NYSDOT contract D265578 bid tabulation

Pavement Resurfacing - NY Routes 878 and 454. Let by New York State DOT on November 6, 2025, Nassau, Suffolk, Region 10. 5 bids received; low bid $8,774,477 by Rosemar Contracting Inc.

Owner
New York State DOT
Letting
06 NOV 2025
Pay items
116
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rosemar Contracting Inc$8,774,477Low
2Posillico Civil Inc$9,430,042+7.0%
3Pratt Brothers Inc$10,223,000+17%
4H & L Contracting LLC$10,246,576+17%
5Tully Construction Company Inc$11,076,046+26%
NYSDOT contract D265578: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rosemar Contracting Inc2. Posillico Civil Inc3. Pratt Brothers Inc4. H & L Contracting LLC5. Tully Construction Company Inc
1Clearing and Grubbing (201.06)LS1$15,000$65,000$25,000$30,000$16,000
2Unclassified Excavation and Disposal (203.02)CY18$350.00$300.00$500.00$200.00$270.00
3Embankment In Place (203.03)CY125$90.00$150.00$215.00$130.00$150.00
4Trench and Culvert Excavation (206.0201)CY25$85.00$10.00$20.00$500.00$205.00
5 (206.03100010)292$120.00$110.00$75.00$150.00$50.00
6 (209.11010024)173$175.00$280.00$250.00$300.00$280.00
7 (304.10119917)40$250.00$500.00$60.00$60.00$240.00
8 (404.0001)TON1,170$125.00$125.00$125.00$125.00$125.00
9Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT1,173$125.00$125.00$125.00$125.00$125.00
10Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT722$125.00$125.00$125.00$125.00$125.00
11 (404.0189)TON202$127.00$150.00$95.00$200.00$250.00
12 (404.0961)TON23,300$127.00$150.00$139.00$155.00$120.00
13 (404.1989)TON54$250.00$1,100.00$425.00$90.00$440.00
14 (404.3789)TON74$250.00$1,100.00$425.00$120.00$350.00
15Diluted Tack Coat (407.0102)GAL20,000$3.00$0.10$5.00$3.00$6.00
16Asphalt Pavement Joint Adhesive (418.7603)LF202,375$0.60$0.60$0.65$0.50$1.00
17Production Cold Milling of Bituminous Concrete (490.10)SY122,200$4.00$1.00$4.75$5.20$4.00
18Production Cold-Mill Surface Planing of Bituminous Concrete (490.15)SY74,400$3.15$1.00$6.00$5.75$6.00
19 (520.09000010)4,800$4.00$3.50$4.00$3.00$6.50
20 (603.6102)LF50$30.00$100.00$39.00$25.00$185.00
21 (603.6103)LF50$36.00$110.00$56.00$28.00$190.00
22 (603.6105)LF50$60.00$130.00$84.00$54.00$195.00
23 (604.07200110)60$2,200.00$2,850.00$4,800.00$2,500.00$2,650.00
24 (604.07210110)13$2,200.00$2,850.00$4,800.00$3,200.00$2,650.00
25 (604.07240110)13$3,500.00$3,060.00$4,200.00$3,900.00$3,400.00
26 (604.07290010)10$100.00$300.00$50.00$140.00$350.00
27HPBO (Mod.) Corrugated Beam Guide Railing (606.2701)LF238$76.00$75.50$85.00$68.00$70.00
28Removing and Disposing HPBO (Mod.) Corrugated Beam Guide Railing (606.7101)LF238$35.00$35.00$15.00$13.00$20.00
29Concrete Sidewalks and Driveways (608.0101)CY36$925.00$925.00$1,700.00$1,400.00$620.00
30 (608.01050109)16$6,800.00$5,250.00$6,000.00$6,500.00$7,290.00
31 (608.01050309)1$11,000$8,800.00$10,500$9,900.00$7,370.00
32 (608.01050709)3$15,000$9,250.00$11,000$11,000$11,370
