NYSDOT contract D265578 bid tabulation
Pavement Resurfacing - NY Routes 878 and 454. Let by New York State DOT on November 6, 2025, Nassau, Suffolk, Region 10. 5 bids received; low bid $8,774,477 by Rosemar Contracting Inc.
- Owner
- New York State DOT
- Letting
- 06 NOV 2025
- Pay items
- 116
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rosemar Contracting Inc | $8,774,477 | Low |
| 2 | Posillico Civil Inc | $9,430,042 | +7.0% |
| 3 | Pratt Brothers Inc | $10,223,000 | +17% |
| 4 | H & L Contracting LLC | $10,246,576 | +17% |
| 5 | Tully Construction Company Inc | $11,076,046 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rosemar Contracting Inc | 2. Posillico Civil Inc | 3. Pratt Brothers Inc | 4. H & L Contracting LLC | 5. Tully Construction Company Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $15,000 | $65,000 | $25,000 | $30,000 | $16,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 18 | $350.00 | $300.00 | $500.00 | $200.00 | $270.00 |
| 3 | Embankment In Place (203.03) | CY | 125 | $90.00 | $150.00 | $215.00 | $130.00 | $150.00 |
| 4 | Trench and Culvert Excavation (206.0201) | CY | 25 | $85.00 | $10.00 | $20.00 | $500.00 | $205.00 |
| 5 | (206.03100010) | 292 | $120.00 | $110.00 | $75.00 | $150.00 | $50.00 | |
| 6 | (209.11010024) | 173 | $175.00 | $280.00 | $250.00 | $300.00 | $280.00 | |
| 7 | (304.10119917) | 40 | $250.00 | $500.00 | $60.00 | $60.00 | $240.00 | |
| 8 | (404.0001) | TON | 1,170 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 9 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1,173 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 10 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 722 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 11 | (404.0189) | TON | 202 | $127.00 | $150.00 | $95.00 | $200.00 | $250.00 |
| 12 | (404.0961) | TON | 23,300 | $127.00 | $150.00 | $139.00 | $155.00 | $120.00 |
| 13 | (404.1989) | TON | 54 | $250.00 | $1,100.00 | $425.00 | $90.00 | $440.00 |
| 14 | (404.3789) | TON | 74 | $250.00 | $1,100.00 | $425.00 | $120.00 | $350.00 |
| 15 | Diluted Tack Coat (407.0102) | GAL | 20,000 | $3.00 | $0.10 | $5.00 | $3.00 | $6.00 |
| 16 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 202,375 | $0.60 | $0.60 | $0.65 | $0.50 | $1.00 |
| 17 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 122,200 | $4.00 | $1.00 | $4.75 | $5.20 | $4.00 |
| 18 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 74,400 | $3.15 | $1.00 | $6.00 | $5.75 | $6.00 |
| 19 | (520.09000010) | 4,800 | $4.00 | $3.50 | $4.00 | $3.00 | $6.50 | |
| 20 | (603.6102) | LF | 50 | $30.00 | $100.00 | $39.00 | $25.00 | $185.00 |
| 21 | (603.6103) | LF | 50 | $36.00 | $110.00 | $56.00 | $28.00 | $190.00 |
| 22 | (603.6105) | LF | 50 | $60.00 | $130.00 | $84.00 | $54.00 | $195.00 |
| 23 | (604.07200110) | 60 | $2,200.00 | $2,850.00 | $4,800.00 | $2,500.00 | $2,650.00 | |
| 24 | (604.07210110) | 13 | $2,200.00 | $2,850.00 | $4,800.00 | $3,200.00 | $2,650.00 | |
| 25 | (604.07240110) | 13 | $3,500.00 | $3,060.00 | $4,200.00 | $3,900.00 | $3,400.00 | |
| 26 | (604.07290010) | 10 | $100.00 | $300.00 | $50.00 | $140.00 | $350.00 | |
| 27 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 238 | $76.00 | $75.50 | $85.00 | $68.00 | $70.00 |
| 28 | Removing and Disposing HPBO (Mod.) Corrugated Beam Guide Railing (606.7101) | LF | 238 | $35.00 | $35.00 | $15.00 | $13.00 | $20.00 |
| 29 | Concrete Sidewalks and Driveways (608.0101) | CY | 36 | $925.00 | $925.00 | $1,700.00 | $1,400.00 | $620.00 |
| 30 | (608.01050109) | 16 | $6,800.00 | $5,250.00 | $6,000.00 | $6,500.00 | $7,290.00 | |
| 31 | (608.01050309) | 1 | $11,000 | $8,800.00 | $10,500 | $9,900.00 | $7,370.00 | |
| 32 | (608.01050709) | 3 | $15,000 | $9,250.00 | $11,000 | $11,000 | $11,370 | |
| 33 | (608.01050909) | 3 | $10,000 | $7,725.00 | $8,500.00 | $10,000 | $9,630.00 | |
| 34 | (608.01051009) | 16 | $9,500.00 | $7,500.00 | $11,000 | $12,000 | $9,500.00 | |
