NYSDOT contract D265739 bid tabulation
Republic Airport - Fire Loop Improvements. Let by New York State DOT on March 26, 2026, Suffolk, Region MO. 3 bids received; low bid $428,000 by Bancker Construction Corp.
- Owner
- New York State DOT
- Letting
- 26 MAR 2026
- Pay items
- 29
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bancker Construction Corp | $428,000 | Low |
| 2 | Araz Industries Inc | $618,360 | +44% |
| 3 | G & M Earth Moving Inc | $644,000 | +50% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bancker Construction Corp | 2. Araz Industries Inc | 3. G & M Earth Moving Inc |
|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 5 | $100.00 | $600.00 | $125.00 |
| 2 | Select Granular Fill (203.07) | CY | 350 | $135.00 | $58.00 | $95.00 |
| 3 | Trench and Culvert Excavation (206.0201) | CY | 370 | $105.00 | $32.00 | $2.00 |
| 4 | Test Pit Excavation (206.05) | EACH | 3 | $100.00 | $1,000.00 | $12,000 |
| 5 | Silt Fence - Temporary (209.13) | LF | 870 | $3.00 | $12.00 | $10.00 |
| 6 | Drainage Structure Inlet Protection, Silt Fence – Temporary (209.1701) | LF | 40 | $3.00 | $18.00 | $30.00 |
| 7 | (304.10119917) | 10 | $1.00 | $700.00 | $1,000.00 | |
| 8 | (404.1271) | TON | 25 | $1.00 | $600.00 | $600.00 |
| 9 | (502.0121) | 5 | $1.00 | $2,900.00 | $3,000.00 | |
| 10 | Performance Concrete Quality Adjustment - PCC Pavement (502.99) | QUALITY UNIT | 1 | $26.25 | $26.25 | $26.25 |
| 11 | Topsoil – Reuse On-Site Materials (610.1401) | CY | 30 | $20.00 | $49.00 | $225.00 |
| 12 | Preparation of Subsoil for Turf Establishment (610.15) | SY | 270 | $30.00 | $20.00 | $25.00 |
| 13 | Turf Establishment -Lawns (610.1602) | SY | 270 | $30.00 | $23.00 | $15.00 |
| 14 | Survey Operations (625.01) | LS | 1 | $1,000.00 | $36,498 | $15,000 |
| 15 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $500.00 | $1,000.00 | $2,500.00 |
| 16 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 3 | $800.00 | $20,000 | $15,000 |
| 17 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 18 | (663.0112) | LF | 13 | $200.00 | $560.00 | $2,000.00 |
| 19 | (663.0116) | LF | 473 | $200.00 | $312.00 | $375.00 |
| 20 | (663.1012) | EACH | 3 | $24,200 | $24,000 | $15,000 |
| 21 | (663.1016) | EACH | 1 | $25,000 | $53,000 | $30,000 |
| 22 | Iron Water Main Fittings (10 - 16 inch diameter) (663.2002) | LB | 2,700 | $27.00 | $10.00 | $15.00 |
| 23 | (689.C0000126) | LS | 1 | $20,000 | $63,000 | $70,000 |
| 24 | (689.F1622626) | 70 | $105.00 | $80.00 | $125.00 | |
| 25 | (689.F1622726) | 70 | $105.00 | $330.00 | $375.00 | |
| 26 | Field Change Payment (FCP) (697.03) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 27 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 28 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 29 | Mobilization (699.040001) | LS | 1 | $14,804 | $23,000 | $19,134 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.