NYSDOT contract D265742 bid tabulation
ASPHALT RESURFACING I495 QUEENS/NASSAU COUNTYLINE TO EXIT 40. Let by New York State DOT on March 26, 2026, Nassau, Region 10. 2 bids received; low bid $31,755,117 by Posillico/H&L JV.
- Owner
- New York State DOT
- Letting
- 26 MAR 2026
- Pay items
- 119
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Posillico/H&L JV | $31,755,117 | Low |
| 2 | Tully Construction Company Inc | $44,482,378 | +40% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Posillico/H&L JV | 2. Tully Construction Company Inc |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $100,000 | $17,500 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 324 | $60.00 | $175.00 |
| 3 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 525 | $80.00 | $275.00 |
| 4 | (209.11010024) | 632 | $100.00 | $280.00 | |
| 5 | (304.00010018) | 346 | $6.00 | $3.00 | |
| 6 | (304.10119917) | 10 | $80.00 | $135.00 | |
| 7 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 4,601 | $125.00 | $125.00 |
| 8 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 4,601 | $125.00 | $125.00 |
| 9 | (404.0189) | TON | 4,521 | $112.00 | $112.00 |
| 10 | (404.0951) | TON | 90,967 | $155.00 | $145.00 |
| 11 | (404.1989) | TON | 417 | $290.00 | $135.00 |
| 12 | (404.2589) | TON | 635 | $320.00 | $380.00 |
| 13 | (404.90710218) | 551 | $900.00 | $500.00 | |
| 14 | Diluted Tack Coat (407.0102) | GAL | 84,750 | $0.10 | $10.00 |
| 15 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 608,877 | $0.72 | $1.00 |
| 16 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 799,229 | $3.00 | $6.00 |
| 17 | (490.17011018) | 6,364 | $15.00 | $11.00 | |
| 18 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 6,026 | $20.00 | $11.00 |
| 19 | (502.10010018) | LS | 1 | $50,000 | $17,000 |
| 20 | (510.00210018) | 26 | $1,500.00 | $1,875.00 | |
| 21 | (510.02210018) | 4 | $2,500.00 | $2,600.00 | |
| 22 | (510.20000018) | 118 | $180.00 | $250.00 | |
| 23 | (510.81000018) | 176 | $50.00 | $110.00 | |
| 24 | (510.91000018) | 72 | $10.00 | $17.00 | |
| 25 | (510.91100018) | 72 | $5.00 | $20.00 | |
| 26 | (520.05000010) | 368 | $5.50 | $11.50 | |
| 27 | (520.09000010) | 8,936 | $3.15 | $7.00 | |
| 28 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 96 | $10.00 | $120.00 |
| 29 | (604.07200110) | 148 | $1,000.00 | $4,000.00 | |
| 30 | (604.07210110) | 148 | $500.00 | $4,000.00 | |
| 31 | (604.07240110) | 57 | $1,000.00 | $2,500.00 | |
| 32 | (604.07290010) | 253 | $150.00 | $280.00 | |
| 33 | (604.07800010) | 253 | $150.00 | $2,500.00 | |
| 34 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 3 | $125.00 | $125.00 |
| 35 | (608.01050010) | 7 | $1,300.00 | $4,500.00 | |
| 36 | (608.01050109) | 1 | $5,700.00 | $6,500.00 | |
| 37 | (608.01050209) | 1 | $5,700.00 | $7,000.00 | |
| 38 | (608.01050909) | 2 | $6,100.00 | $7,000.00 | |
| 39 | (608.02010015) | 44 | $240.00 | $280.00 | |
| 40 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 53 | $600.00 | $700.00 |
| 41 | (608.02020015) | 22 | $50.00 | $145.00 | |
| 42 | (609.04010510) | 61 | $100.00 | $90.00 | |
| 43 | Topsoil - Roadside (610.1402) | CY | 692 | $98.00 | $90.00 |
| 44 | Turf Establishment - Roadside (610.1601) | SY | 692 | $4.00 | $4.00 |
| 45 | Watering Vegetation (610.19) | 1,000 GALLONS | 101 | $98.00 | $100.00 |
| 46 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,150,000 | $6,956,000 |
| 47 | Type III Construction Barricades (619.04) | EACH | 523 | $100.00 | $100.00 |
| 48 | (619.0901) | LF | 1,929,219 | $0.35 | $0.35 |
| 49 | (619.10050020) | 1,148 | $9.00 | $50.00 | |
| 50 | (619.110743) | EACH | 5 | $2,500.00 | $5,700.00 |
| 51 | (619.111133) | EACH | 1 | $2,500.00 | $7,000.00 |
| 52 | Vehicle Arresting Barrier (619.23) | EACH | 3 | $30,000 | $10,000 |
| 53 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $900,000 | $2,100,000 |
| 54 | Pavement Patching (Force Acount) (619.2601) | DOL | 70,000 | $1.00 | $1.00 |
| 55 | Cleaning Closed Drainage Systems (621.03) | LF | 29,606 | $1.00 | $15.00 |
| 56 | Cleaning Drainage Structures (621.04) | EACH | 625 | $650.00 | $825.00 |
| 57 | Survey Operations (625.01) | LS | 1 | $100,000 | $80,000 |