| 35 | (608.01051109) | 24 | $7,500.00 | $5,500.00 | $6,000.00 | $6,600.00 | $9,260.00 | |
| 36 | (608.01051209) | 6 | $19,000 | $18,500 | $21,000 | $21,000 | $9,450.00 | |
| 37 | (608.02010015) | 620 | $75.00 | $75.00 | $60.00 | $5.00 | $325.00 | |
| 38 | (608.02020015) | 410 | $55.00 | $80.00 | $25.00 | $5.00 | $60.00 | |
| 39 | Surface-Applied Detectable Warning Units (608.20) | SY | 20 | $585.00 | $65.00 | $1,100.00 | $905.00 | $50.00 |
| 40 | (609.0401) | LF | 30 | $90.00 | $90.00 | $60.00 | $180.00 | $155.00 |
| 41 | (609.04070510) | 374 | $75.00 | $106.90 | $95.00 | $150.00 | $100.00 | |
| 42 | Topsoil - Roadside (610.1402) | CY | 31 | $150.00 | $150.00 | $183.00 | $150.00 | $150.00 |
| 43 | Turf Establishment - Roadside (610.1601) | SY | 263 | $18.00 | $18.00 | $20.00 | $18.00 | $18.00 |
| 44 | Improvement of Vegetated Areas (614.05) | SY | 185 | $30.00 | $30.00 | $35.00 | $30.00 | $30.00 |
| 45 | (614.060102) | EACH | 4 | $950.00 | $950.00 | $1,150.00 | $950.00 | $950.00 |
| 46 | (614.060202) | EACH | 4 | $1,100.00 | $1,100.00 | $1,300.00 | $1,100.00 | $1,100.00 |
| 47 | (617.01010024) | 8 | $350.00 | $350.00 | $350.00 | $350.00 | $350.00 | |
| 48 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $502,000 | $649,800 | $417,855 | $682,349 | $1,245,000 |
| 49 | Type III Construction Barricades (619.04) | EACH | 8 | $150.00 | $30.00 | $300.00 | $120.00 | $150.00 |
| 50 | (619.0901) | LF | 250,000 | $0.42 | $0.43 | $0.45 | $0.43 | $0.45 |
| 51 | (619.10050020) | 60 | $60.00 | $100.00 | $75.00 | $25.00 | $140.00 | |
| 52 | (619.110743) | EACH | 4 | $7,500.00 | $1,000.00 | $15,000 | $5,500.00 | $5,790.00 |
| 53 | (619.110943) | EACH | 4 | $7,000.00 | $1,000.00 | $15,000 | $5,500.00 | $6,700.00 |
| 54 | Vehicle Arresting Barrier (619.23) | EACH | 1 | $8,000.00 | $9,000.00 | $15,000 | $16,000 | $10,000 |
| 55 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $200,000 | $560,000 | $345,000 | $365,000 | $720,000 |
| 56 | Traffic Control Supervisor (619.25) | MONTH | 14 | $1,000.00 | $50.00 | $1,000.00 | $100.00 | $3,500.00 |
| 57 | Pavement Patching (Force Acount) (619.2601) | DOL | 20,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 58 | Cleaning Closed Drainage Systems (621.03) | LF | 1,720 | $7.50 | $5.00 | $4.50 | $4.00 | $11.00 |
| 59 | Cleaning Drainage Structures (621.04) | EACH | 113 | $800.00 | $1,000.00 | $850.00 | $800.00 | $800.00 |
| 60 | (621.51010010) | 250 | $20.00 | $25.00 | $15.00 | $50.00 | $15.50 | |
| 61 | Survey Operations (625.01) | LS | 1 | $75,000 | $10,000 | $45,000 | $35,000 | $55,000 |
| 62 | Cleaning, Sealing and/or Filling Cracks (633.12) | LS | 1 | $100,000 | $175,000 | $275,000 | $100,000 | $185,000 |
| 63 | Cleaning, Sealing and/or Filling Joints (633.13) | LF | 200 | $41.00 | $50.00 | $50.00 | $7.00 | $50.00 |
| 64 | Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401) | SY | 2,100 | $15.00 | $10.00 | $80.00 | $5.00 | $100.00 |
| 65 | (634.10010015) | LS | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 66 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 17 | $5,500.00 | $7,000.00 | $6,000.00 | $8,500.00 | $9,500.00 |
| 67 | Rain Gauge (637.26) | EACH | 1 | $500.00 | $1,000.00 | $300.00 | $1,500.00 | $300.00 |
| 68 | Office Technology and Supplies (637.34) | DOL | 17,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 69 | Construction Testing supplies – Consumables (637.36) | DOL | 200 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 70 | (645.03030015) | 4 | $2,750.00 | $2,750.00 | $3,500.00 | $2,998.00 | $4,200.00 | |
| 71 | (645.03040015) | 2 | $5,000.00 | $5,000.00 | $6,500.00 | $5,864.00 | $7,000.00 | |
| 72 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 15 | $64.00 | $63.50 | $78.00 | $75.00 | $150.00 |
| 73 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 454 | $65.00 | $65.00 | $59.00 | $56.00 | $150.00 |
| 74 | Overhead Sign Panels (645.61) | SF | 5 | $100.00 | $350.00 | $240.00 | $230.00 | $225.00 |
