NYSDOT contract D265751 bid tabulation
RESURFACING - Route 209 - Port Jervis Line to Route 211. Let by New York State DOT on March 26, 2026, Orange, Region 08. 4 bids received; low bid $9,441,441 by Argenio Brothers Inc.
- Owner
- New York State DOT
- Letting
- 26 MAR 2026
- Pay items
- 36
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Argenio Brothers Inc | $9,441,441 | Low |
| 2 | Kyle Conti Construction LLC | $10,162,261 | +8.0% |
| 3 | J D'Annunzio & Sons Inc | $10,917,000 | +16% |
| 4 | Crisdel Group Inc | $11,717,172 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Argenio Brothers Inc | 2. Kyle Conti Construction LLC | 3. J D'Annunzio & Sons Inc | 4. Crisdel Group Inc |
|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 1,519 | $315.00 | $460.00 | $570.00 | $384.11 |
| 2 | (203.24010017) | 308 | $78.00 | $210.00 | $160.00 | $63.88 | |
| 3 | (304.00010018) | 47,250 | $7.25 | $0.15 | $0.70 | $5.98 | |
| 4 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1,168 | $140.00 | $140.00 | $140.00 | $140.00 |
| 5 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 300 | $140.00 | $140.00 | $140.00 | $140.00 |
| 6 | (404.0179) | TON | 532 | $75.00 | $180.00 | $125.00 | $168.34 |
| 7 | (404.1979) | TON | 11,671 | $120.50 | $145.00 | $155.00 | $166.52 |
| 8 | (404.3779) | TON | 7,810 | $144.15 | $165.00 | $156.00 | $166.82 |
| 9 | (406.1262) | TON | 14,863 | $104.75 | $130.00 | $165.00 | $151.77 |
| 10 | (407.01040009) | 9,564 | $6.25 | $11.00 | $6.00 | $3.94 | |
| 11 | (407.01110004) | 25,937 | $0.11 | $0.60 | $0.35 | $0.28 | |
| 12 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 39,232 | $1.07 | $1.00 | $1.00 | $1.21 |
| 13 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 30,667 | $16.75 | $18.50 | $26.00 | $31.54 |
| 14 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 123,303 | $2.35 | $3.65 | $7.00 | $7.04 |
| 15 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 2 | $140.00 | $140.00 | $140.00 | $140.00 |
| 16 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 95 | $450.00 | $485.00 | $280.00 | $539.06 |
| 17 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $1,536,500 | $1,250,000 | $800,000 | $1,443,000 |
| 18 | (619.0901) | LF | 220,384 | $0.38 | $0.40 | $0.25 | $0.40 |
| 19 | (619.110511) | EACH | 3 | $11,800 | $14,000 | $10,000 | $7,862.40 |
| 20 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 8,390 | $4.75 | $3.00 | $6.25 | $3.55 |
| 21 | Asphalt Gutter (624.020101) | TON | 47 | $300.00 | $280.00 | $485.00 | $258.37 |
| 22 | Plant Production Quality Adjustment to 624.020101 (624.020110) | QUALITY UNIT | 3 | $140.00 | $140.00 | $140.00 | $140.00 |
| 23 | Survey Operations (625.01) | LS | 1 | $277,450 | $75,000 | $10,000 | $58,285 |
| 24 | (627.50140008) | 22,668 | $5.25 | $8.50 | $6.75 | $5.28 | |
| 25 | (633.05040008) | LS | 1 | $85,100 | $74,725 | $123,234 | $55,761 |
| 26 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 9 | $4,500.00 | $8,250.00 | $6,400.00 | $6,306.69 |
| 27 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | (649.31000008) | 24,937 | $0.50 | $1.15 | $0.85 | $0.37 | |
| 29 | (685.16010014) | 109,416 | $1.40 | $1.40 | $1.30 | $1.47 | |
| 30 | (685.17010009) | 39,739 | $1.00 | $1.00 | $0.65 | $1.01 | |
| 31 | (685.17010014) | 12,962 | $1.40 | $1.40 | $1.30 | $1.47 | |
| 32 | Field Change Payment (FCP) (697.03) | DOL | 475,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 33 | Asphalt Price Adjustment (698.04) | DOL | 12,580 | $1.00 | $1.00 | $1.00 | $1.00 |
| 34 | Fuel Price Adjustment (698.05) | DOL | 5,608 | $1.00 | $1.00 | $1.00 | $1.00 |
| 35 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 36 | Mobilization (699.040001) | LS | 1 | $356,913 | $380,000 | $415,000 | $440,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.