NYSDOT contract D265724 bid tabulation
Asphalt Pavement Resurfacing NY 27 to Harrison Ave. Let by New York State DOT on March 5, 2026, Nassau, Region 10. 3 bids received; low bid $16,646,464 by Pratt Brothers Inc.
- Owner
- New York State DOT
- Letting
- 05 MAR 2026
- Pay items
- 116
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pratt Brothers Inc | $16,646,464 | Low |
| 2 | H & L Contracting LLC | $17,440,178 | +5.0% |
| 3 | Posillico Civil Inc | $18,858,328 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pratt Brothers Inc | 2. H & L Contracting LLC | 3. Posillico Civil Inc |
|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 240 | $25.00 | $110.00 | $250.00 |
| 2 | Select Granular Fill (203.07) | CY | 77 | $10.00 | $25.00 | $70.00 |
| 3 | Trench and Culvert Excavation (206.0201) | CY | 88 | $8.00 | $60.00 | $10.00 |
| 4 | (209.11010024) | 10 | $425.00 | $375.00 | $350.00 | |
| 5 | (304.00010018) | 3,460 | $4.00 | $1.00 | $2.00 | |
| 6 | (304.10119917) | 333 | $25.00 | $60.00 | $50.00 | |
| 7 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 2,225 | $125.00 | $125.00 | $125.00 |
| 8 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 2,225 | $125.00 | $125.00 | $125.00 |
| 9 | (404.0189) | TON | 3,126 | $121.00 | $125.00 | $136.00 |
| 10 | (404.0961) | TON | 41,363 | $139.00 | $159.55 | $155.00 |
| 11 | (404.1969) | TON | 65 | $765.00 | $385.00 | $450.00 |
| 12 | (404.2589) | TON | 65 | $765.00 | $386.00 | $450.00 |
| 13 | Diluted Tack Coat (407.0102) | GAL | 36,722 | $5.00 | $3.00 | $0.10 |
| 14 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 108,980 | $0.65 | $2.25 | $1.00 |
| 15 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 312,130 | $5.00 | $6.75 | $8.00 |
| 16 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 18,361 | $5.00 | $8.00 | $14.00 |
| 17 | (502.10010018) | LS | 1 | $15,000 | $5,000.00 | $5,000.00 |
| 18 | (510.00210018) | 130 | $1,600.00 | $800.00 | $1,400.00 | |
| 19 | (510.02210018) | 94 | $1,800.00 | $850.00 | $2,400.00 | |
| 20 | (510.20000018) | 442 | $65.00 | $75.00 | $250.00 | |
| 21 | (510.81000018) | 554 | $75.00 | $40.00 | $65.00 | |
| 22 | (510.91000018) | 816 | $12.00 | $11.00 | $1.00 | |
| 23 | (510.91100018) | 15 | $12.00 | $25.00 | $8.00 | |
| 24 | (520.05000010) | 708 | $5.75 | $5.10 | $5.75 | |
| 25 | (520.09000010) | 4,432 | $3.25 | $4.00 | $3.15 | |
| 26 | Temporary Timber Sheeting (552.12) | SF | 625 | $2.00 | $2.00 | $1.00 |
| 27 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 336 | $60.00 | $40.00 | $250.00 |
| 28 | (603.6002) | LF | 20 | $495.00 | $200.00 | $440.00 |
| 29 | (603.77210015) | 2 | $2,000.00 | $500.00 | $700.00 | |
| 30 | (604.07200110) | 27 | $1,200.00 | $3,200.00 | $1,340.00 | |
| 31 | (604.07210110) | 1 | $1,200.00 | $3,000.00 | $1,340.00 | |
| 32 | (604.07240110) | 1 | $4,000.00 | $3,400.00 | $4,000.00 | |
| 33 | (604.07290010) | 25 | $200.00 | $165.00 | $180.00 | |
| 34 | (604.07800010) | 10 | $1,700.00 | $550.00 | $250.00 | |
| 35 | (604.13000011) | 1 | $600.00 | $1,500.00 | $7,000.00 | |
