NYSDOT contract D265818 bid tabulation
Asphalt Pavement Resurfacing - Various Locations. Let by New York State DOT on October 1, 2026, Suffolk, Region 10. 5 bids received; low bid $23,251,338 by Rosemar Contracting Inc.
- Owner
- New York State DOT
- Letting
- 01 OCT 2026
- Pay items
- 116
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rosemar Contracting Inc | $23,251,338 | Low |
| 2 | H & L Contracting LLC | $23,388,637 | +1.0% |
| 3 | Posillico Civil Inc | $27,078,434 | +16% |
| 4 | Pratt Brothers Inc | $27,878,787 | +20% |
| 5 | Tully Construction Company Inc | $52,321,890 | +125% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rosemar Contracting Inc | 2. H & L Contracting LLC | 3. Posillico Civil Inc | 4. Pratt Brothers Inc | 5. Tully Construction Company Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $50,000 | $25,000 | $65,000 | $65,000 | $50,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 290 | $100.00 | $35.00 | $10.00 | $90.00 | $360.00 |
| 3 | Test Pit Excavation (206.05) | EACH | 15 | $300.00 | $1,000.00 | $995.00 | $500.00 | $2,150.00 |
| 4 | (304.00010018) | 3,820 | $1.30 | $1.89 | $2.00 | $4.00 | $13.00 | |
| 5 | (304.10119917) | 143 | $130.00 | $45.00 | $60.00 | $75.00 | $373.00 | |
| 6 | (402.25020018) | 90 | $40.00 | $75.56 | $80.00 | $42.50 | $95.00 | |
| 7 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 3,701 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 8 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 1,540 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 9 | (404.0189) | TON | 47 | $132.00 | $310.00 | $380.00 | $500.00 | $760.00 |
| 10 | (404.0961) | TON | 46,259 | $132.00 | $160.00 | $165.00 | $151.00 | $200.00 |
| 11 | (404.1989) | TON | 75 | $300.00 | $480.00 | $380.00 | $1,200.00 | $590.00 |
| 12 | (404.2589) | TON | 8 | $300.00 | $500.00 | $380.00 | $1,200.00 | $610.00 |
| 13 | (404.90710218) | 100 | $550.00 | $1,600.00 | $750.00 | $500.00 | $630.00 | |
| 14 | Diluted Tack Coat (407.0102) | GAL | 37,640 | $1.00 | $0.15 | $0.10 | $5.75 | $11.30 |
| 15 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 157,700 | $1.05 | $2.00 | $0.65 | $2.00 | $1.21 |
| 16 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 398,290 | $3.75 | $4.50 | $5.25 | $5.75 | $4.75 |
| 17 | (490.17011018) | 1,415 | $15.00 | $45.00 | $16.00 | $25.00 | $8.40 | |
| 18 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 88 | $100.00 | $10.00 | $200.00 | $45.00 | $8.40 |
| 19 | (502.10010018) | LS | 1 | $10,000 | $5,000.00 | $15,000 | $15,000 | $6,000.00 |
| 20 | (502.9100) | 342 | $50.00 | $1.00 | $5.00 | $15.00 | $18.00 | |
| 21 | (510.00210018) | 115 | $1,400.00 | $725.00 | $1,300.00 | $2,800.00 | $2,000.00 | |
| 22 | (510.02210018) | 5 | $2,000.00 | $2,100.00 | $4,100.00 | $4,000.00 | $4,200.00 | |
| 23 | (510.20000018) | 509 | $150.00 | $110.00 | $100.00 | $100.00 | $240.00 | |
| 24 | (510.81000018) | 350 | $50.00 | $70.00 | $65.00 | $200.00 | $80.00 | |
| 25 | (510.91000018) | 415 | $50.00 | $12.00 | $15.00 | $15.00 | $18.00 | |
| 26 | (520.05000010) | 689 | $5.00 | $10.60 | $6.00 | $6.00 | $6.25 | |
| 27 | (520.09000010) | 16,207 | $3.75 | $2.75 | $4.00 | $3.50 | $3.50 | |
| 28 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 80 | $65.00 | $60.00 | $50.00 | $235.00 | $120.00 |
| 29 | (604.07200110) | 103 | $2,600.00 | $1,500.00 | $1,350.00 | $2,100.00 | $3,400.00 | |
| 30 | (604.07210110) | 28 | $2,600.00 | $1,500.00 | $1,350.00 | $3,000.00 | $3,400.00 | |
| 31 | (604.07240110) | 21 | $4,000.00 | $2,500.00 | $3,000.00 | $4,750.00 | $5,250.00 | |
| 32 | (604.07290010) | 30 | $300.00 | $145.00 | $130.00 | $250.00 | $560.00 | |
| 33 | (608.01050009) | 1 | $10,500 | $20,422 | $5,100.00 | $21,000 | $35,000 | |
| 34 | (608.01050109) | 192 | $6,800.00 | $6,421.98 | $5,630.00 | $7,000.00 | $28,000 | |
| 35 | (608.01050209) | 85 | $7,100.00 | $4,921.98 | $6,025.00 | $5,400.00 | $28,000 | |