33 (608.01050909)3$10,000$7,725.00$8,500.00$10,000$9,630.00
34 (608.01051009)16$9,500.00$7,500.00$11,000$12,000$9,500.00
35 (608.01051109)24$7,500.00$5,500.00$6,000.00$6,600.00$9,260.00
36 (608.01051209)6$19,000$18,500$21,000$21,000$9,450.00
37 (608.02010015)620$75.00$75.00$60.00$5.00$325.00
38 (608.02020015)410$55.00$80.00$25.00$5.00$60.00
39Surface-Applied Detectable Warning Units (608.20)SY20$585.00$65.00$1,100.00$905.00$50.00
40 (609.0401)LF30$90.00$90.00$60.00$180.00$155.00
41 (609.04070510)374$75.00$106.90$95.00$150.00$100.00
42Topsoil - Roadside (610.1402)CY31$150.00$150.00$183.00$150.00$150.00
43Turf Establishment - Roadside (610.1601)SY263$18.00$18.00$20.00$18.00$18.00
44Improvement of Vegetated Areas (614.05)SY185$30.00$30.00$35.00$30.00$30.00
45 (614.060102)EACH4$950.00$950.00$1,150.00$950.00$950.00
46 (614.060202)EACH4$1,100.00$1,100.00$1,300.00$1,100.00$1,100.00
47 (617.01010024)8$350.00$350.00$350.00$350.00$350.00
48Basic Work Zone Traffic Control (619.01)LS1$502,000$649,800$417,855$682,349$1,245,000
49Type III Construction Barricades (619.04)EACH8$150.00$30.00$300.00$120.00$150.00
50 (619.0901)LF250,000$0.42$0.43$0.45$0.43$0.45
51 (619.10050020)60$60.00$100.00$75.00$25.00$140.00
52 (619.110743)EACH4$7,500.00$1,000.00$15,000$5,500.00$5,790.00
53 (619.110943)EACH4$7,000.00$1,000.00$15,000$5,500.00$6,700.00
54Vehicle Arresting Barrier (619.23)EACH1$8,000.00$9,000.00$15,000$16,000$10,000
55Nighttime Operations (Entire Project) (619.24)LS1$200,000$560,000$345,000$365,000$720,000
56Traffic Control Supervisor (619.25)MONTH14$1,000.00$50.00$1,000.00$100.00$3,500.00
57Pavement Patching (Force Acount) (619.2601)DOL20,000$1.00$1.00$1.00$1.00$1.00
58Cleaning Closed Drainage Systems (621.03)LF1,720$7.50$5.00$4.50$4.00$11.00
59Cleaning Drainage Structures (621.04)EACH113$800.00$1,000.00$850.00$800.00$800.00
60 (621.51010010)250$20.00$25.00$15.00$50.00$15.50
61Survey Operations (625.01)LS1$75,000$10,000$45,000$35,000$55,000
62Cleaning, Sealing and/or Filling Cracks (633.12)LS1$100,000$175,000$275,000$100,000$185,000
63Cleaning, Sealing and/or Filling Joints (633.13)LF200$41.00$50.00$50.00$7.00$50.00
64Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401)SY2,100$15.00$10.00$80.00$5.00$100.00
65 (634.10010015)LS1$10,000$10,000$10,000$10,000$10,000
66Engineer’s Field Office – Type 3 (637.13)MONTH17$5,500.00$7,000.00$6,000.00$8,500.00$9,500.00
67Rain Gauge (637.26)EACH1$500.00$1,000.00$300.00$1,500.00$300.00
68Office Technology and Supplies (637.34)DOL17,500$1.00$1.00$1.00$1.00$1.00
69Construction Testing supplies – Consumables (637.36)DOL200$1.00$1.00$1.00$1.00$1.00
70 (645.03030015)4$2,750.00$2,750.00$3,500.00$2,998.00$4,200.00
71 (645.03040015)2$5,000.00$5,000.00$6,500.00$5,864.00$7,000.00
72Ground-Mounted Sign Panels without Z-bars (645.5101)SF15$64.00$63.50$78.00$75.00$150.00
73Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF454$65.00$65.00$59.00$56.00$150.00
74Overhead Sign Panels (645.61)SF5$100.00$350.00$240.00$230.00$225.00