| 36 | (604.501012) | LF | 4 | $5,000.00 | $1,000.00 | $3,000.00 |
| 37 | Concrete Sidewalks and Driveways (608.0101) | CY | 37 | $1,400.00 | $1,200.00 | $925.00 |
| 38 | (608.01050109) | 42 | $5,000.00 | $5,500.00 | $5,350.00 | |
| 39 | (608.01050209) | 8 | $3,900.00 | $3,600.00 | $5,675.00 | |
| 40 | (608.01050309) | 7 | $9,800.00 | $9,250.00 | $5,750.00 | |
| 41 | (608.01050409) | 6 | $9,300.00 | $8,750.00 | $5,900.00 | |
| 42 | (608.01050709) | 5 | $8,700.00 | $8,200.00 | $6,775.00 | |
| 43 | (608.01050809) | 8 | $6,900.00 | $6,500.00 | $7,250.00 | |
| 44 | (608.01050909) | 8 | $7,200.00 | $6,750.00 | $5,475.00 | |
| 45 | (608.01051009) | 10 | $7,400.00 | $7,000.00 | $5,675.00 | |
| 46 | (608.01051109) | 8 | $5,500.00 | $5,200.00 | $5,175.00 | |
| 47 | (608.01051309) | 1 | $9,000.00 | $8,500.00 | $6,550.00 | |
| 48 | (608.02010015) | 434 | $70.00 | $5.00 | $470.00 | |
| 49 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 1 | $1,500.00 | $2,000.00 | $700.00 |
| 50 | (608.02020015) | 291 | $36.00 | $5.00 | $70.00 | |
| 51 | Surface-Applied Detectable Warning Units (608.20) | SY | 10 | $1,000.00 | $400.00 | $775.00 |
| 52 | (608.94010007) | 1,648 | $39.00 | $36.50 | $36.50 | |
| 53 | Cast-in-Place Concrete Curb (As Detailed) (609.04) | LF | 24 | $120.00 | $100.00 | $135.00 |
| 54 | (609.04010510) | 990 | $56.00 | $45.00 | $68.00 | |
| 55 | (609.04030510) | 170 | $59.00 | $48.00 | $75.00 | |
| 56 | Turf Establishment - Roadside (610.1601) | SY | 1,000 | $10.00 | $8.00 | $6.50 |
| 57 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $665,000 | $750,000 | $1,200,000 |
| 58 | Type III Construction Barricades (619.04) | EACH | 150 | $75.00 | $130.00 | $100.00 |
| 59 | (619.0901) | LF | 71,327 | $0.60 | $0.48 | $0.50 |
| 60 | (619.10050020) | 524 | $75.00 | $7.00 | $30.00 | |
| 61 | (619.110933) | EACH | 1 | $10,000 | $55,000 | $6,000.00 |
| 62 | (619.111133) | EACH | 4 | $10,000 | $50,000 | $4,500.00 |
| 63 | Vehicle Arresting Barrier (619.23) | EACH | 50 | $500.00 | $100.00 | $1.00 |
| 64 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $609,098 | $648,000 | $750,000 |
| 65 | Traffic Control Supervisor (619.25) | MONTH | 9 | $1,000.00 | $100.00 | $100.00 |
| 66 | Pavement Patching (Force Acount) (619.2601) | DOL | 25,000 | $1.00 | $1.00 | $1.00 |
| 67 | Cleaning Closed Drainage Systems (621.03) | LF | 2,490 | $4.00 | $4.00 | $4.00 |
| 68 | Cleaning Drainage Structures (621.04) | EACH | 250 | $875.00 | $850.00 | $900.00 |
| 69 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 10,653 | $5.00 | $2.00 | $27.00 |
| 70 | Survey Operations (625.01) | LS | 1 | $125,000 | $20,000 | $30,000 |
| 71 | Cleaning, Sealing and/or Filling Joints (633.13) | LF | 198,520 | $2.50 | $0.55 | $0.05 |
| 72 | Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15) | SY | 20 | $815.00 | $54.00 | $500.00 |
| 73 | Field Laboratory (637.01) | EACH | 1 | $15,000 | $3,800.00 | $20,000 |
| 74 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,500.00 | $1,500.00 | $4,500.00 |
| 75 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 11 | $5,000.00 | $7,000.00 | $11,000 |