| 36 | (608.01050309) | 31 | $10,600 | $9,921.98 | $9,070.00 | $11,300 | $28,000 | |
| 37 | (608.01050409) | 15 | $10,800 | $9,421.98 | $9,450.00 | $10,700 | $29,000 | |
| 38 | (608.01050509) | 8 | $12,000 | $11,672 | $9,285.00 | $13,400 | $28,000 | |
| 39 | (608.01050609) | 11 | $15,000 | $13,422 | $13,090 | $15,000 | $31,000 | |
| 40 | (608.01050709) | 23 | $10,500 | $8,921.98 | $14,225 | $10,100 | $28,000 | |
| 41 | (608.01050809) | 2 | $10,000 | $7,171.98 | $9,725.00 | $8,100.00 | $38,000 | |
| 42 | (608.01050909) | 191 | $7,000.00 | $8,171.00 | $8,740.00 | $9,200.00 | $29,000 | |
| 43 | (608.01051009) | 69 | $7,200.00 | $8,221.98 | $9,340.00 | $9,300.00 | $28,000 | |
| 44 | (608.01051109) | 21 | $6,800.00 | $5,921.98 | $6,125.00 | $6,600.00 | $28,000 | |
| 45 | (608.01051209) | 5 | $20,000 | $18,672 | $10,740 | $21,700 | $28,000 | |
| 46 | (608.01051309) | 9 | $7,000.00 | $9,171.98 | $5,760.00 | $10,400 | $28,000 | |
| 47 | (608.02010015) | 7,031 | $90.00 | $5.00 | $10.00 | $75.00 | $256.00 | |
| 48 | (608.02020015) | 3,515 | $75.00 | $5.00 | $10.00 | $39.00 | $95.00 | |
| 49 | (608.10080008) | 786 | $21.00 | $55.00 | $20.00 | $75.00 | $44.00 | |
| 50 | Embedded Detectable Warning Units (608.21) | SY | 3 | $695.00 | $360.00 | $720.00 | $1,000.00 | $180.00 |
| 51 | Cast-in-Place Concrete Curb (As Detailed) (609.04) | LF | 22 | $150.00 | $100.00 | $75.00 | $500.00 | $225.00 |
| 52 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,000,000 | $825,000 | $1,975,000 | $1,950,549 | $5,100,000 |
| 53 | Type III Construction Barricades (619.04) | EACH | 24 | $100.00 | $135.00 | $70.00 | $200.00 | $300.00 |
| 54 | (619.10050020) | 860 | $45.00 | $8.00 | $40.00 | $30.00 | $24.00 | |
| 55 | (619.110943) | EACH | 8 | $10,000 | $2,000.00 | $12,000 | $10,000 | $33,300 |
| 56 | Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613) | MONTH | 10 | $290.00 | $289.00 | $289.00 | $345.00 | $345.00 |
| 57 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $250,000 | $450,000 | $995,000 | $445,000 | $1,950,000 |
| 58 | Cleaning Closed Drainage Systems (621.03) | LF | 250 | $15.00 | $20.00 | $5.00 | $10.00 | $30.00 |
| 59 | Cleaning Drainage Structures (621.04) | EACH | 737 | $800.00 | $625.00 | $1,100.00 | $1,025.00 | $1,100.00 |
| 60 | Survey Operations (625.01) | LS | 1 | $100,000 | $50,000 | $55,000 | $115,000 | $300,000 |
| 61 | Cleaning, Sealing and/or Filling Cracks (633.12) | LS | 1 | $150,000 | $65,000 | $385,000 | $395,000 | $400,000 |
| 62 | Cleaning, Sealing and/or Filling Joints (633.13) | LF | 16,018 | $6.00 | $0.50 | $8.95 | $8.95 | $10.71 |
| 63 | Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401) | SY | 3,984 | $15.00 | $10.00 | $5.00 | $50.00 | $135.00 |
| 64 | Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15) | SY | 27 | $150.00 | $75.00 | $460.00 | $160.00 | $345.00 |
| 65 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,500.00 | $4,800.00 | $5,600.00 | $1,500.00 | $3,600.00 |
| 66 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 14 | $6,000.00 | $6,500.00 | $9,900.00 | $9,000.00 | $13,000 |
| 67 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 68 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 69 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 70 | (637.41000115) | 14 | $180.00 | $200.00 | $250.00 | $325.00 | $1,200.00 | |
| 71 | (639.21010011) | LS | 1 | $75,000 | $75,000 | $75,000 | $80,000 | $75,000 |
| 72 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 22 | $65.00 | $65.00 | $65.00 | $65.00 | $110.00 |
| 73 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 71 | $75.00 | $75.00 | $75.00 | $75.00 | $110.00 |
| 74 | Type A Sign Posts (645.81) | EACH | 184 | $425.00 | $400.00 | $400.00 | $400.00 | $450.00 |
| 75 | (645.81090003) | 6 | $125.00 | $125.00 | $125.00 | $125.00 | $150.00 | |
| 76 | Reference Marker Panel (646.21) | EACH | 11 | $250.00 | $250.00 | $250.00 | $250.00 | $65.00 |
