NYSDOT contract D265550 bid tabulation
HAZARDOUS TREE REMOVAL TACONIC STATE PARKWAY. Let by New York State DOT on August 7, 2025, Dutchess, Putnam, Region 08. 5 bids received; low bid $1,198,496 by New England Property Maintenance.
- Owner
- New York State DOT
- Letting
- 07 AUG 2025
- Pay items
- 16
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | New England Property Maintenance | $1,198,496 | Low |
| 2 | Adirondack Tree Surgeons Inc | $1,341,721 | +12% |
| 3 | Doyle Contracting Inc | $1,369,775 | +14% |
| 4 | Farney Tree & Excavation LLC | $1,746,368 | +46% |
| 5 | Red Rose Landscaping LLC | $2,439,300 | +104% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. New England Property Maintenance | 2. Adirondack Tree Surgeons Inc | 3. Doyle Contracting Inc | 4. Farney Tree & Excavation LLC | 5. Red Rose Landscaping LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | (614.060302) | EACH | 635 | $500.00 | $552.00 | $805.00 | $700.00 | $1,400.00 |
| 2 | (614.060402) | EACH | 290 | $900.00 | $1,104.00 | $1,290.00 | $1,400.00 | $2,100.00 |
| 3 | (614.060502) | EACH | 140 | $1,500.00 | $2,412.00 | $1,600.00 | $2,800.00 | $2,500.00 |
| 4 | (614.060602) | EACH | 11 | $1,700.00 | $4,656.00 | $2,600.00 | $5,600.00 | $5,000.00 |
| 5 | (614.060702) | EACH | 2 | $2,200.00 | $5,820.00 | $3,300.00 | $6,400.00 | $10,000 |
| 6 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $252,000 | $90,000 | $80,000 | $195,000 | $250,000 |
| 7 | (619.110522) | EACH | 2 | $16,000 | $9,500.00 | $8,000.00 | $10,500 | $23,000 |
| 8 | Truck Mounted Variable Message Signs (TMVMS) (619.1113) | EACH | 2 | $4,000.00 | $9,500.00 | $8,000.00 | $24,000 | $6,000.00 |
| 9 | Survey Operations (625.01) | LS | 1 | $2,500.00 | $5,000.00 | $5,000.00 | $70,000 | $30,000 |
| 10 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 12 | $2,000.00 | $5,300.00 | $3,000.00 | $500.00 | $5,500.00 |
| 11 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 12 | Field Change Payment (FCP) (697.03) | DOL | 20,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 13 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 15 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Mobilization (699.040001) | LS | 1 | $46,096 | $51,605 | $50,000 | $67,168 | $90,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of August 7, 2025. Compiled by Mirage Metrics.