NYSDOT contract D265485 bid tabulation
ROUTE 9W SST CANAL STREET TO ROUTE 32 ULSTER COUNTY. Let by New York State DOT on May 8, 2025, Ulster, Region 08. 4 bids received; low bid $2,191,626 by A Colarusso & Son Inc.
- Owner
- New York State DOT
- Letting
- 08 MAY 2025
- Pay items
- 46
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | A Colarusso & Son Inc | $2,191,626 | Low |
| 2 | Argenio Brothers Inc | $2,715,715 | +24% |
| 3 | Callanan Industries Inc | $2,811,087 | +28% |
| 4 | Paleen Construction Corp | $3,336,097 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. A Colarusso & Son Inc | 2. Argenio Brothers Inc | 3. Callanan Industries Inc | 4. Paleen Construction Corp |
|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 1,402 | $35.00 | $73.50 | $75.00 | $200.00 |
| 2 | (203.24010017) | 24 | $90.00 | $350.00 | $225.00 | $75.00 | |
| 3 | (404.0001) | TON | 256 | $120.00 | $120.00 | $120.00 | $120.00 |
| 4 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1 | $120.00 | $120.00 | $120.00 | $120.00 |
| 5 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 80 | $120.00 | $120.00 | $120.00 | $120.00 |
| 6 | (404.0179) | TON | 131 | $200.00 | $215.00 | $160.00 | $200.00 |
| 7 | (406.1262) | TON | 6,525 | $131.00 | $148.25 | $140.00 | $170.00 |
| 8 | Straight Tack Coat (407.0103) | GAL | 2,666 | $12.00 | $14.25 | $35.00 | $12.00 |
| 9 | (407.01120007) | 1,807 | $5.00 | $10.50 | $6.00 | $12.00 | |
| 10 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 49,779 | $0.75 | $1.00 | $1.75 | $1.50 |
| 11 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 56,216 | $2.90 | $5.30 | $5.50 | $8.00 |
| 12 | Concrete Sidewalks and Driveways (608.0101) | CY | 4 | $2,900.00 | $4,000.00 | $4,000.00 | $5,250.00 |
| 13 | (608.02010015) | 8 | $190.00 | $1,700.00 | $1,000.00 | $400.00 | |
| 14 | (608.02020015) | 5 | $350.00 | $60.00 | $1,500.00 | $400.00 | |
| 15 | (608.21000003) | 4 | $525.00 | $500.00 | $375.00 | $600.00 | |
| 16 | (609.0401) | LF | 20 | $550.00 | $140.00 | $450.00 | $150.00 |
| 17 | Topsoil - Roadside (610.1402) | CY | 1,111 | $110.00 | $144.00 | $126.68 | $150.00 |
| 18 | Turf Establishment - Roadside (610.1601) | SY | 10,248 | $1.45 | $2.60 | $1.27 | $2.60 |
| 19 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $139,000 | $206,750 | $375,000 | $200,000 |
| 20 | (619.0901) | LF | 15,051 | $0.50 | $0.55 | $0.26 | $0.55 |
| 21 | (619.100101) | LF | 33,240 | $0.50 | $0.55 | $0.26 | $0.55 |
| 22 | (619.110532) | EACH | 5 | $6,000.00 | $5,300.00 | $5,000.00 | $7,500.00 |
| 23 | Cleaning Closed Drainage Systems (621.03) | LF | 2,678 | $13.50 | $6.60 | $12.50 | $16.25 |
| 24 | Cleaning Drainage Structures (621.04) | EACH | 90 | $540.00 | $300.00 | $500.00 | $650.00 |
| 25 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 3,087 | $6.40 | $7.70 | $7.00 | $10.00 |
| 26 | Survey Operations (625.01) | LS | 1 | $9,000.00 | $25,500 | $20,000 | $10,000 |
| 27 | (625.09010015) | LS | 1 | $3,000.00 | $1,000.00 | $2,500.00 | $1,000.00 |
| 28 | (627.50140008) | 22,170 | $2.00 | $4.15 | $0.22 | $6.00 | |
| 29 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 12,004 | $0.25 | $0.70 | $1.00 | $1.50 |
| 30 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 10 | $3,800.00 | $5,000.00 | $3,500.00 | $4,000.00 |
| 31 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | (680.05010007) | 4 | $24,000 | $25,900 | $22,400 | $26,000 | |
| 33 | (680.05020007) | 2 | $5,000.00 | $5,350.00 | $4,630.00 | $5,325.00 | |
| 34 | (680.51200208) | 4 | $170.00 | $925.00 | $2,500.00 | $400.00 | |
| 35 | (685.02000010) | 243 | $45.00 | $15.00 | $55.00 | $55.00 | |
| 36 | (685.16010014) | 14,568 | $1.45 | $1.60 | $1.78 | $1.60 | |
| 37 | (685.17010014) | 11,537 | $1.45 | $1.60 | $1.78 | $1.60 | |
| 38 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 4,007 | $2.50 | $2.70 | $2.65 | $2.70 |
| 39 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 2,142 | $2.35 | $2.50 | $2.75 | $2.50 |
| 40 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 32 | $130.00 | $140.00 | $68.00 | $140.00 |
| 41 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 10 | $155.00 | $170.00 | $270.00 | $170.00 |
| 42 | Field Change Payment (FCP) (697.03) | DOL | 150,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 43 | Asphalt Price Adjustment (698.04) | DOL | 4,990 | $1.00 | $1.00 | $1.00 | $1.00 |
| 44 | Fuel Price Adjustment (698.05) | DOL | 239 | $1.00 | $1.00 | $1.00 | $1.00 |
| 45 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 46 | Mobilization (699.040001) | LS | 1 | $84,000 | $94,056 | $95,000 | $125,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of May 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.