| 77 | Steel Post, 1.1 lb/ft (646.31) | EACH | 7 | $320.00 | $320.00 | $320.00 | $320.00 | $150.00 |
| 78 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 253 | $150.00 | $150.00 | $150.00 | $150.00 | $330.00 |
| 79 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 253 | $50.00 | $50.00 | $50.00 | $50.00 | $90.00 |
| 80 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 7 | $30.00 | $30.00 | $30.00 | $30.00 | $90.00 |
| 81 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 17 | $30.00 | $30.00 | $30.00 | $30.00 | $180.00 |
| 82 | (655.05010010) | 32 | $1,000.00 | $950.00 | $1,005.00 | $1,000.00 | $3,400.00 | |
| 83 | Cast Frame F3, Mountable Curb Box CM3 & Reticuline Grate G3 (655.0703) | EACH | 2 | $1,700.00 | $1,100.00 | $1,900.00 | $2,025.00 | $2,400.00 |
| 84 | (655.07030010) | 14 | $1,300.00 | $1,245.00 | $1,500.00 | $1,635.00 | $2,000.00 | |
| 85 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 87 | $1,650.00 | $1,500.00 | $1,930.00 | $2,025.00 | $2,400.00 |
| 86 | Manhole Frame & Grate (655.1201) | EACH | 4 | $500.00 | $1,400.00 | $720.00 | $735.00 | $800.00 |
| 87 | (662.60030008) | 9 | $1,000.00 | $55.00 | $300.00 | $1,395.00 | $3,000.00 | |
| 88 | (662.62000010) | 24 | $1,000.00 | $1,950.00 | $1,005.00 | $1,000.00 | $3,400.00 | |
| 89 | Adjust Existing Valve Box Elevation (663.33) | EACH | 30 | $150.00 | $55.00 | $135.00 | $60.00 | $3,400.00 |
| 90 | (663.51000004) | 21 | $1,200.00 | $90.07 | $1,865.00 | $1,200.00 | $6,400.00 | |
| 91 | (670.14480010) | 117 | $700.00 | $500.00 | $630.00 | $550.00 | $2,300.00 | |
| 92 | (670.90010008) | 16 | $2,540.00 | $2,537.00 | $2,537.00 | $3,000.00 | $3,000.00 | |
| 93 | (675.99000023) | 3,600 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 94 | (680.05010007) | 37 | $31,850 | $31,834 | $35,000 | $32,000 | $38,000 | |
| 95 | (680.05020007) | 30 | $4,810.00 | $4,807.00 | $5,000.00 | $5,100.00 | $5,800.00 | |
| 96 | (680.51111010) | 114 | $975.00 | $972.00 | $2,500.00 | $1,000.00 | $1,300.00 | |
| 97 | (680.520205) | LF | 120 | $29.00 | $29.00 | $29.00 | $29.00 | $35.00 |
| 98 | Inductance Loop Installation (680.54) | LF | 704 | $31.00 | $31.00 | $34.00 | $31.00 | $37.00 |
| 99 | Inductance Loop Wire (680.72) | LF | 2,816 | $2.00 | $2.00 | $2.00 | $2.00 | $2.40 |
| 100 | (680.80326110) | 4 | $6,525.00 | $6,502.00 | $6,502.00 | $6,500.00 | $8,000.00 | |
| 101 | (680.83200010) | LS | 1 | $10,000 | $7,250.00 | $8,700.00 | $45,000 | $21,000 |
| 102 | (680.97115011) | 4 | $6,525.00 | $6,502.00 | $6,502.00 | $6,500.00 | $8,000.00 | |
| 103 | (685.03130018) | 10 | $220.00 | $220.00 | $220.00 | $225.00 | $260.00 | |
| 104 | (685.07200110) | 458,108 | $0.72 | $0.72 | $0.75 | $0.75 | $0.86 | |
| 105 | (685.07200210) | 266 | $150.00 | $150.00 | $150.00 | $150.00 | $180.00 | |
| 106 | (685.07200310) | 405 | $175.00 | $175.00 | $175.00 | $175.00 | $210.00 | |
| 107 | (685.07200410) | 1,160 | $1.95 | $1.95 | $1.95 | $1.95 | $2.33 | |
| 108 | (685.07200510) | 51,294 | $2.40 | $2.40 | $2.50 | $2.40 | $2.87 | |
| 109 | (685.07200610) | 445,408 | $0.72 | $0.72 | $0.75 | $0.75 | $0.86 | |
| 110 | (685.07200710) | 14,400 | $1.95 | $1.95 | $1.95 | $1.95 | $2.33 | |
| 111 | (691.04000020) | 54,600 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 112 | Field Change Payment (FCP) (697.03) | DOL | 1,030,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 113 | Asphalt Price Adjustment (698.04) | DOL | 253,365 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 114 | Fuel Price Adjustment (698.05) | DOL | 9,126 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 115 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 116 | Mobilization (699.040001) | LS | 1 | $887,526 | $883,000 | $1,041,478 | $995,000 | $1,990,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of October 1, 2026. Compiled by Mirage Metrics.