| 76 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 |
| 77 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 |
| 78 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 79 | (637.41000115) | 9 | $300.00 | $200.00 | $250.00 | |
| 80 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 102 | $65.00 | $65.00 | $150.00 |
| 81 | Type A Sign Posts (645.81) | EACH | 49 | $262.00 | $262.00 | $262.00 |
| 82 | Reference Marker Panel (646.21) | EACH | 28 | $91.00 | $91.00 | $91.00 |
| 83 | Steel Post, 1.1 lb/ft (646.31) | EACH | 4 | $241.00 | $241.00 | $241.00 |
| 84 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 20 | $281.00 | $281.00 | $281.00 |
| 85 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 20 | $141.00 | $141.00 | $141.00 |
| 86 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 53 | $31.00 | $31.00 | $31.00 |
| 87 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 4 | $37.00 | $37.00 | $37.00 |
| 88 | (648.50010008) | 180 | $25.00 | $5.00 | $1.00 | |
| 89 | Pavement Ride Quality Adjustment to Asphalt Level 2 (653.1020) | QUALITY UNIT | 60 | $110.00 | $110.00 | $110.00 |
| 90 | (655.05010010) | 28 | $1,100.00 | $2,000.00 | $900.00 | |
| 91 | (655.07030010) | 1 | $1,700.00 | $1,245.00 | $2,400.00 | |
| 92 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 27 | $1,800.00 | $1,700.00 | $1,800.00 |
| 93 | (662.62000010) | 11 | $1,100.00 | $1,800.00 | $900.00 | |
| 94 | Adjust Existing Valve Box Elevation (663.33) | EACH | 33 | $65.00 | $75.00 | $170.00 |
| 95 | (670.14480010) | 21 | $665.00 | $900.00 | $900.00 | |
| 96 | (675.99000023) | 10,000 | $1.00 | $1.00 | $1.00 | |
| 97 | (680.05010007) | 30 | $37,000 | $31,000 | $31,000 | |
| 98 | (680.05020007) | 30 | $5,025.00 | $3,700.00 | $3,700.00 | |
| 99 | (680.51111010) | 33 | $900.00 | $1,200.00 | $2,700.00 | |
| 100 | (680.80320014) | 11 | $4,800.00 | $3,200.00 | $3,200.00 | |
| 101 | (680.83200010) | LS | 1 | $35,000 | $5,000.00 | $5,000.00 |
| 102 | (685.02000010) | 9 | $10.00 | $140.00 | $300.00 | |
| 103 | (685.03100018) | 48 | $225.00 | $225.00 | $225.00 | |
| 104 | (685.07200110) | 199,473 | $0.75 | $0.72 | $1.00 | |
| 105 | (685.07200210) | 4 | $150.00 | $150.00 | $150.00 | |
| 106 | (685.07200310) | 258 | $175.00 | $175.00 | $175.00 | |
| 107 | (685.07200410) | 2,474 | $2.00 | $1.95 | $2.00 | |
| 108 | (685.07200510) | 85,380 | $2.50 | $2.40 | $2.50 | |
| 109 | (685.07200610) | 66,085 | $0.75 | $0.72 | $1.00 | |
| 110 | (685.07200710) | 3,228 | $2.00 | $1.95 | $2.00 | |
| 111 | (691.04000020) | 126,000 | $1.00 | $1.00 | $1.00 | |
| 112 | Field Change Payment (FCP) (697.03) | DOL | 1,153,000 | $1.00 | $1.00 | $1.00 |
| 113 | Asphalt Price Adjustment (698.04) | DOL | 12,562.81 | $1.00 | $1.00 | $1.00 |
| 114 | Fuel Price Adjustment (698.05) | DOL | 639 | $1.00 | $1.00 | $1.00 |
| 115 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 116 | Mobilization (699.040001) | LS | 1 | $625,000 | $667,000 | $725,320 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 5, 2026. Compiled by Mirage Metrics.