75Type A Sign Posts (645.81)EACH84$295.00$295.00$240.00$232.00$475.00
76 (645.81090003)2$75.00$75.00$60.00$60.00$90.00
77Pole-Mounted Sign Support System (Band Mounting) (645.85)EACH4$850.00$850.00$439.00$400.00$150.00
78Reference Marker Panel (646.21)EACH74$75.00$75.00$170.00$49.00$95.00
79Steel Post, 1.1 lb/ft (646.31)EACH74$100.00$100.00$70.00$67.00$175.00
80Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH14$275.00$275.00$350.00$336.00$350.00
81Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41)EACH13$150.00$150.00$256.00$248.00$250.00
82Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51)EACH8$75.00$75.00$200.00$200.00$250.00
83Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH77$30.00$30.00$148.00$144.00$225.00
84Pavement Ride Quality Adjustment to Asphalt Level 2 (653.1020)QUALITY UNIT50$125.00$125.00$125.00$125.00$125.00
85 (655.05010010)4$1,400.00$2,800.00$2,500.00$2,277.17$2,000.00
86 (655.07030010)17$1,200.00$1,500.00$1,325.00$1,405.00$1,400.00
87Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706)EACH45$1,500.00$1,850.00$2,100.00$1,735.00$1,700.00
88 (655.16000011)3$400.00$75.00$1,800.00$770.00$900.00
89Adjust Existing Valve Box Elevation (663.33)EACH1$150.00$200.00$500.00$75.00$900.00
90 (670.14480010)10$250.00$850.00$250.00$1,400.00$900.00
91 (675.99000023)10,000$1.00$1.00$1.00$1.00$1.00
92 (680.05010007)8$28,500$28,500$32,000$30,000$33,000
93 (680.05020007)6$4,500.00$4,500.00$5,000.00$5,000.00$5,200.00
94 (680.51050010)4$1,900.00$3,300.00$5,000.00$2,000.00$1,900.00
95 (680.51111010)13$975.00$1,350.00$580.00$600.00$532.00
96 (680.520106)LF53$26.00$26.00$52.00$48.00$48.00
97 (680.520110)LF239$69.00$69.00$74.00$68.10$68.00
98 (680.520205)LF25$16.00$16.00$39.00$35.70$36.00
99 (680.80326110)5$3,500.00$3,500.00$4,300.00$3,951.00$4,000.00
100 (680.83200010)LS1$5,000.00$5,000.00$20,000$5,800.00$6,000.00
101 (685.02000007)88$14.00$100.00$35.00$97.75$150.00
102 (685.03100018)49$130.00$133.93$130.00$133.93$130.00
103 (685.03130018)39$155.00$159.68$155.00$159.68$155.00
104 (685.07200110)190,500$0.65$0.67$0.65$0.67$0.65
105 (685.07200210)12$150.00$154.53$150.00$154.53$150.00
106 (685.07200310)180$175.00$180.29$175.00$180.29$175.00
107 (685.07200410)3,500$1.85$1.91$1.85$1.91$2.00
108 (685.07200510)5,500$2.50$2.58$2.50$2.58$2.50
109 (685.07200610)100,500$0.65$0.67$0.65$0.67$0.65
110 (685.07200710)600$1.85$1.91$1.85$1.91$2.00
111 (691.04000020)24,000$1.00$1.00$1.00$1.00$1.00
112Field Change Payment (FCP) (697.03)DOL720,000$1.00$1.00$1.00$1.00$1.00
113Asphalt Price Adjustment (698.04)DOL56,121$1.00$1.00$1.00$1.00$1.00
114Fuel Price Adjustment (698.05)DOL7,224$1.00$1.00$1.00$1.00$1.00
115Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00
116Mobilization (699.040001)LS1$336,490$362,694$375,000$390,000$425,000
NYSDOT contract D265578: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of November 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy