | $5,600.00 |
| 28 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 9 | $600.00 | $1,200.00 | $1,500.00 |
| 29 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 |
| 30 | Field Change Payment (FCP) (697.03) | DOL | 10,000 | $1.00 | $1.00 | $1.00 |
| 31 | Mobilization (699.040001) | LS | 1 | $40,000 | $51,217 | $56,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 20, 2025. Compiled by Mirage Metrics.