| 75 | Type A Sign Posts (645.81) | EACH | 84 | $295.00 | $295.00 | $240.00 | $232.00 | $475.00 |
| 76 | (645.81090003) | 2 | $75.00 | $75.00 | $60.00 | $60.00 | $90.00 | |
| 77 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 4 | $850.00 | $850.00 | $439.00 | $400.00 | $150.00 |
| 78 | Reference Marker Panel (646.21) | EACH | 74 | $75.00 | $75.00 | $170.00 | $49.00 | $95.00 |
| 79 | Steel Post, 1.1 lb/ft (646.31) | EACH | 74 | $100.00 | $100.00 | $70.00 | $67.00 | $175.00 |
| 80 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 14 | $275.00 | $275.00 | $350.00 | $336.00 | $350.00 |
| 81 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 13 | $150.00 | $150.00 | $256.00 | $248.00 | $250.00 |
| 82 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 8 | $75.00 | $75.00 | $200.00 | $200.00 | $250.00 |
| 83 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 77 | $30.00 | $30.00 | $148.00 | $144.00 | $225.00 |
| 84 | Pavement Ride Quality Adjustment to Asphalt Level 2 (653.1020) | QUALITY UNIT | 50 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 85 | (655.05010010) | 4 | $1,400.00 | $2,800.00 | $2,500.00 | $2,277.17 | $2,000.00 | |
| 86 | (655.07030010) | 17 | $1,200.00 | $1,500.00 | $1,325.00 | $1,405.00 | $1,400.00 | |
| 87 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 45 | $1,500.00 | $1,850.00 | $2,100.00 | $1,735.00 | $1,700.00 |
| 88 | (655.16000011) | 3 | $400.00 | $75.00 | $1,800.00 | $770.00 | $900.00 | |
| 89 | Adjust Existing Valve Box Elevation (663.33) | EACH | 1 | $150.00 | $200.00 | $500.00 | $75.00 | $900.00 |
| 90 | (670.14480010) | 10 | $250.00 | $850.00 | $250.00 | $1,400.00 | $900.00 | |
| 91 | (675.99000023) | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 92 | (680.05010007) | 8 | $28,500 | $28,500 | $32,000 | $30,000 | $33,000 | |
| 93 | (680.05020007) | 6 | $4,500.00 | $4,500.00 | $5,000.00 | $5,000.00 | $5,200.00 | |
| 94 | (680.51050010) | 4 | $1,900.00 | $3,300.00 | $5,000.00 | $2,000.00 | $1,900.00 | |
| 95 | (680.51111010) | 13 | $975.00 | $1,350.00 | $580.00 | $600.00 | $532.00 | |
| 96 | (680.520106) | LF | 53 | $26.00 | $26.00 | $52.00 | $48.00 | $48.00 |
| 97 | (680.520110) | LF | 239 | $69.00 | $69.00 | $74.00 | $68.10 | $68.00 |
| 98 | (680.520205) | LF | 25 | $16.00 | $16.00 | $39.00 | $35.70 | $36.00 |
| 99 | (680.80326110) | 5 | $3,500.00 | $3,500.00 | $4,300.00 | $3,951.00 | $4,000.00 | |
| 100 | (680.83200010) | LS | 1 | $5,000.00 | $5,000.00 | $20,000 | $5,800.00 | $6,000.00 |
| 101 | (685.02000007) | 88 | $14.00 | $100.00 | $35.00 | $97.75 | $150.00 | |
| 102 | (685.03100018) | 49 | $130.00 | $133.93 | $130.00 | $133.93 | $130.00 | |
| 103 | (685.03130018) | 39 | $155.00 | $159.68 | $155.00 | $159.68 | $155.00 | |
| 104 | (685.07200110) | 190,500 | $0.65 | $0.67 | $0.65 | $0.67 | $0.65 | |
| 105 | (685.07200210) | 12 | $150.00 | $154.53 | $150.00 | $154.53 | $150.00 | |
| 106 | (685.07200310) | 180 | $175.00 | $180.29 | $175.00 | $180.29 | $175.00 | |
| 107 | (685.07200410) | 3,500 | $1.85 | $1.91 | $1.85 | $1.91 | $2.00 | |
| 108 | (685.07200510) | 5,500 | $2.50 | $2.58 | $2.50 | $2.58 | $2.50 | |
| 109 | (685.07200610) | 100,500 | $0.65 | $0.67 | $0.65 | $0.67 | $0.65 | |
| 110 | (685.07200710) | 600 | $1.85 | $1.91 | $1.85 | $1.91 | $2.00 | |
| 111 | (691.04000020) | 24,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 112 | Field Change Payment (FCP) (697.03) | DOL | 720,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 113 | Asphalt Price Adjustment (698.04) | DOL | 56,121 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 114 | Fuel Price Adjustment (698.05) | DOL | 7,224 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 115 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 116 | Mobilization (699.040001) | LS | 1 | $336,490 | $362,694 | $375,000 | $390,000 | $425,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of November 6, 2025. Compiled by Mirage Metrics.