| 58 | Cleaning, Sealing and/or Filling Cracks (633.12) | LS | 1 | $400,000 | $675,000 |
| 59 | Cleaning, Sealing and/or Filling Joints (633.13) | LF | 7,119 | $1.50 | $12.00 |
| 60 | Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15) | SY | 1,068 | $20.00 | $75.00 |
| 61 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $5,000.00 | $5,700.00 |
| 62 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 10 | $9,910.00 | $18,000 |
| 63 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 |
| 64 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 |
| 65 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 |
| 66 | (637.41000115) | 10 | $200.00 | $600.00 | |
| 67 | (637.41000215) | 10 | $200.00 | $600.00 | |
| 68 | (637.41000315) | 10 | $200.00 | $600.00 | |
| 69 | (637.41000415) | 10 | $200.00 | $600.00 | |
| 70 | (637.41000515) | 10 | $200.00 | $600.00 | |
| 71 | (637.41000615) | 10 | $200.00 | $600.00 | |
| 72 | (637.41000715) | 10 | $200.00 | $600.00 | |
| 73 | (645.03040015) | 2 | $5,705.00 | $3,500.00 | |
| 74 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 274 | $58.00 | $125.00 |
| 75 | Type A Sign Posts (645.81) | EACH | 40 | $364.00 | $325.00 |
| 76 | Reference Marker Panel (646.21) | EACH | 39 | $178.00 | $55.00 |
| 77 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 46 | $142.00 | $75.00 |
| 78 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 291 | $56.00 | $95.00 |
| 79 | Steel Post, 1.1 lb/ft (646.31) | EACH | 230 | $153.00 | $150.00 |
| 80 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 26 | $41.00 | $125.00 |
| 81 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 16 | $45.00 | $150.00 |
| 82 | (647.83001002) | 230 | $8.00 | $10.00 | |
| 83 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 99,711 | $0.50 | $0.35 |
| 84 | Pavement Ride Quality Adjustment to Asphalt Level 2 (653.1020) | QUALITY UNIT | 7,425 | $125.00 | $125.00 |
| 85 | Cast Frame F3, Mountable Curb Box CM3 & Reticuline Grate G3 (655.0703) | EACH | 5 | $500.00 | $2,290.00 |
| 86 | (655.07030010) | 143 | $500.00 | $1,850.00 | |
| 87 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 1 | $500.00 | $2,290.00 |
| 88 | Manhole Frame & Cover (655.1202) | EACH | 6 | $500.00 | $720.00 |
| 89 | (662.62000010) | 6 | $1,000.00 | $5,000.00 | |
| 90 | (670.0106) | EACH | 4 | $5,000.00 | $3,900.00 |
| 91 | (670.1130) | EACH | 4 | $5,200.00 | $3,900.00 |
| 92 | Breakaway Transformer Base (Aluminum) (670.19) | EACH | 4 | $1,200.00 | $2,000.00 |
| 93 | Ground Wire No. 6 AWG. (670.7501) | LF | 175 | $3.50 | $6.00 |
| 94 | Performance Concrete Quality Adjustment (670.99) | QUALITY UNIT | 1 | $28.65 | $28.65 |
| 95 | (675.99000023) | 10,000 | $1.00 | $1.00 | |
| 96 | (680.51111010) | 1 | $2,539.20 | $1,870.00 | |
| 97 | (680.520103) | LF | 175 | $24.00 | $25.00 |
| 98 | (680.520106) | LF | 175 | $32.00 | $35.00 |
| 99 | (680.520203) | LF | 355 | $16.00 | $38.00 |
| 100 | Inductance Loop Installation (680.54) | LF | 2,560 | $30.64 | $38.00 |
| 101 | Shielded Lead-in Cable (680.71) | LF | 760 | $5.00 | $3.50 |
| 102 | Inductance Loop Wire (680.72) | LF | 8,040 | $5.00 | $1.50 |
| 103 | (680.83200010) | LS | 1 | $10,000 | $9,000.00 |
| 104 | (680.99910011) | LS | 1 | $5,000.00 | $5,000.00 |
| 105 | (683.91150010) | 4 | $16,000 | $16,700 | |
| 106 | (685.02000007) | 143 | $150.00 | $10.00 | |
| 107 | (685.03130018) | 130 | $145.00 | $145.00 | |
| 108 | (685.07200210) | 17 | $145.00 | $145.00 | |
| 109 | (685.07200410) | 224,862 | $1.50 | $1.60 | |
| 110 | (685.07200510) | 8,216 | $2.00 | $2.00 | |
| 111 | (685.07200710) | 6,066 | $1.50 | $1.60 | |
| 112 | (685.16010014) | 827,140 | $1.45 | $1.50 | |
| 113 | (685.17010014) | 168,120 | $1.45 | $1.50 | |
| 114 | (691.04000020) | 189,000 | $1.00 | $1.00 | |
| 115 | Field Change Payment (FCP) (697.03) | DOL | 2,413,000 | $1.00 | $1.00 |
| 116 | Asphalt Price Adjustment (698.04) | DOL | 46,906.36 | $1.00 | $1.00 |
| 117 | Fuel Price Adjustment (698.05) | DOL | 8,521 | $1.00 | $1.00 |
| 118 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 119 | Mobilization (699.040001) | LS | 1 | $1,198,458 | $1,520,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.